COMMISSION
ORDER
DIVISION:
Planning & Research
COMMISSION
ORDER NUMBER:
PR-79-272
SUBMITTED
BY: C.I. MacGillivray
MEETING
DATE: 11-2-78
DISCUSSION/BACKGROUND:
Due to a
review of our Primary Road System records,
Iowa 78
begins on the Jefferson‑Washington County line approximately 3 ½ miles
northeast of Pleasant Plain, Iowa and travels easterly to the Jefferson‑Henry
County line at the west edge of Coppock, Iowa.
PROPOSAL/ACTION
RECOMMENDATION:
Locate
Beginning on
the Jefferson‑Washington County line at a point approximately 850 feet
east of the N ¼ Corner of Section 5‑T73N‑R8W, Jefferson County (S ¼
Corner of Section 32‑T74N‑R8W, Washington County); thence easterly
along the Jefferson-Washington County line following substantially the section
line of Sections 5, 4, 3, and 2‑T73N‑R8W to a point near the N ¼
Corner of Section 2‑T73N‑R8W, Jefferson County (S ¼ Corner Section
35‑T74N‑R8W, Washington County); thence in a southeasterly direction
through Sections 2 and 1‑T73N‑R8W to the Jefferson‑Henry
County line (west corporation line of the City of Coppock)
at a point approximately 880 feet south of the NE Corner Section 1‑T73N‑R8W,
Jefferson County (NW Corner Section 6-T73N-R7W, Henry County).
NOW,
THEREFORE: Be it resolved that the Iowa Department of Transportation approve
the location of
NOTE: To
become effective upon the adoption of this resolution.
COUNTY:
Jefferson-Washington
ROUTE:
APPROVAL
DATE: 10-3-45
Beginning on
the Jefferson‑Washington County line at a point near the N ¼ Corner
Section 2-T73N‑R8W; thence west along the Jefferson‑Washington
County line for a distance of about 3 miles to a point near the S ¼ Corner
Section 32-T74N‑R8W,
NOTE: Road construction completed and Maintenance
assumed 11/9/48 (Verbal report by Teal).
REVISED: 11-2-78
OFFICIAL
DESCRIPTION CHANGE
COUNTY:
ROUTE:
APPROVAL
DATE: 10-3-45
Beginning on
the Henry‑Jefferson County line at the west corporation line of the Town
of Coppock, at a point about 880 feet south of the
northeast corner Section 1‑T73N‑R8W, Jefferson County; thence in a
westerly and northwesterly direction for a distance of about 1 ½ miles to a
point near the N ¼ Corner Section 2‑T73N‑R8W, Jefferson County.
NOTE: Road construction completed and maintenance
assumed 11/9/48 (Verbal report by Assistant District Engineer Teal).
REVISED: 11-2-78