INSTRUCTIONS FOR COMPLETION OF

PCC PAVING & STRUCTURAL REPORTS

 

The new reporting process does not include Mobile Mixer information. Use the following forms and reports when using a Mobile Mixer:

 

Form E 115                                Air & Slump Record

Form E 120                                Mobile Mixer Data Record

Report #820180                         Gradation Test

Report #821297                         Nuclear Density of Plastic PC Concrete

Report #820020                         Mobile Mixer Calibration

 

Project No.

Enter the project number listed on the plans.

 

Plant Name

Enter the name of the ready mix plant and location for structural concrete. Enter the approximate location of a paving plant set up by a contractor.

 

Example:         Croell - Waverly (Ready Mix)

2 miles NW of Waverly (Paving Plant)

 

Contractor/Sub

A group of people or a company must perform the work being done, either a prime or sub contractor. Enter the name of the contractor performing the work. If it is a subcontractor, list this after the contractor name.

 

Weather

Enter a brief description of the actual weather conditions at the paving plant. Weather conditions are not required for structural concrete (Ready Mix).

 

Contract ID

Enter the nine-digit contract number listed at the top of a contract. This is not the five-digit accounting ID number listed with the project number.

 

County

Enter the county listed on the project plans.

 

Temperatures, Min. & Max.

An air temperature shall be recorded early in the morning for the minimum and around mid-afternoon for the maximum. Take the temperatures in a shaded area, otherwise they are meaningless. Temperatures are not required for structural concrete, except bridge decks.

 

Report No.

Start with the number 1 at the beginning of work for each project. The ending report number shall coincide with the last day each item is completed for paving and the last week for structural. Do not restart the report sequence if the project carries over to the next year.

 

Example:         (Paving)           16 days of 10.5 inch slip form paving - report 1 through 16.

            (Ready Mix)     8 weeks of concrete on Des. 1290 - report 1 through 8.

 

Date This Report

Enter the date the concrete is placed for each day of paving. Enter the last day of the workweek for structures (normally the Saturday date).

 

Date of Last Report

Self-explanatory.

 

Design No.

Enter the design number of the structure where the concrete is being placed on each project. Leave this space blank on paving projects.

 

Check Mix (Central or Ready)

Place an “X” in the appropriate box provided indicating how the concrete is being produced.

 

Check Usage (Paving, Structural, Incidental, Patching)

Place an “X” in the appropriate box provided to indicate the type of work where the concrete is used.

 

Date (Mo./Day)

This column is only used for Ready Mix concrete applications. Enter the month and the date for each day of production during the week.

 

Example:         5/24, 7/01, 12/03, etc.

 

Mix Number

Enter the mix number being used that is listed in the proportion tables of IM 529.

 

Location- Station (Beg./End/Dir)

Enter the beginning and ending station for concrete placed daily by mix. Enter the direction (N, S, E, W) for divided sections or B for 2-lane sections. For structural concrete enter the unit placed (Example: pier, cap, footing, deck). Enter item placed for other work. (Example: sidewalk, drive) The grade inspector will provide the location or item placed to the plant inspector.    

 

Batched

Enter the total cu. yds. batched for each mix for a paving plant. Enter the total cu. yds. batched for each unit poured for structures.

 

% Of Est. Used

Enter the percent of estimated concrete used. The grade inspector will provide the % of estimate used ((cubic yards used / cubic yards estimated) X100) to the plant inspector

 

Fine, Intermediate & Coarse Aggregate (Moisture)

Enter the percent moisture once in the morning and once in the afternoon for paving projects. Enter the percent moisture for each unit poured on structures.

 

Fine, Intermediate & Coarse Aggregate (T203 sp gr)

Enter the specific gravity for each aggregate listed in the T203 source tables.

 

Fine, Intermediate & Coarse Aggregate (Dry Wt.)

Enter the weight  of each aggregate calculated by absolute volumes.

 

Actual Quantities Used Per cu. yds. (Pounds)

Cement     Enter the pounds of cement calculated by absolute volumes.

Fly Ash     Enter the pounds of fly ash calculated by absolute volumes.

GGBFS     Enter the pounds of ggbfs calculated by absolute volumes.

Fine           Enter the actual pounds of fine aggregate adjusted by moisture content.

Inter.         Enter the actual pounds of intermediate aggregate adjusted by moisture content.

Coarse      Enter the actual pounds of coarse aggregate adjusted by moisture content.

In Agg.      Enter the calculated difference between the actual weights and the dry weights of all aggregates.

Plant         Enter the average pounds of water added at the plant for each cu. yd.

Grade        Enter the average pounds of water added on the grade (if permitted by specification).

 

Avg. W/C Ratio

Enter the ratio of total water, including water in the aggregates and water added on the grade, in one cu. yd. divided by the total sum of cement, fly ash, and ggbfs in one cu. yd., report to three decimal places.

 

CPI Gradations

This section of the report is for reporting the Certified Plant Inspector gradation test results for the coarse and fine aggregates being used in the mix.

 

Batched (Today or Week)

Place an “X” under the Today column if the report is being submitted daily (paving).

Place an “X” under the Week column if the report is being submitted weekly (structures).

 

Concrete Batched

Enter the total cu. yd. of concrete batched under the appropriate column. Paving plant totals are normally under the Today column; structural concrete totals are normally under the Week column.

 

To Date Total

Enter the running total for both concrete and cement.

 

Air Entraining (Air Ent.)

Enter the brand name or source, average rate per cu. yd., and lot number.

 

Water Reducer (Wat. Red.)

Enter the brand name or source, average dosage rate, and lot number.

 

Retarder

Enter the brand name or source, average dosage rate, and lot number.

 

Calcium Chloride (Cal. Chlor.)

Enter the brand name or source, average dosage rate, and lot number only when added at the plant site.

 

Superplasticizer (Superplas.)

Enter the brand name or source, average dosage rate, and lot number.

 

Concrete Treatment

Place an “X” directly behind Ice, Heated Water, or Heated Materials, if one or more are used. If ice is used to cool the mix, enter the pounds of ice per cu. yd.

 

Cement

Enter the cement type, specific gravity, and source. See IM 401 for the actual source name.

 

Fly Ash

Enter the type and specific gravity and source. See IM 491.17 for the actual source name.

 

Example:         Chillicothe and ISG Headwaters are not source names.

            Ottumwa is the source name.

 

Rock

Enter the T203 A number, and gradation number.

 

GGBFS

Enter the grade, specific gravity, and source. See IM 491.14 for the actual source name.

 

Sand

Enter the T203 A number, and gradation number.

 

Intermediate

Enter the T203 A number.

 

Remarks

Enter delays, which may take place. Enter description of noncomplying test results.

 

CPI

Enter the Certified Plant Inspector name and certification number.

 

Monitor

Enter the plant monitor name and certification number.

 

If using the computer spreadsheet, most of this information will be entered on the Project Information and Mix Information sheets and automatically transferred to the Report. For QMC and BR mixes, the combined gradation will be calculated from aggregate percentages entered in the Mix Information Station From and To, Totals to Date Cement and Concrete, and Remarks will be entered directly on the Report.

 

The next page is an example of a completed Paving Plant Report.