11.60 DECKS AND OVERLAYS
11.61 DECK OVERLAY PREPARATION
The surface, once cleaned, must remain clean until the grout and concrete is placed. There have been cases where the prepared deck surface has become contaminated during the decking operations by concentrated traffic of vehicles transporting the concrete. This is especially true when the skid-steer type loaders are used to transport mix. The deck surface is contaminated by the abrasive action between the concrete surface and the rubber tires, and also from oil and other foreign material tracked in from off the bridge. Contamination can be recognized by discoloration or oil on the deck surface. Contamination is especially noticeable in the wheel paths used by the vehicles.
Core specimens taken and tested for bond strength from areas as mentioned above showed a marked decrease in bond strength between the interfaces.
To prevent the cleaned deck surface from being contaminated by traffic, the contractor shall cover any prepared surface with sheets of plywood, multiple layers of plastic, or other suitable material. To ensure a clean surface prior to placement of the overlay system, areas which become contaminated shall be resandblasted followed by an air blast.
Class A Floor Repair
Removal for Class A Bridge Floor Repair will no longer be determined by electrical
corrosion detection during construction. Unless plans specify definite limits for Class
A repair, repair removals will include only the actual spalled and hollow areas found
during construction.
District Maintenance Engineers or the Office of Bridge Maintenance and Inspection will
supply a preliminary audible and/or visual survey to the Office of Bridges and Structures,
who will place that information on a plan sheet. On special occasions, an electrical
corrosion detection plot may be requested.
Unless the Office of Bridge Maintenance and Inspection or Office of Bridges and Structures
determines a need for adjustment, plans will show one plot based on the audible and visual
survey. The plan diagram will be entitled "Survey Plot" with date of survey given. Plan note
will be as follows:
In many instances the re-bars have been reduced in cross section area by rust action. Any further reduction in diameter of the bars by grinding results in a decreased load carrying and load distribution capacity of the floor system.
Therefore, the above method of concrete removal in Class A areas shall not be permitted. All methods of concrete removal must be submitted to the project engineer for approval. Other methods, which may utilize the Gallion Scarifier in removing concrete without damaging steel, may be submitted to the project engineer for approval. It is recommended that removal practices be discussed at preconstruction meetings. Emphasis needs to be placed on how the contractor will prevent steel damage.
B. Specification 2413.05, Paragraph B, states in part, "... at the direction of the engineer limited areas of removal greater than 50% of the floor thickness may be removed" without continuing removal to full depth. These limited areas would be included in measurements as though "Class A Bridge Floor Repair."
"Limited areas" have been defined as maximum of 1 m2 (9 square feet). Deteriorated concrete must be removed even if below the reinforcing steel. Areas having more than 1 m2 (9 square feet) and more than 50% of the deck thickness in one location should be totally removed as Class B bridge floor repair. It was not the intent of the specifications to pay extra for these small normally isolated areas of over depth Class A floor repair.
For concrete slab or voided slab bridges, the Office of Bridges and Structures shall be contacted to obtain guidance and approval for any removal below the top mat of reinforcing steel. Generally, repairs requiring removal below the top mat will be restricted to longitudinal strips not exceeding 1 meter (3 feet) in width. This restriction is to ensure that structural integrity of the deck section is maintained. The Office of Bridges and Structures will provide project specific guidance based on field determined conditions of the bridge deck.
Work on Adjacent Lanes
Specification 2413.10 permits limited
work on an area adjacent to a previously placed lane during the 72-hour curing period. Basically,
any operation which interferes with the curing process shall be for a minimal time only in a
limited affected area. Operations that could potentially damage previously placed surface are
restricted as noted in Specification 2413.10.
For instance, this does not mean that the contractor can fold back a strip of burlap for the entire length of a lane prior to sawing the outer 150 to 225 mm (6 to 9 inch) width strip of the previously placed overlay and then replace the burlap several hours later. This work can be accomplished by folding back a strip of burlap several meters (feet) in length just ahead of the saw and replacing the wet burlap immediately after sawing.
Obtaining a continuous wet cure, especially at an early age in the curing period, is EXTREMELY important in securing a sound durable deck overlay.
Should the 72 hour wet curing process be interrupted for more than one hour (accumulated time), the affected overlay area should be removed and replaced at contractor's expense.
Rule-of-Thumb:
If work cannot be completed within an hour exposure period, the contractor shall be
required to accomplish preparation work after curing period has expired.
11.62 SEQUENCE OF POURING
Bridge plans require a placement sequence as indicated by the encircled numbers on the concrete placement diagram in the plans. (Refer to Example Concrete Placement Diagrams, Appendix 11-19.) Note that positive moment sections are placed first, with the adjacent negative moment sections placed during subsequent pours. Check for plan notes on both noncontinuous and continuous placements that may indicate specific intervals between pouring adjacent positive and negative moment sections.
