SS-01017
(Replaces SS-01008)
SUPPLEMENTAL SPECIFICATIONS
FOR
Mobilization for Erosion Control
Effective Date
April 30, 2002
THE STANDARD SPECIFICATIONS, SERIES 2001, ARE AMENDED BY THE FOLLOWING MODIFICATIONS AND ADDITIONS. THESE ARE SUPPLEMENTAL SPECIFICATIONS AND THEY SHALL PREVAIL OVER THOSE PUBLISHED IN THE STANDARD SPECIFICATIONS.
01017.01 MOBILIZATIONS, EROSION CONTROL.
Prior to the Preconstruction Conference, the Contractor shall submit for approval an Erosion Control Implementation Plan (ECIP) for accomplishing all aspects of the erosion control work. The ECIP shall also include a description of any additions or modifications to the project. Deviations from the approved ECIP shall not be implemented without written permission from the Engineer. The Contractor and Engineer shall review and modify the ECIP as needed during the course of the project.
The ECIP shall include stages for erosion control work to
address the Contractor’s timetable and sequence for major activities on the project, including
the number of Mobilizations, Erosion Control, anticipated for the project. The number of
mobilizations shall consider, as a minimum, clearing and grubbing activities, the number
of earthwork balances for the project, sensitive areas requiring special consideration,
anticipated suspension of work, and compliance with the Pollution Prevention Plan (PPP).
The Contractor shall consider separate mobilizations needed for different crews performing
work such as silt fence, seeding, or ditch checks. However, multiple mobilizations shall
will not be paid for a single crew performing different items
of work that require the same equipment to be mobilized.
Only one mobilization will be paid for each stage of work
described in the ECIP. Within the scope of work defined for each single mobilization described
in the ECIP, additional movement due to weather delays or at the option of the Contractor shall
will not be counted as a mobilization.
Additional mobilizations not outlined in the ECIP must be approved by the Engineer. Only one mobilization will be paid for each stage of additional work approved by the Engineer.
The Contractor shall mobilize with sufficient labor, equipment,
and materials to perform the erosion control included in the ECIP. If the Contractor fails to
mobilize when erosion control work is needed to comply with the ECIP and the PPP, the Engineer
will direct the Contractor to mobilize within 72 hours of a written order. Notification shall
will be given to the Contractor.
If the Contractor fails to mobilize within such time period,
a deduction of $300.00 $750.00 per calendar day will
be made from money due under the contract, except when such time period is extended by the
Engineer.
This item shall not include work provided under the item of Mobilizations, Emergency Erosion Control.
01017.02 MOBILIZATIONS, EMERGENCY EROSION CONTROL.
The Contractor shall mobilize with sufficient labor, equipment, and materials, on the job site within 8 hours of a written order by the Engineer to install temporary erosion control items on an emergency basis. The written order by the Engineer will include a description of the required work. Only one mobilization will be paid for the work described in the written order.
Notification shall will
be given to the Contractor. If the Contractor fails to mobilize within such time period,
a deduction of $300.00 $1500.00 per calendar day will
be made from money due under the contract, except when such time period is extended by the
Engineer.
An emergency shall
will be considered to be a sudden occurrence of a
serious and urgent nature, which requires work not included in the contract or is
beyond normal maintenance of erosion control items and the mobilizations included
in the erosion control implementation plan. Emergency work requires immediate
mobilization and movement of necessary labor, equipment, and materials to the
emergency site, followed by the immediate installation of temporary erosion
control measures.
01017.03 METHOD OF MEASUREMENT.
A. Mobilizations, Erosion Control.
Mobilizations, Erosion Control, performed in conformance with the requirements of
this Supplemental Specification, will be measured as units and the quantity measured
for payment will be the number of such mobilizations in the approved ECIP and acceptably
performed, and any additional mobilizations approved by the Engineer and acceptably performed.
B. Mobilizations, Emergency Erosion Control.
Mobilizations, Emergency Erosion Control, performed in conformance with the requirements
of this Supplemental Specification, will be measured as units and the quantity measured
for payment will be the number of such mobilizations directed in writing by the Engineer
and acceptably performed.
01017.04 BASIS OF PAYMENT.
Payment will be provided per Article 1109.03, B, 1, of the Standard Specifications at the unit prices stipulated in this Supplemental Specification. Mobilization for Erosion Control costs shall not be included as part of the contract item for "Mobilization" described in Section 2533 of the Standard Specifications.
A. Mobilizations, Erosion Control.
The quantity will be paid for at the contract unit price of $400
$500.00 each for Mobilizations, Erosion Control,
which price shall be full compensation for the staged movement of labor, equipment,
and materials; and for all labor, tools, equipment, and incidentals necessary to
complete the movement.
Individual erosion control items provided for in the
contract, and acceptably furnished and placed under the item of Mobilizations,
Erosion Control, will be paid for separately at the contract unit price for the
item or items.
B. Mobilizations, Emergency Erosion Control.
The quantity will be paid for at the contract unit price of $1000 each for
Mobilizations, Emergency Erosion Control, which price shall be full compensation
for movement of labor, equipment and materials; and for all labor, tools, equipment,
and incidentals necessary to complete the movement.
Individual temporary erosion control items provided
for in the contract, and acceptably furnished and placed under the item of
Mobilizations, Emergency Erosion Control, will be paid for separately at the
contract unit price for the item or items.