TABLE OF RESPONSIBILITY |
||||
QUALITY ACTION |
CPI & QMA |
SMALL QTY. |
||
General |
|
|
||
Use of Qualified Labs & Certified Technicians |
CONTR/RCE |
CONTR |
||
Use of Certified Labs & Qualified Technicians |
DME/CTRL |
DME/CTRL |
||
Preparation of the Job Mix Formula (JMF) |
CONTR(2) |
CONTR(2) |
||
Approval of the JMF |
DME |
DME |
||
Calibration of the Plant |
CONTR |
CONTR |
||
Monitoring of Plant Operations |
DME/RCE(1) |
DME/RCE(1) |
||
Inspection of Plant Operations |
CONTR(1) |
CONTR(1) |
||
Asphalt Binder |
|
|
||
Direct & Witness Verification Sample of Asphalt Binder |
RCE/DME(3) |
NA |
||
Sample Asphalt Binder |
CONTR(3) |
NA |
||
Secure Verification Sample of Asphalt Binder |
RCE/DME |
NA |
||
Transport Verification Sample of Asphalt Binder |
CONTR/RCE |
NA |
||
Run & Report Verification Sample of Asphalt Binder |
DME/CTRL |
NA |
||
Aggregate |
|
|
||
Direct & Witness Verification Sample of Combined Aggregate |
RCE(4) |
NA |
||
Sample Combined Aggregate |
CONTR(4) |
CONTR(4) |
||
Direct & Witness Splitting of Combined Aggregate Sample |
RCE(5) |
NA |
||
Secure Verification Sample of Combined Aggregate |
RCE |
NA |
||
Transport Verification Sample of Combined Aggregate |
CONTR/RCE |
NA |
||
Run & Report QC Tests on Combined Aggregate Gradation |
CONTR(5) |
CONTR(5) |
||
Run & Report Verification Tests on Combined Aggregate Gradation |
DME/RCE(5) |
NA |
||
Report Validation per IM 216 on Combined Aggregate Gradation |
DME/RCE |
NA |
||
Obtain & Transport Verification Samples of Coarse Aggregate Quality |
DME(4) |
NA |
||
Run & Report Verification Tests on Coarse Aggregate Quality |
CTRL |
NA |
||
Loose Hot Mix |
|
|
||
Determine Loose Hot Mix Paired Sample Frequency/Location |
RCE(3) |
CONTR |
||
Direct & Witness Verification Sample of Loose Hot Mix |
RCE(3) |
NA |
||
Sample Loose Hot Mix Paired Samples |
CONTR(3) |
CONTR(3) |
||
Secure Verification Sample of Loose Hot Mix |
RCE |
NA |
||
Transport Verification Sample of Loose Hot Mix |
CONTR/RCE |
NA |
||
Run & Report QC Tests on Loose Hot Mix Samples |
CONTR(1) |
CONTR(1) |
||
Run & Report Verification Tests on Loose Hot Mix Samples |
DME(1) |
NA |
||
Report Validation of Hot Mix Tests |
CONTR(1) |
NA |
||
Evaluate Test Results/Take Action when Validation Fails |
DME |
NA |
||
Compacted Hot Mix |
|
|
||
Determine Density Coring Frequency/Location |
RCE(3) |
RCE(3) |
||
Direct & Witness Coring & Transport to QC Lab |
RCE(3) |
RCE(3) |
||
Obtain Core Samples & Prepare Samples at the QC Lab |
CONTR |
CONTR |
||
Run Density Testing on Cores |
RCE(3) |
RCE(3) |
||
Record Density Testing Measurements on Cores |
RCE(3) |
RCE(3) |
||
Report Density Testing Results on Cores |
CONTR(1) |
CONTR(1) |
||
Revisions |
|
|
||
Adjust Production to Maintain JMF Targets |
CONTR |
CONTR |
||
Report Plant Adjustments |
CONTR(1) |
CONTR(1) |
||
Approve Revisions to JMF Targets |
DME |
DME |
||
Shut Down Production when Required |
CONTR |
CONTR |
||
NOTES: |
ABBREVIATIONS: |
|||
(1) Must be done by Certified Level I HMA Technician |
CPI = Certified Plant Inspection |
CONTR = Contractor |
||
(2) Must be done by Certified Level II HMA Technician |
QMA = Quality Mgmt. of Asphalt |
DME = District Materials |
||
(3) Must be done by Certified HMA Sampler |
RCE = Project Engineer |
CTRL = Central Materials |
||
(4) Must be done by Certified Level I Aggr. Technician |
|
|
||
(5) Must be done by Certified Level II Aggr. Technician |
|
|
||