Check the "concrete placement diagram" sheet because some projects will state that no alternate placement sequences will be allowed. Others will note:
In cases where plans allow alternates, those requests shall be forwarded by the project engineer to the Office of Construction for evaluation and approval. All requests for alternatives need to include:
A. Sequence of Placement
When plans allow alternatives, the contractor needs to request a change and choose
an alternate placement sequence. The project engineer must then determine if that request
meets requirements of the concrete placement diagram shown on the plans. Example diagrams
shown in Appendix 11-19 are the sequences normally
shown on the plans. Other sequences are shown when special conditions exist. Review assures
that a contractor's request does not violate placement sequence required.
B. Haul Time and Placement Rate
Project engineers must review the contractor's estimate of haul time and placement rate to
determine if times are realistic. If estimates appear unrealistic, times must be adjusted to
practical values. Haul time must include time elapsed from batching (addition of mix water)
to placement of concrete in the forms. Placement rate should be measured in cubic meters
(cubic yards) of concrete placed per hour.
With present placement equipment, approximately 50 cubic meters (cubic yards) per hour should be the maximum anticipated to calculate retarder needed for completion of the placement.
C. Maximum Air Temperature
No continuous placement is to be attempted when temperature forecast is above
30oC (85oF). This value is still being evaluated on a yearly
basis. As each new season begins, be sure to confirm the maximum placement temperature
with the Office of Construction.
D. Concrete Temperature
Working time of concrete varies with the temperature of concrete, and concrete
temperature varies with the temperature of different materials used in the mix. In
order to determine the dosage rate of retarder, an estimate of the mix temperature
must be made. The following are suggested estimating methods:
■ The temperature of concrete from previous placements could be taken.
■ If a ready mix producer is placing concrete the day before a deck placement, this concrete could be checked for concrete temperature.
■ A computer program has been developed for calculation of theoretical rate of
evaporation using Excel. This program incorporates the charts from the specifications
in a formula table included on report Forms NH-65 and NH-65M. The program simplifies the
determination of the theoretical rate of evaporation and enables the user to perform trial
evaluations for possible changes in air temperature, relative humidity, plastic concrete
temperature, and wind velocity. A copy of the Excel program for theoretical rate of evaporation
is available at
Regardless of the method used, make the best estimate of what the concrete temperature will be, probably during the warmest part of the day and go with it. Remember, concrete shall not be placed in new decks if the concrete temperature is above 32o C (90oF).
Use of Retarders
Several brands of retarding admixture are approved for use. (Refer to
Materials I.M 403.) All brands do not retard the set of concrete for the same amount of time,
therefore, it is important to know which brand will be used. Retarders are not to be used when the
anticipated temperature of the mix is below 13oC (55oF); however, placement
requirements must be met within the initial set time indicated for the non-retarded concrete.
Retarding admixtures require a concrete temperature of 13oC (55oF) or greater in order to activate and effectively retard the set of concrete. If the proposed placement cannot be accomplished within the initial set time for non-retarded concrete, the concrete mix temperature will have to be increased through the use of heated materials. When heated materials are used, it is recommended that a concrete mix temperature of 18oC (65oF) be targeted for effective activation of retarding admixtures.
A. Non-continuous Beam Bridge
Since the beams of a concrete beam bridge are not continuous over the piers, no upward deflection can be transmitted from span to span. For example: During concrete placement in span 3, no uplift exists in span 2 or span 4. However, the beam ends at pier 2 must be free to rotate as load is placed throughout the positive moment area of span 3.
NOTE: It is important for the concrete to remain plastic at pier 2 until placement is complete throughout the positive moment section of span 3. This will eliminate the possibility of stress cracking the slab over the pier.
Now calculate the minimum initial set time required. This is equal to the haul time plus the time required to place all of section 6 and section 3. One hour is added to the minimum required time as a safety factor.
English Units | |
Placement time = 82 yd3 ÷ 40 yd3/hr. = | 2.0 hrs. |
Haul time = | 1.0 hr. |
Minimum working time limit = | 3.0 hr. |
Safety factor = | 1.0 hr. |
Total | 4.0 hrs. |
Metric Units | |
Placement time - 63 m3 ÷ 30 m3/hr. | 2.0 hrs. |
Haul time = | 1.0 hr. |
Minimum working time limit = | 3.0 hrs. |
Safety factor = | 1.0 hr. |
Total | 4.0 hrs. |
Referring to Materials I.M. 403, non-retarded concrete will remain plastic for only 2.5 hours at 24oC (75oF). However, concrete will remain plastic at 24oC (75oF) for 6.1 hours if POZZOLITH 100XR is added at the rate of 89 ml per 45.4 kg (3 ounces per 100 pounds) of cement. Thus, the contractor's request to place concrete in a full-width continuous pour may be approved provided POZZOLITH 100XR retarding admixture is used.
