PCC PAVING - FIELD AND PLANT SAMPLING AND TESTING GUIDE

(See Specifications for Complete Details.)

 

 

 

 

Field Acceptance

Plant Acceptance

 

Article

Work Type

Air & Slump

Gradation QC

Gradation Verification

 

 

(No slump for slipform paving)

 

 

2122

PCC Shoulders

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2301

PCC Pavement

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2301

PCC Pavement - QMC

1/700 yd3: 1/100 yd3 RM

S/T 1/1500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3, Test 2/week,

If <500 yd3/day, S/T 1 wk

2301

Bridge Approaches,

Gores, tapers, radiuses

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

n/a

2302

PCC Widening

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2310

PCC Overlay

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2310

PCC Overlay - QMC

1/700 yd3: 1/100 yd3 RM

S/T 1/1500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3, Test 2/week,

If <500 yd3/day, S/T 1 wk

(1) If less than 20 yd3/ day, the engineer may waive air testing if inspection is not available and producer has exhibited consistency in prior placements

(3)  Sampling and testing rate if no other concrete supplied. Use structural or paving test results to cover non structural concrete items.

(4)  If less than 500 yd3 per day / intermittent construction continues for more than two weeks, obtain verification samples weekly and test 20% of the samples obtained.