IaRTN Development Timeline
- January 2007 - Business model completed
- September 2007 - Proposals submitted
- October through November 2008 - Vendor network demonstrations
- December 2007 - Leica Geosytems issued “Intent to Award”
- January 2008 - Contracts executed
- January through June 2008 - Preliminary engineering
- July through October 2008 - Installation
- November through December 2008 - Acceptance testing
- January 2009 - Network training
- Feb. 1, 2009 - Network operational