B. Continuous Beam or Girder Bridge
EXAMPLE:
A contractor requests to be allowed to place concrete full-width and full-length
of a continuous welded plate girder bridge requiring the quantities of concrete shown
on Example Concrete Placement Diagrams,
Appendix 11-19. They can realistically haul and place concrete at a rate of 30 cubic
meters (40 cubic yards) per hour. Maximum anticipated concrete temperature is 24o
C (75oF). Brand of retarder requested is Daratard 17.
Since the beams of this structure are continuous over the piers, upward deflection can be transmitted to span 2 during concrete placement in span 3. Therefore, it is important for the concrete to remain plastic in the major portion of span 2 until placement is complete throughout the positive moment section of span 3. Experience indicates that stress cracking will not occur if the concrete in the positive moment section of span 2 remains plastic until such time as placement is complete in span 3 positive moment section.
Minimum initial set time required is then computed as follows:
English Units | |
Placement time = 132 yd3 ÷ 40 yd3/hr. = | 3.3 hrs. |
Haul time = | 1.0 hr. |
Minimum working time limit = | 4.3 hr. |
Safety factor = | 1.0 hr. |
Total | 5.3 hrs. |
Metric Units | |
Placement time - 101 m3 ÷ 30 m3/hr. | 3.3 hrs. |
Haul time = | 1.0 hr. |
Minimum working time limit = | 4.3 hrs. |
Safety factor = | 1.0 hr. |
Total | 5.3 hrs. |
Referring to Materials I.M. 403, it can be seen that Daratard 17 added at a rate of 89 ml per 45.4 kg (3 ounces per 100 pounds) of cement will retard the set of concrete for only 4.3 hours. However, if the amount of Daratard is increased to 118 ml per 45.4 kg (4 ounces per 100 pounds) of cement, set will be retarded for 6.6 hours. Therefore, the contractor's request to place concrete in a full-width continuous pour may be approved if Daratard 17 is added at the rate of 118 ml per 45.4 kg (4 ounces per 100 pounds) of cement.
C. Continuous Concrete Slab Bridges
The use of retarding admixture is not required, but may be necessary if falsework spans are of such a length that will permit deflection. No payment would be made for these situations since it was the contractor's choice to design long falsework spans. Special instructions requiring specific placement sequences will be noted either on the plans or as a condition of review of the falsework plans.
D. Summary
Addition of a retarder is not required when the placement sequence shown on the plans for non-continuous bridges is followed.
For continuous bridges, retarder may be needed when placing adjacent positive moment sections. The contractor could place Sections 1 and 2 the same day probably without retarder. Then Sections 3 and 4 should not be placed until enough strength has developed in Sections 1 and 2 so the uplift would not crack the concrete.
When the guidelines of this instruction are followed, approval from the Construction Office is not required.
Concrete Bridge Floors
Specification 2317 shall apply to smoothness
of the completed deck surface for primary, non-primary, and interstate projects and when
specifically required for other projects. This includes bridges over 30 m (100 feet) in
length except concrete slab bridges. Construction of smooth-riding and maintenance-free
bridge floors requires particular attention and care by the inspector and contractor. The
following sections should be reviewed and kept in mind when preparing for such work.
A. Grades for Screeds
Recent plans for Iowa DOT steel girder and concrete beam bridges include additional information for determination of bridge deck grades. The information is provided in a "Table of Beam Line Haunch Elevations". This table is developed by the designer and provides the theoretical elevation of bottom of deck (ie: top of girder or beam) plus the deadload deflection. This table of elevations can be used to compare directly with the actual field surveyed top of girder/beam elevations at the plan shot locations. The comparison of the theoretical elevation and actual field survey elevation provides the information for anticipated embedment or haunch and grade information for setting deck forms. This "Table of Beam Line Haunch Elevations" provides a simpler process for calculating bridge deck grades. For additional guidance in the use of this plan information contact the Office of Construction.
Since the deflection due to the weight of reinforcing steel is very small, it may be neglected. Thus elevation shots on the beams may be taken before the reinforcing bars are placed and the grades then computed.
B. Screed Clearance Block
Be sure the finishing machine is setup and operated "exactly" as it will be used during the placement. There have been instances where the check pass was made, then prior to actual placement a working platform was added to the machine's truss beam. This additional weight caused a twist in the machine, dropping the trailing screed edge, and reduced the slab thickness by 6 mm (1/4 inch).
C. Screed/Finish Machine Support
NOTE: Rarely will it be allowed to support a finish machine by placing the rail supports directly on the bridge beam.
