11.40 REINFORCEMENT
Clearances and respective tolerances for bridge deck reinforcing are defined in Construction Manual 11.41.
Field welding of deformed reinforcing steel is not permitted without the approval of the Construction or Bridge Engineer as stated in Materials I.M. 558, Field Welding Inspection Manual.
11.41 PLACEMENT AND CHECKING (BRIDGE FLOORS)
Four dimensions must be given special attention when checking placement of bridge
slab reinforcing:
1. Slab thickness
2. Clearance of bottom reinforcement from bottom of slab
3. Distance from bottom of slab to top of top mat of reinforcement
4. Cover over top mat of reinforcement
Slab Thickness
This shall be the nominal slab thickness shown on the plans with a tolerance
of minus zero and plus 19 mm (3/4 inch).
Clearance of Bottom Reinforcement
The clearance of bottom of reinforcement from bottom of slab shall be the
nominal clearance shown on the plans with a tolerance of minus 3 mm (1/8 inch)
and plus 6 mm (1/4 inch). Contractors must provide an adequate number of bolsters
and/or bar chairs of suitable height and strength to maintain clearance within
this range.
Clearance of Top Mat Reinforcement
Distance "d" is the slab thickness minus specified concrete cover over the top
steel.
When all top reinforcing is of the same diameter, the nominal "d" distance is to be maintained with a tolerance of minus 6 mm (1/4 inch). The nominal "d" distance may be increased as long as the requirements for slab thickness and cover over top reinforcement are met. Contractors must provide an adequate number of bar chairs of suitable height and strength to maintain the distance within this range of tolerance.
When more than one diameter of top reinforcement bar is used, the above described "d" distance shall be maintained for the larger diameter bar. The distance may be decreased for the smaller diameter bar by an amount not to exceed the difference in the bar diameters.
Cover Over Top Mat of Reinforcement
Minimum allowable cover shall be the nominal cover shown on the plans minus 3 mm (1/8 inch).
Maximum cover will be controlled by maximum allowable slab thickness.
Slab Bridges
Some slab bridges have the bottom of slab formed in a straight line from
edge to edge, while the top of slab is crowned. This results in a variable
slab depth of a variable distance from bottom of slab to top of reinforcing.
The contractor will have to provide variable height bar chairs to maintain the
proper positioning for top reinforcing for these slab bridges.
Special Attention Areas
A. Tie-downs and Supports
Specifications 2404.07 requires that bottom and top mat reinforcing be independently supported. The support system spacing shall not exceed 4 feet (1.2 m) in each direction for bolsters or continuous high chairs and 3 feet (0.9 m) in each direction for individual high chairs. These supports should also be placed near the ends of the bridge and under bars near the curbs to ensure bar position and clearances are maintained.
B. Epoxy Coated Bar
C. Clearance Check
D. Checks During Placement
When the slab is of deficient thickness or cover, corrections must be made immediately. Deficiencies in thickness or cover may be a result of incorrect rebar placement, settling of the finish machine supports, or incorrect/change in the finish machine setting. For deficiencies in thickness or cover that exceed 13 mm (1/2 inch), contact the Office of Construction to discuss need for additional action.
E. Cleaning Forms and Steel
11.42 EPOXY COATED REINFORCEMENT
Care and Handling
Epoxy coated bars are subjected to many quality control tests and
inspections prior to leaving the supplier's facility. However, from that
point forward, careless handling and construction practices can cause
excessive coating damage. Contractors should be strongly encouraged to
exercise care in handling, storage, and placing of epoxy coated bars.
If problems are noted after delivery, the inspector is to contact the
District Materials Office.
By specification, epoxy coated bar is a certified product when delivered
to our projects. (EXCEPTION: Epoxy coated deck steel is a certified product,
and is accepted on a field assurance/acceptance test.)
A. Handling
B. Storage
C. Placing
After epoxy coated bars are placed, walking on the bars by construction personnel should be held to a minimum. Bars in high traffic areas or runways for concrete placement should be protected with plywood or other suitable material. Concrete placement equipment shall not be placed on, or supported by, any reinforcing steel.
Bar supports and tie wires for epoxy coated reinforcement shall be coated with epoxy, nylon, or plastic. (Refer to Specification 2404.07. Also refer to Materials IM 451.01 for approval of chairs and bolsters.)
Field Inspection
There are two aspects to field inspection. First, complete the requirements
of Materials I.M. 204 for assurance/
acceptance testing. When the largest bar diameter used for deck steel is delivered,
contact the District Materials Engineer for sampling and testing. The Second
aspect is primarily concerned with evaluating the physical condition of all epoxy coating.
Epoxy coated bars should be inspected for damaged coating:
A. Damage Evaluation and Repair
B. Bent Bars
C. Fading of Color
D. Damaged Ends
Repair of Damaged Coating
When damaged coating must be repaired, the patching or touch-up material should
be applied in strict accordance with the instructions furnished by the manufacturer.
Generally, surface preparation consists of a THOROUGH manual cleaning
of damaged areas, including complete removal of: (1) unbonded epoxy and (2) all rust.
Cleaning is usually accomplished with a power driven wire brush, hand steel brush,
and/or emery paper. Care should be exercised during preparation so that excessive
sound epoxy is not damaged. Acceptance criteria for epoxy repair and touch-up materials
is in accordance with the original epoxy resin manufacturer's recommendations.
[Refer to Specification 4151.03, Paragraph E
]. Note: Coating patch materials shall be of organic composition and shall be a
two-component liquid properly mixed that hardens to a solid form upon curing. Check
Materials IM 451.03B - Appendix B
for approved touch-up materials.
NOTE: Repaired areas do not have as much corrosion or abrasion resistance as factory-applied coatings.
11.43 CAGE STEEL (DRILLED SHAFTS)
General items to look for are:
11.44 SPLICING
Example: During removal of an existing curb on a bridge deck widening project, existing rebar is either cut with the saw or broken during concrete demolition. In this case additional demolition is needed to provide a lap development length.
Currently, several couplers are manufactured which can be used to mechanically splice rebar. Mechanical splicing for the above conditions may be approved unless the plans exclude their usage. Mechanical splices, for field approval, shall develop 125% of the rebar's yield strength. Consideration for splice usage must be initiated by the contractor. The project engineer is to forward that request to the Office of Construction for review.
Splice Approval
The use of mechanical splices will only be permitted when specified in the plans
or approved by Office of Bridge Design. When mechanical splices are permitted
Materials I.M. 451 Appendix E
provides the basis for acceptance and an approved list of mechanical splicers.
When proposed mechanical splices are not on the approved list, the project engineer shall require three sample splices to be made using the same equipment and process proposed for the project. These samples must be at least 450 mm (18 inches) long and have the splice approximately centered in the sample. Samples will be submitted to the Office of Materials for testing prior to field approval. If the samples fail to develop 125% of the rebar's yield:
Bottom Line is mechanical splicing has been used successfully in many projects from deck widening to drilled shafts to new construction. Mechanical splicing shall be used only if preapproved or detailed on the plans. For mechanical splices not on the approved list, three mock-up splices must be submitted for testing. (The testing is to assure proper field methods have been used to develop a reliable splice.)
Descriptions of currently approved mechanical splices is provided in Materials I.M. 451 Appendix E.
11.45 PAYMENT FOR REINFORCING STEEL
Some fabricators have chosen to calculate the bend distance and thereby shorten the length of bar required. If they use this length to calculate the mass (weight), it will be less than plan quantities. So long as this mass (weight) is within 1 percent of the plan quantities, no further documentation is necessary. (Refer to Specification 2404.09.)