10.40 WETLANDS AND SECTION 404 PERMITS - INTRODUCTION
A good rule of thumb is any project that includes new ROW purchase and/or impacts an aquatic resource should be reviewed for Section 404 requirements.
10.41 WETLANDS – DEFINITION AND REGULATION
Wetlands are protected in Iowa by federal laws (33 CFR Part 323), executive orders (EO 11990), state laws (§314.23-24), and Iowa DOT policy (PPM 500.03).
Wetlands are regulated in Iowa by the U.S. Army Corps of Engineers (Corps), who authorize projects in compliance with Section 404 of the Clean Water Act; U.S. Environmental Protection Agency (EPA), who enforces Section 404; and the Iowa Department of Natural Resources (DNR), who issue Section 401 Water Quality Certifications for all Section 404 Permits. In addition, the U.S. Fish & Wildlife Service, Natural Resource Conservation Service, Federal Highway Administration, and State Historical Preservation Officer all play important roles in the wetland permitting process.
10.42 PERMIT PROCESS
The Corps issues two types of Section 404 permits, General and Individual. General Permits include Nationwide Permits and Regional General Permits and are issued periodically for categories of activities that result in only minimal adverse affects to the aquatic environment. Individual Permits are issued for projects with more significant adverse impacts on a case-by-case basis. Individual Permit authorizations are based on a public interest review that includes a comment period for resource agencies and the public. Section 401 Water Quality Certifications are issued for the entire Nationwide Permit program as well as for specific Regional General Permits. Individual Permits require project specific Section 401 Water Quality Certifications.
Section 404 Authorization is requested by preparing either a Pre-Construction Notice, in the case of a General Permit, or an Individual Permit Application. Both documents contain project concept, locations, history, schedule, plans, cross-sections, wetland avoidance and minimization efforts, wetland delineations and other detailed site data, a proposed mitigation plan, and many other types of information.
General Permits are reviewed in-house by the Corps and are typically issued within 45 days of submittal. Individual Permits require 90-120 day review time, including a 30-day Public Notice period.
A Section 404 authorization contains requirements and conditions specific to the proposed construction project. It is imperative that the Iowa DOT field construction staff AND the contractor are aware of all permit requirements and work together to ensure compliance. Failure to comply with a Section 404 permit may result in an enforcement action against the Department including a cease and desist order to stop all project work and fines of up to $25,000 per day until compliance is met. Corps and DNR inspectors may and do visit construction projects without prior notice.
Upon issuance of a Section 404 authorization, the Water Resources manager will prepare a cover memo highlighting any issues of particular concern and forward the memo and 404 permit to the District Construction Engineer. The Office of Contracts may include the 404 permit in the contract documents at the request of the Office of Location and Environment for environmentally sensitive projects. Copies of the permit should be kept at the primary project site, mitigation project site and the Construction Residency at all times until completion of both the primary project and the mitigation site. The memo and permit can also be found in the Electronic Records Management System.
Other types of permits may be required for any given project and are generally administered separately. Other permits may include floodplain, sovereign lands, storm water (NPDES) and a structure permits.
10.43 MITIGATION
Compensatory mitigation is required for most projects requiring Section 404 authorization. Typically, a proposed site and development concept is identified in the permit application or pre-construction notice. Following authorization, the mitigation project is designed by OLE or OLE's wetland consultants and let as a separate project. In some cases, mitigation may be accomplished in conjunction with the primary project by modifying a project feature such as a stream crossing, ditch, or borrow. The Corps requires that mitigation must be completed prior to or concurrent with wetland fill activities along of the primary project.
Mitigation projects may be restorations of previously drained wetlands, creations of new wetland areas, enhancements of degraded areas, or preservation of resources likely to be developed. Mitigation may also include improvements to streams or other resources.
Mitigation projects may include site grading, construction of water control structures, removal of existing drainage features, planting of both uplands and wetlands with native seed, live plugs, and/or trees. It is important for the contractor to understand that mitigation projects often require work in wet soil conditions.
One of the most critical elements for mitigation success is construction to the proper elevations. This ensures that the water necessary to sustain the mitigation wetlands will be available as designed. Sometimes, it is generally desirable to leave finish grades rough and uneven with shallow and variable slopes and to create undulating bottom surfaces with diverse water depths. Removal of tile from wetland areas works best if the tile line is removed in its entirety. Wetland seeding is most successful when performed in the spring time on moist soil. These types of important activities will be identified in project plans; therefore, plan reference notes should be carefully followed.
The Water Resources Section in the Office of Location and Environment have biological and engineering staff available to discuss wetland mitigation projects. When in doubt, please check with the Water Resources Section.
10.44 MITIGATION AS-BUILT PLANS
Projects utilizing consultant inspection will likely include mitigation Post Construction preparation as a work order task.
10.45 MITIGATION MONITORING
10.46 PRECONSTRUCTION CONFERENCE
10.47 COMPLETED WORK CERTIFICATION FORM
10.48 CONSTRUCTION WORK NOT SHOWN ON PLANS