D. Subdeck Support System
Typically, the total of all loads plus a large factor of safety is accounted for by reducing the distance between the jacks. The inspector should always question, and note in the diary, situations where jacks appear to be:
Specification 2412.03 states that temporary welds will not be authorized, unless otherwise approved by the Engineer, to attach hangers to steel beams to support floor form joists. Materials I.M. 558, Field Welding Inspection Manual, also does not permit any welding to the top flange of steel members for supporting floor form joists. Materials I.M. 558 does permit welding of hangers to shear studs on steel beams subject to specific requirements. Welding of hangers to shear stirrups on concrete beams would also be permitted subject to the requirements of Materials I.M. 558 provided the shear stirrups are not epoxy coated.
E. Screed Support System
During the finish machine's "dry run" the inspector should watch for:
F. Consistency of Concrete
G. Unacceptable Practices
If finishing is a problem, "CONFILM" (a Master Builders evaporation retardant product) can be applied to the struck-off surface. This product reduces surface evaporation, but causes no detrimental surface effects when used as explained in the following. The product is typically applied following final surface finishing to minimize surface moisture loss until the wet cure has been placed. The product must not be used as a finishing aid since the water in the product would be worked into the concrete surface and will change the water/cement ratio. If additional surface finishing is necessary following application, the finishing must not be done until the “sheen” on the surface of the concrete from the water in the product has gone. This will indicate that the water is no longer present and only the barrier film from the product remains.
2. Excessive manipulation of the concrete is detrimental to its durability and should be avoided. Concrete is best when it is placed, finished, and cured with the least amount of disturbance.
3. Excessive floating, over-vibration, and adding water are sure to cause scaling. Concrete must be spread during the dumping process, not piled up and caused to flow by use of a vibrator. Vibration should be done so no area is over-vibrated, yet all is vibrated.
4. All footprints should be vibrated before the finish machine finishes the concrete.
5. Excess cement-sand paste removed from in front of the finishing machine drum must not be allowed to be deposited in the bridge deck gutter area. This paste, when removed, should be distributed across the unfinished concrete mix for blending and reconsolidation through vibration. This is to prevent the development of weak areas in the concrete deck surface due to insufficient aggregate distribution.
H. Use of Finishing Machine
I. Straightedging
J. Transverse Grooving
Recent changes have been made in the grooving of bridge decks, bridge deck overlays, bridge approaches, and overlay of bridge approaches. Project plans are now including notes that state that transverse grooving or tining in plastic concrete will not be allowed. In lieu of this, the plans are requiring that longitudinal grooving is to be cut in the hardened concrete. This is currently being addressed as notes in the plans, but will be included in future Specification revisions. Be alert for these notes on future projects.
K. Retarders
L. Adequate Labor Force
20 cubic meters (or 20 cubic yards) per hour should be a minimum, depending on the quantity of concrete to be placed. Any method of delivery to the deck should be checked to see that rate of placement can be such that finishing operations can proceed at a steady pace, with final finishing completed before the concrete starts its initial set.
M. Curing
Interstate and Primary Projects
With the change to cutting longitudinal grooves in the surface of bridge deck s and
bridge deck overlays, the old method of transverse grooving in plastic concrete was eliminated.
With this out of the placement sequence, we are now able to expedite wet burlap cure within 10
minutes of final finishing. As such, there is also no need to apply white pigmented curing
compound, therefore it has also been eliminated from the placement process. Minor marring of
the surface can be allowed in order to ensure that the wet burlap cure is expedited. Burlap
must be wet before placing. In hot, dry weather, it is better to be a little early than late
with burlap cover. An hour or so later, the second layer of burlap should be laid and both kept
thoroughly wet for the curing period.
Other Projects
Due to the additional costs associated with cutting longitudinal grooves in the
surface of bridge decks and bridge deck overlays as opposed to transverse grooving in plastic
concrete during the placement, the Specifications are being retained for Other Projects to use
white pigmented curing compound as part of the curing process.
Immediately after final finishing and transverse grooving the area finished shall be covered with white-pigmented curing compound. Application of white-pigmented curing compound provides a preliminary surface seal to minimize surface moisture loss until the continuous wet cure process is in place. NOTE: Surface moisture loss will still occur, to some degree, even with white-pigmented curing compound covering the concrete surface. Expediting wet burlap and the continuous wet cure process is critical.
Application and time of placement of cure is critical toward preventing plastic shrinkage cracking of the deck surface. The rate of cure application, uniformity of coverage, and length of time between final finishing and cure application must be closely monitored. Delayed application, inadequate cure rate and/or coverage combined with even the slightest wind velocity can result in plastic shrinkage cracking of the deck surface. Due to the natural shrinkage of concrete as it cures, these plastic shrinkage cracks can propagate into full-depth cracks. Prior to placing curing compound, exposed reinforcing steel for the barrier rail shall be protected with a suitable covering to prevent pigment contamination.
Materials I.M. 405 requires the District Materials personnel to approve, by lot number, all white cure compounds. Be sure this approval has been secured prior to starting the deck pour.
NOTE: Clear curing compound is accepted by manufacturer with a yearly recertification by that manufacturer. Check with the District Materials Office, because a random sampling of clear cure prior to incorporation may be required.
