2108.01 DESCRIPTION.
Overhaul shall consist of the transportation of excavated material from roadway and borrow
excavation, from channel excavation, and from excavation for structures, a distance in
excess of the free haul limit specified for the particular kind of excavation involved.
2108.02 METHOD OF MEASUREMENT.
In determining what constitutes necessary haul, it will be assumed that material taken
from excavation will be deposited in embankment after having been hauled the minimum
possible distance. The haul distance for material moved from borrow outside the roadway
will be measured from the center of mass along the shortest route determined by the
Engineer to be feasible and satisfactory. The haul distance for material obtained from the
roadway, including interchanges and intersections, and placed inside the main roadway
will be measured along the center line of the roadway.
If pavement equipment crossings are designated by the Contractor as provided in Article 1105.12, B, and the contract provides for payment of overhaul on the material involved, overhaul on the material obtained within the roadway will be computed and measured along the center line as described above on the basis that material taken from excavation was deposited in adjacent embankment after having been hauled the minimum possible distance irrespective of the number and location of equipment crossings designated by the Contractor. The haul distance for material moved from outside the roadway will be measured along the shortest route determined by the Engineer as feasible and satisfactory, on the assumption that an equipment crossing was designated opposite the point where the haul road enters the roadway.
The limits of free haul will be determined from a mass diagram by fixing on the volume curve two points, one on each side of the neutral grade point, one in excavation and the other in embankment, so that the distance between them equals the free haul distance and the included quantity of excavation and embankment balance. All materials within the free haul limit will be eliminated from further consideration. The distance between the center of gravity of the remaining mass of excavation and the remaining mass of embankment, minus the free haul distance, will be the overhaul distance. The quantity of overhaul will be the product of the overhaul distance in stations multiplied by the number of cubic yards of materials hauled a distance greater than the free haul distance. (The quantity of overhaul will be measured in station meters. A station meter is defined as the product of an overhaul distance of 1 metric station multiplied by 1 cubic meter of material hauled a distance greater than the free haul distance.)
Unless otherwise provided in the contract documents, the free haul distance will be 1000 feet (300 m).
Payment for Overhaul will be for quantities shown in the contract documents in conjunction with quantities shown in the contract documents described in Article 2102.13 and under the conditions described therein. If Class 10 excavation quantities are changed, overhaul quantities will also be subject to change. If the overhaul change can be identified, it will be computed by the Engineer; if not, it will be adjusted by the ratio of adjusted quantities to original quantities shown in the contract documents of Class 10 excavation.
2108.03 BASIS OF PAYMENT.
The quantity of overhaul, measured as provided above, will be paid for at the contract
unit price per station yard (station meter) with the following exceptions:
Overhaul will not be paid for selected backfill material if it can be secured and used as shown in the contract documents. Should changes from the contract documents cause an increase or decrease in necessary haul, payment will be adjusted for such increase or decrease at the contract unit price per station yard (station meter).
If no unit bid price of a money value appears in the contract for overhaul, increased overhaul will be paid for at an unit price agreed to by the Contractor and Engineer, but not to exceed $0.02 per station yard ($0.09 per station meter).