PCC NON-STRUCTURAL & MISCELLANEOUS - FIELD AND PLANT SAMPLING AND TESTING GUIDE (See Specifications for Complete Details.) |
||||
|
|
Field Acceptance |
Plant Acceptance |
|
Article |
Work Type |
Air & Slump |
Gradation QC |
Gradation Verification |
|
|
|
|
|
Base Repair |
1/30 yd3 (1) |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
PCC Base |
1/700 yd3: 1/100 yd3 RM |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Base Widening |
1/700 yd3: 1/100 yd3 RM |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Detour Pavement, 3 yrs or less |
n/a |
n/a |
n/a |
|
seal course |
n/a |
n/a |
n/a |
|
Curtain Wall |
1/30 yd3 |
n/a |
n/a |
|
Pipe collars |
n/a |
n/a |
n/a |
|
Catch basins, abandonment,collars |
n/a |
n/a |
n/a |
|
Flowable Mortar |
n/a |
S/T for Mix Design only |
n/a |
|
Revetment Grout |
1/half day |
S/T for Mix Design only |
n/a |
|
|
Fabric Formed Revetment |
1/half day |
S/T for Mix Design only |
n/a |
Sidewalks |
1/100 yd3 (1) |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Trails |
1/100 yd3 |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Curb & Gutter |
1/100 yd3 (1) |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Driveways |
1/100 yd3 (1) |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Railroad Approach Sections |
1/100 yd3 (1) |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Fence construction |
n/a |
n/a |
n/a |
|
Type A and B |
n/a |
n/a |
n/a |
|
Patching (Full depth), rumble strip |
1/30 yd3 (1) |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Patching (Partial depth) |
1/30 yd3 (1) |
S/T 1st week, S/T 1 per month (3) |
S/T 1/project (3) |
|
Thrust blocks |
n/a |
n/a |
n/a |
|
(1) If less than 20 yd3/ day, the engineer may waive air testing if inspection is not available and producer has exhibited consistency in prior placements (3) Sampling and testing rate if no other concrete supplied. Use structural or paving test results to cover non structural concrete items. |