After curing compound is applied, the surface must be covered with wet burlap as soon as possible. Minor marring of the surface can be allowed in order to ensure the wet burlap cure is expedited. Burlap must be wet before placing. In hot, dry weather, it is better to be a little early than late with burlap cover. An hour or so later, the second layer of burlap should be laid and both kept thoroughly wet for the curing period.
Optional methods of curing bridge floors are listed in Specification 2412.07. Since shrinkage cracks are due to rapid loss of surface moisture before the concrete has attained adequate strength, it is imperative that curing protection be initiated before much evaporation can occur (other than free surface water).
N. Cold Weather Placement
O. Floor Drains
Major problems foreseen should be brought to the attention of the Office of Construction.
Placement Methods
Distribution of ready mix concrete from the truck to the bridge deck by concrete pump,
conveyors, or crane & bucket is a regularly used procedure. The practice is common
where access is difficult except at ends of the structure.
Placement of concrete by pump or conveyors is regulated by Specification 2403.08; Paragraphs A, B, C, and D are especially appropriate to pumped concrete.
Rules of Thumb:
1. Use of aluminum materials for the conveyance of concrete is prohibited by
Specification 2403.08. Concrete being conveyed
by aluminum materials can abrade the aluminum resulting in the release of aluminum particles. These
aluminum particles can chemically react with Portland cement causing an abnormal increase in air
content of the concrete and cause an increase in volume.
Examples of conveyance equipment would be tremies, pump conduit/tubing, crane buckets, etc. Forming materials made from aluminum or with aluminum surfaces that will come into contact with concrete are not restricted provided:
2. Concrete for slump and air tests should be obtained from the point of discharge to forms.
3. Air and slump tests performed on the bridge deck during deck pour must contend with vibration of the reinforcing steel and may affect test results.
4. Air content of concrete varies with slump, air temperature, humidity, and mixing time. It is also affected by distance being pumped or conveyed, number of drops (i.e. elbows), distance of unrestricted free fall, only to name a few.
5. Slump can be affected by pumping or use of conveyors due to additional mixing action. Slump uniformity is important for proper finishing.
6. Back up pumping and conveyor equipment, in case of breakdown, is most important when this equipment provides the only access to the placement area.
7. When concrete is placed on the floor by pumping or conveyor, the pump conduit or conveyor must be supported by floor forms rather than on reinforcing steel. Besides being quite heavy when full of concrete, the conduit transmits vibrations from the pump to the reinforcing steel. These vibrations can be quite detrimental, especially when transmitted to floor areas where concrete has taken initial set.
8. The walkway provided for foot travel directly on reinforcing steel can most appropriately be placed adjacent to pump conduit so as to accommodate the placement and removal of conduit sections.
9. Some method should be devised to clean up concrete that may spill from the belt placer or pump conveyor.
10. Pumped or conveyed concrete can be transported a considerable distance and to considerable heights with good results. The key is to move the material as close to horizontal as possible, keep restrictions and drops to a minimum, and eliminate free fall as much as practical. (Free fall can also occur in the pump pipe and between conveyors as well as in the forms.)
11.63 INSTALLATION OF JOINTS
A. Inspection Checklist
2. Position of the 13 x 6 mm (1/2 x 1/4 inch) keeper bars on vertical face of the expansion plate angles has to be consistent with the recommendations of the manufacturer of the neoprene seal. The depth that a seal is set varies greatly with the different manufacturers.
3. The neoprene seal has to be installed so bottom of the seal touches top of the 13 x 6 mm (1/2 x 1/4 inch) keeper bars, but should not be forced past the keeper bars.
4. Make sure expansion opening between angles of the expansion device are consistent with the expansion setting shown on design plans and that the same expansion opening is maintained from gutter to gutter.
5. The neoprene seal must project beyond the outside edge of slab as shown on the plans.
B. Summary
Steel Extruded Expansion Joints
(Strip Seals)
Strip seal joints are the current joint design being used on new bridges and as replacement
for preformed neoprene and sliding plate joints on existing bridges that are rehabilitated. As
with preformed neoprene joints, strip seals are commonly used at the abutments of prestress
bridges over 80 m (265 feet) in length. They may also be used at one or more piers on long,
multi-unit, prestress bridges.
Strip seal joints consist of two extruded steel channels that extend across the full width of the bridge roadway. The steel channels terminate within the concrete bridge barrier rail with the ends of the channels angled up within the barrier rail section. Previous designs provided for a 30 degree channel angle, but current projects are using a 60 degree channel angle (ie: double 30 degree).
The channel angle in the barrier rail is intended to contain water in the gutter area and prevent water from draining out the ends of the strip seal joint. To ensure this, both the end of the channel and low point of the neoprene gland trough must be a minimum of 100 mm (4 inches) above the gutter line.
