9.50 PROTECTION, CURING, AND REPAIR
9.51 PREVENTION OF RAIN DAMAGE TO PLASTIC CONCRETE
At the preconstruction conference, it is important to emphasize that protective coverings and temporary forms must be available and that protection of fresh pavement from rain damage is the Contractor’s responsibility. Contractor should be advised to follow weather forecasts closely to prevent being caught unprepared in case of rain. Plastic film is preferred for surface and edge protection, since burlap alone in a heavy rain is insufficient to prevent access of water and subsequent pavement surface erosion.
When using concrete mixtures containing slag, the concrete often gains strength much slower than a mix without slag. This can be a problem when a rain event occurs. When slag is being used it is often necessary for the contractor to cover a significantly larger section of pavement to prevent rain damage on the surface.
The District should be notified when pavements are damaged by rain so an evaluation of damage can be made. Acceptance or rejection of damaged portions of the pavement will be based on extent of damage incurred as provided in Specifications 1105.04 and Construction Manual 2.53. Repair of damaged edges and surface may be considered, but extensively damaged pavement may require removal and replacement.
9.52 CURING OF KEYED AND DOWELED JOINTS
9.53 REPAIR OF DEFICIENT PAVEMENT
Rain damage varies considerably depending on rainfall intensity, duration, and protective measures taken by the Contractor. Covering and side forms placed by the Contractor afford sufficient protection to unhardened concrete in some cases. In other cases, surface and edges may erode to such a degree that removal and replacement of the slab is the only solution.
Guidelines follow for corrective measures that may be taken or used to restore damaged pavement to an acceptable condition. This instruction is not intended to cover the whole spectrum of deficiencies that may occur on a paving project during construction. Other proposed procedures or methods suggested by the contractor may be considered.
Recommended Repair Method
A. Rain Damage and Excessive Edge Slump
NOTE: When fresh concrete mix is added to plastic pavement for the purposes of replacing eroded mix or repairing excessive edge slump, the mix shall be vibrated to ensure proper consolidation.
2. After concrete has hardened:
B. Vehicle Traffic on Plastic Concrete
Remove and replace sections where rutting is severe.
Minor wheel track rutting may be repaired by using Class A bridge floor repair methods.
C. Random/Uncontrolled Cracking
Specification 2301.22 requires the Contractor to
repair random and uncontrolled cracks at no additional cost to the Contracting Authority. The
intent of this specification is to hold the Contractor responsible for cracking resulting from
the Contractor's operations. Methods of repair are to be submitted to the Engineer for approval.
Recommended methods of repair for random or uncontrolled cracks are included in
Appendix 9-6. Project specific circumstances may dictate that repair methods other than those listed in
Appendix 9-6 be allowed with approval of the Project Engineer.
D. Shrinkage Cracks
Remove and replace affected areas with new pavement in severe cases.
Minor cracks may be filled with pressure injected epoxy or repaired using Class A bridge floor repair methods.
E. Rough Pavement Sections
Surface variations, which exceed the specification smoothness requirements, require correction by
the Contractor. Surface correction shall be accomplished with approved diamond grinding equipment.
Use of milling machines, Roto Mill, Galion Scarifier, or other impact devices shall not be permitted.
F. Limitations
Necessary corrective measures on hardened concrete shall only be made after concrete attains age and
strength requirements in Specification 2301.31.
All required corrective measures shall be completed prior to coring for pavement thickness measurements.
Consultation with the Office of Construction is recommended before placing an HMA or bonded PCC overlay.
9.54 MUD BALL REPAIR
Correction of any discovered mud balls in a pavement surface shall be as follows:
If a severe problem with mud balls is suspected on a specific project, formal acceptance by Project Engineer should be delayed until the following spring. This will allow the winter freeze-thaw cycles and snowplowing activities to expose additional mud balls located adjacent to pavement surface. These newly discovered mud ball areas will then also require corrective measures as stated above.
9.55 COLD WEATHER PAVING AND PLANT OPERATIONS
The required cold weather protection needed during any given day should be mutually agreed upon between the Contractor and Project Engineer. A daily predetermined weather forecast should be used. For example, the low temperature forecast from the 4:00 pm local radio newscast could be the agreed upon temperature forecast. Once a decision is made as to the appropriate cold weather protection needed, any changes to the amount of protection needed must be agreed between the Contractor and Project Engineer to avoid potential claims.
Below -4o C (25o F), Specification 2301.19B requires four layers of burlap between layers of 1.0 x 10-4 mm (4 mil) plastic or an equivalent commercial insulating material approved by the Project Engineer. Equivalent materials include:
Specification 2301.19B also includes provisions for removal of the cold weather protection. Often a night or two of low temperatures is followed by several days of warmer temperatures. The provisions in 2301.19B provide a means for allowing the removal of cold weather protection when it will no longer be necessary. This is especially important in that it allows the Contractor to reuse covering materials more quickly rather than unnecessarily leaving them on pavement that no longer needs to be covered.
When cold weather protection is required, the Contractor will be reimbursed for extra work per Specification 2301.35. The reimbursement amount is the same value regardless of number of layers of protection required.
Cold Weather Plant Operation
Specification 2301.29 states that
concrete mixing and placement may be started when the air temperature is at least 1o C
(34o F) and rising. In the late fall season before the subgrade begins to freeze and
soil temperatures are still relatively warm, it is permissible to allow paving plant operations
to begin below 1o C (34o F) providing a decent weather forecast is predicted.
Paving plant operations basically self regulate during these conditions.
The intent is to maximize the remaining good paving weather still available in the fall. This provision is not intended to make a paving day out of one that is not, but to allow for as much concrete pavement placement as possible during a day forecast for good weather.
After the subgrade begins to freeze, the above provisions should be halted and specifications strictly enforced.
9.56 Curing Application
The curing shall be applied no later than one half hour after placement. In very hot, dry, windy conditions this is not soon enough. A price adjustment schedule is provided as Table C5 in Appendix 2-34C for areas of pavement where cure is not applied in a timely manner.