2.10 PRECONSTRUCTION

2.11 PRECONSTRUCTION CONFERENCE

2.12 HAUL ROADS

2.13 STREAM CROSSINGS

2.14 WATER REGISTRATION AND PERMIT

2.15 WORKING & SHOP DRAWING - SUBMITTAL & REVIEW

Specification 1105.03 Working & Shop Drawings was added to the Specifications effective with the October 16, 2007 GS-01013. This Specification was developed to bring submittal and review requirements for working and shop drawings together in one section of the Specifications.

This Specification identifies the contractual requirements for submittal and review of working and shop drawings including identification of the primary review office. In addition, an Excel spreadsheet was developed which provides additional guidance information on work type, Specification Article, and distribution of approved documents. This spreadsheet is available at the following web site addresses under “Structures”.

http://www.dot.state.ia.us/construction/index.htm or
http://dotnet/construct/construct_body_index2.asp.

Working and shop drawing signature requirements are clarified in the following.

1. In the case of the contractor and their fabricator; working or shop drawing submittals do not need to be signed by a licensed Engineer if they are prepared from the information provided in the plans without any changes and the contract documents (ie: plans, specifications, etc.) do not state preparation must be by a licensed Engineer. If the working/shop drawing preparer proposes design changes in their submittal, that would require them to have the submittal prepared and signed by a licensed Engineer.

2. In the case of the reviewer who will approve the working/shop drawings; the same as above would apply. Also note that the review and approval does not relieve the submitter/contractor from responsibility as to the overall correctness of the submittal as stated in Article 1105.03.