Strip seal joints are more effective in sealing the expansion joint and preventing leakage of water
through the joint and onto the substructure units. For strip seals to function effectively they must
be installed correctly and maintained on a regular basis. To insure that strip seal joints function
properly, there are a number of precautions that should be noted regarding the installation of this
type of joint. Precautions:
11.64 BRIDGE FLOORS
Finishing and Equipment
Rails used to support the finishing machine on bridge deck overlay projects shall be set
so rails extend beyond each end of the bridge.
On some bridges, the wing post has been modified to accept steel formed barrier rails. Specifically, rails have been offset or repositioned to clear the wing post. In these situations, it is impractical to set a continuous straight line of support rails past the wing post. Generally this leaves a small area of deck surface adjacent to the face of curb which is not machine finished. This area may be finished by hand methods, or air screeds, using hand-held concrete vibrators.
Profile Grades - Overlays
Plans for bridge deck overlay projects provide a "surface raise" dimension. This value shall
be considered a minimum and screed guides shall be adjusted to achieve a smooth profile.
BE CAREFUL: In some instances the finishing machine rails have been adjusted to obtain a smooth profile to the extent that the thickness of the overlay placed was excessive. This is a concern:
In achieving a smooth profile grade, the grade line should not be increased by more than 6 mm (1/4 inch) over the raise specified on the plans. However, a raise of 13 mm (1/2 inch) may be permitted provided the rise does not affect more than 33% of the deck area and the existing profile grade justifies the additional thickness.
If a preliminary field examination indicates that a surface raise in excess of 13 mm (1/2 inch) is necessary to achieve an acceptable grade line, a provision must be made to determine the overrun of concrete mix used in excess of the 13 mm (1/2 inch) plan surface raise. This will necessitate taking extra depth checks during placement and possibly cross-sections of the existing deck surface and sections after the overlay is placed. Payment for the overrun will be by a Change Order extending the unit price for concrete.
Approval by the Office of Construction will be necessary prior to placing an overlay greater than plan thickness when:
Transverse Grooving
Over the past few years the texturing of bridge deck floors and deck overlays resulted in
a number of different types of grooving devices being used to groove deck surfaces. Combs with
various tine widths, shapes, spacing, and a fluted magnesium float have been used to groove
surfaces.
Research on tine texture and spacing pattern has been conducted to evaluate the impacts on tire noise. The outcome of the research findings has resulted in changes to the spacing pattern for tine texture on bridge decks and deck overlays.
Specifications require that a broom or comb shall be:
Longitudinal Grooving
In Hardened Concrete
Recent changes have been made in the grooving of bridge decks, bridge deck
overlays, bridge approaches, and overlay of bridge approaches. Project plans are now including notes
that state that transverse grooving or tining in plastic concrete will not be allowed. In lieu of
this, the plans are requiring that longitudinal grooving is to be cut in the hardened concrete. This
is currently being addressed as notes in the plans, but will be included in future Specification revisions.
Be alert for these notes on future projects.
For staged bridge projects (ie: bridge replacements, bridge deck overlays, etc.) where the plans specify longitudinal grooving in hardened concrete, the plans will provide an option for interim "coarse broom" surface texture to be used for staged traffic surfaces. The purpose for the optional interim "coarse broom" surface texture is to enable the contractor to reduce their mobilization of grooving equipment to one event instead of multiple mobilizations. If the contractor opts to use the interim "coarse broom" surface texture, they will be permitted to complete all stages of deck work before being required to do longitudinal grooving. The intent is that within 30 days following the completion of all stages, the contractor will complete the required longitudinal grooving of the deck surface. "Coarse broom" surface texture will not be permitted as a traffic surface texture during winter months, so regardless of the status of completed stages, the contractor will be required to longitudinally groove prior to winter weather.
Missed Texturing
There will be times, due to various reasons, when texturing will have to be omitted from
a pour. One such event could be when inclement weather catches a pour and covering prevents
texturing. Obviously this condition is NOT desirable, however, what if?
EXAMPLE #1: A deck or an overlay is being placed and the texturing has to be omitted:
EXAMPLE #2: A subdeck is being placed where an overlay is required, often the plans will require some type of texturing. Such texturing is intended to improve the overlay's bond. If conditions during the pour present a situation where texturing has to be omitted:
11.65 CONCRETE
Data from bridge deck repair projects of the last several seasons have been reviewed. The evaluation indicates that the actual water/cement ratios are very close to the design, or intended, water/cement ratio. Therefore, no maximum or limiting water/cement ratio specification for the low slump, bridge repair concrete is recommended. The water/cement ratio of low slump concrete need not be determined for bridge overlay surface courses.
The witnessing and documentation of the dilution procedure of the air and water reducing admixtures must be observed.
Existing specifications presently allow a mobile concrete mixer to be used for certain structural concrete repair, if part of a bridge deck repair project ( Specification 2413), and also for barrier rails on the same type of projects (Specification 2513). For these, and any other concrete construction for which the project engineer might authorize this equipment, a water/cement ratio limit is specified. Thus, the water/cement ratio must be checked, and documented, for compliance when low-slump concrete is not being produced.
Frequency of Checks
Since cement registers and water meters are continuously recording, a water/cement ratio
check may be made at any interval, e.g. hourly, half days, or at the end of a placement.
A minimum of one check per day's placement should be made and documented.
Density Testing
Durable, low maintenance bridge decks require impermeable (very dense) concrete. Therefore,
checking density during placement is an essential part of deck surfacing and overlay inspection.
Test frequencies for determining the density of bridge deck surfacing and overlays are listed in
Material's I.M. 204, Appendix M-2.
Nuclear density testing frequency is based on a minimum of three nuclear density tests for each placement. Testing frequency of nuclear density testing for each placement shall be one test within 5 feet (1500 mm) of the beginning and end of the placement and additional tests shall be equally spaced a maximum of 100 feet (30 000 mm) throughout the length of the placement.
It is always desirable to take more than the minimum nuclear density tests per length of overlay placed. If densities are at or near the lower specification limits, additional testing will need to be performed.
C. Vibrating Mix at Test Well Location
If the oscillating screed vibrators are functioning properly, complying density of the concrete mix in the test well will be obtained without any difficulty. Obtaining required density at test well locations, without supplemental vibration, assures us that the contractors' equipment and placement procedures are capable of producing the desired results throughout the overlay being placed.
D. Density Test Wells on Bridge Deck Repair Projects
Occasionally a deck repair job may only have a minimal quantity of Class A Bridge Floor Repair and the location of these repairs are not always at the optimum spacing for nuclear density checks. If this is the case, additional test wells should be constructed in the bridge floor prior to placing the overlay. Typically, wells need to be about 250 mm x 250 mm x 40 mm (10 inch x 10 inch x 1.5 inch). Note: The depth of 40 mm (1.5 inch) is in addition to the normal 50 mm (2 inch) overlay thickness.
Test wells constructed by the contractor will be measured and paid for as Class A Bridge Floor Repairs.
11.66 APPROACH SECTIONS
Plan Tabulation 112-6, “Tabulation of Bridge Approach Section,” identifies for each bridge approach whether the abutment is ‘Movable’ or ‘Fixed.’ The Standard Road Plans RK Series provides the details for bridge approach pavement construction. Standard Road Plan RK-19A and RK-20(1) provides specific details for ‘Movable’ and ‘Fixed’ abutment conditions.
The ‘Movable’ or ‘Fixed’ term refers to the vertical edge at the bridge end against which the approach pavement is to be placed. One other aspect that must be evaluated is whether the vertical bridge end and the ledge upon which the approach pavement is placed are rigidly attached (i.e. do they move together or are they independent of each other in movement?).
The RK-20 series of bridge approach standards is a new design being used on all interstate and primary projects. The new approach pavement structure to mitigate approach failure due to potential settlement under the approach slab. The design has increased the reinforcing in the first slab section off the end of the bridge to enable the slab to carry traffic loads even when a void develops below the slab. The second slab section off the end of the bridge has also been reinforced. In addition, for the 'Movable' abutment a reinforced concrete 'lug' has been incorporated into the first slab section. The intent of this 'lug' is to prevent the approach slab from being displaced as the bridge abutment moves.
Continuing research is under way to identify the causes of void development under the approach pavement behind bridge abutments. Further improvements in design and construction practices are anticipated in the future to address the void development problem.
Note: The RK-19 series standards have been retained for use by counties and cities on secondary projects should they choose not to use the new RK-20 series standards.
'Movable' Abutments
A 'Movable' abutment is one which is rigidly attached to the superstructure and therefore
'moves' with the superstructure when it expands or contracts from thermal movement (Refer to
Standard Road Plan RK-19A, Detail “A,”
Movable Abutment Bridge or RK-20(1), Detail
"A", Movable Abutment).
There are two types of ‘Movable’ abutment designs. These are explained by the following situations:
Situation 1: If there is no joint in the bridge deck adjacent to the bridge end and the ledge on which the approach pavement is placed moves together with the vertical bridge end, the abutment is considered ‘Movable.’ In this situation, places a ‘CF’ Joint at the vertical interface between the approach pavement and the bridge end. Do not use dowels in this situation to attach the approach pavement to the ledge.
Situation 2: This situation occurs in many older bridges and is uniquely different from the first situation. As explained in the following, in this ‘Movable’ abutment design, the abutment is NOT rigidly attached to the superstructure.
If there is no joint adjacent to the bridge end and the vertical bridge end can move independently of the ledge on which the approach pavement sits, then the end of the bridge would be considered ‘Movable’ and the ledge would be considered ‘Fixed.’ In this situation, it would be advantageous to dowel the approach pavement into the ‘Fixed’ ledge of the abutment and place some type of expansion joint material (possibly ‘CF’, ‘E’ or other material) against the ‘Movable’ bridge end.
Consideration must be given to the ledge width and the thermal movement of the bridge end (i.e. bridge length and type) when determining the joint material to be used at each location. Material capable of 25 mm +/- (1 inch +/-) of movement (i.e.: 50 mm (2 inch) joint width of ‘CF’ material) should be capable of handling movements for this ‘Movable’ abutment design. If the ledge width is too narrow to accommodate the approach pavement and the joint material used, the ledge may have to be widened.
'Fixed' Abutments
A ‘Fixed’ abutment is one that is unattached to the superstructure and therefore allows
thermal movement to take place independently in the superstructure while the abutment remains
‘Fixed’ in position. (Refer to Standard Road Plan
RK-19A, Detail “A,” Fixed Abutment Bridge
or RK-20(1), Detail "A:,
Fixed Abutment).
There is typically one type of ‘Fixed’ abutment which is explained in the following:
If there is a joint in the bridge deck adjacent to the end of the bridge (within one or two feet), the vertical bridge end will be considered ‘Fixed’ and the ledge on which the approach pavement will be placed is rigidly attached to the vertical bridge end. Note that the joint in the bridge deck could be a sliding plate, a strip seal, a compression seal (armored or unarmored) or preformed joint material. For the ‘Fixed’ abutment design, place an ‘E’ joint at the vertical interface between the approach pavement and the bridge end. Use dowels to attach the approach pavement to the ledge it will sit on.
Bridge Approach Tapers
On deck overlay construction, normally some treatment of the approach is necessary and will
be indicated on the plans. It must be noted that tapers will no longer be placed by Maintenance.
Watch the contract documents for bid items for ACC material. For projects where asphalt tapers
are proposed and no quantity for ACC is given, a Change Order will be required.
Shoulder Maintenance
When temporary concrete barrier rails are used on deck repair and overlay jobs, traffic is
constricted into a narrower lane. This in turn could cause a rapid deterioration of shoulders
at bridge approaches and require the following corrective measures:
B. Ruts and loss of asphaltic cement concrete surfacing on Interstate shoulders should be maintained using an asphalt cement concrete pre-mix, hot mix, or some similar treatment to minimize the development of holes or ruts. A Change Order will be issued for this work unless there is an ACC contract item for shoulder maintenance and even then it may have to be extended.
C. When shoulder strengthening was not included as a bid item, but is needed for the project, justification for the Change Order must consider:
11.67 SMOOTHNESS OF BRIDGE DECKS
Specification
B. Profilograph testing of each wheel path of each lane will be required. However, wheel paths
per lane will be averaged together for a profile index. C. On new bridge decks the whole bridge is considered as 1 section.
2317 2428
This specification deals with deck smoothness, pay incentives, and price reductions. Some highlights
are:
A. It covers all bridge decks and overlays greater than 30 m (100 feet), including any approach
work. This applies to primary, non-primary, and interstate work unless specifically excluded by the
contract documents. Profilograph testing is to be performed for all work
and is to include a minimum of 100 feet (30 m) beyond the approach section when there is adjoining
pavement. An average profile index for smoothness is to be calculated for all work areas except
exclusions as stated in
Specification
2317.04
2428.04. For the excluded areas, the profilograph is to be
used only for evaluation of 0.5 inch (13 mm) bumps and dips and determination of needed
areas of correction.
NOTE: 5.0 m (16 feet) from each abutment and from each expansion joint will be blanked out for index calculation.
D. For overlays where the expansion joint is NOT new or replaced, segments are:
E. Testing Times
F. Surface Correction
Grinding head is to be at least 0.6 m (24 inches) wide. It is preferable to have a head 0.9 m (36 inches) wide.
Correction will follow Specification 2532.
NOTE: This could be a problem if the project engineer approves any correction method other
than grinding.
If a surface correction is made, a second trace will be needed to evaluate effectiveness of the correction.
G. Incentives
The initial profile index will be used for incentive evaluation.
The entire bridge
Grinding any
Incentive index for:
H. Price Reduction
The final profile index will be used for reduction evaluation.
Contractor may grind to avoid price reduction.
Price reduction is mandatory if the final index is:
Grinding is mandatory for:
Surface Checking
A 3 m (10 foot) surface check shall be conducted on all bridges, bridge approaches,
deck overlays, and overlay of approaches not covered by the Smoothness Specification.
Surface areas inaccessible to profilometer shall also be checked.
On some projects only one wheel path may be included in the placement width. For price adjustment or incentive pay, only the portion within the traveled lane shall apply.
Variable width sections for on and off ramps, which are outside the through traveled lane, will be checked with the surface checker.