CHAPTER 3
GENERAL INSPECTION
3.00 GENERAL INSPECTION INSTRUCTIONS
3.01 INSPECTION PERSONNEL
An inspector must be honest and fair, exercising responsibilities with firmness and good nature. Inspectors must work cooperatively with fellow employees, supervisors, and contractors. The inspector must avoid supervising the contractor's work operations or performing any other activity that could be construed as a responsibility of the contractor; otherwise, the contracting authority's position could be jeopardized in the event of a dispute or claim.
Responsibilities
The inspector, as a member of the construction team, must perform assigned duties in a manner that
will promote the progress of the project. The inspector should be familiar with the construction
schedule and know how the work to be inspected fits into that overall schedule. Completion of the
work within the contract time is important to both the contracting authority and the contractor.
Inspectors are accountable to the project engineer for satisfactory performance of their duties.
In performing assigned duties, an inspector has the following responsibilities:
■ Plan Familiarity
Authority
The inspector has the authority to reject materials or suspend work if the quality of either is in
dispute with the contractor. Settlement of a dispute is decided by the project engineer.
An inspector's authority does not extend to modification of any of the provisions of the contract
documents, acceptance of the work, acting as a supervisor for the contractor, or improper interference
in the contractor's project management.
3.02 SUPERVISION BY SUBCONTRACTOR
3.03 COMMUNICATION WITH CONSULTANTS AND CONSULTANT PLAN ERRORS
Every effort should be made during plan review to discover errors in staking layouts, elevations, reinforcing steel quantities, etc. Any project costs resulting from plan errors, such as the removal and reconstruction of an item built according to an erroneous plan, should be reported to the Office of Construction for recovery from the consultant.
County and city engineers should apply this same philosophy to errors in plans by consultants they hire.
3.04 REMOVING MATERIALS FROM PROJECTS
Construction materials are defined as, but not limited to, pile cut-offs, old plywood, broken tools, piles of aggregate, erosion control materials and plantings, concrete test beams, samples of aggregates or other materials, and the products of project site clearance.
Complete cleanup of the construction area or plant site, including test materials, is the responsibility of the contractor.
3.05 SALVAGED PROJECT MATERIALS REPORTING
The form shall be completely filled out any time project materials are salvaged to a maintenance facility. The form needs the signature and initials of the project inspector and the maintenance employee who received the material.
Distribute a copy of completed form to project engineer, area maintenance manager, Office of Inventory, and project file. The Office of Inventory will add the salvaged items to the 999 series of inventory for the maintenance facility that received these materials. Include copy of completed form in the final payment packet for the project per Construction Manual 2.45.
3.06 NOTICE OF SUSPENSION OR RESUMPTION OF WORK
Upon settlement of the question at issue, the "Notice of Suspension or Resumption of Work" (Form 810036) shall be reissued to release the contractor from the work suspension order. Although the work suspension order may be issued by the inspector, the release requires the project engineer's signature.
Copies of the "Notice of Suspension or Resumption of Work" (Form 810036) should be given to the contractor, District Construction Engineer (DCE), and project engineer.
3.07 REQUIREMENTS FOR MONITORING THE CERTIFIED PLANT INSPECTION PROGRAM AND QUALITY MANAGEMENT - ASPHALT (QM-A)
On certified plant inspection projects, it is a requirement for the plant monitor to be a certified technician for the type of work involved.
QM-A requirements can be considered an expansion of the certified plant program for HMA. In addition to normal certified plant inspection duties, under QM-A the contractor is also required to design and submit their own mix designs for agency approval. At the plant, the contractor is required to analyze and control mix production properties through frequent field testing, based on specified gyratory or Marshall mix design criteria.
For a QM-A project, the plant monitor must be a certified HMA technician. This certification is obtained by attending the Level I HMA course and passing the required examinations.
It is imperative that project engineers maintain an adequate staff of trained, experienced plant monitors. This can be accomplished by having employees participate in the appropriate technician training and certification programs and pass the examinations.
Certified plant inspection will apply to items of work as defined in Specification 2521.03. Any items of work excluded from certified plant inspection will be as noted in contract documents. Work excluded from certified plant inspection will also be excluded from QM-A requirements.
In the event the contractor's certified technician is absent, the contractor must contact consultants or other available certified technicians to arrange for inspection.
For duties performed by the certified HMA technician on QM-A projects, the contractor must also contact consultants or other sources for available certified technicians in cases of absenteeism. Because of the laboratory skills necessary to perform this work and the decision making authority as a representative of the contractor, it is not possible or appropriate for the project engineer to provide certified HMA technician services to the contractor in cases of unexpected absences. If the contractor fails to provide certified HMA technicians as required by specification, work covered by QM-A shall be suspended until the project is properly staffed.
Portland Cement Concrete Paving
Plant Monitoring
Appendix 3-2 lists the minimum monitoring requirements. A plant
monitor will normally be assigned to each project with duties split between plant and grade inspection.
Plant monitor should schedule work so the plant can be visited daily during production. The amount of
time spent at the plant will depend on the overall quality control at the production plant. QM-A Test
beams for determining flexural strengths are to be transported from the grade to the plant site by
contracting agency personnel.
Structural Concrete Plant Monitoring
Appendix 3-3 lists the minimum monitoring requirements. The
project engineer and contractor should agree in advance whether aggregate gradations, moisture, and
specific gravity tests will be waived for concrete which is furnished at a maximum rate of 20 m3
(25 cubic yards) per day. This determination should be in accordance with
Materials I.M. 528.
Ready mix tickets shall be prepared and signed by the certified plant inspector.
Test beams for determining flexural strengths are to be transported from the grade to the plant site by contracting agency personnel. The certified plant inspector is responsible for curing and storage of the beams. Contracting agency personnel are responsible for testing and reporting results.
Hot Mix Asphalt Paving Plant
Monitoring
Appendix 3-4 lists the monitoring requirements.
Responsibilities are shared between the plant monitor, grade inspector, and materials
personnel. A plant monitor will normally be assigned to each project with duties split
between plant and grade inspection, and may also be assigned to multiple projects under
construction at the same time. The plant monitor should schedule work so that the plant
can be visited daily
during production, at a minimum, as frequently as required by
Appendix 3-4. The amount of time spent at the plant, beyond minimum requirements,
will depend on the overall quality control at the production plant. The project inspector
will be providing production and placement information to be entered on the daily plant
report.
Visits by the project inspector to the plant laboratory for exchange of information and to perform administrative activities will normally be done daily.
The plant monitor will typically be responsible for performing the density testing on HMA core samples.
Plant Reports
The project engineer should make arrangements with the certified technician for timely distribution
of plant reports. On QM-A projects, the contractor shall FAX a copy of the daily plant report and
QM-A Summary Sheet to the District Materials Engineer on a daily basis. The original and all copies
of the plant report shall be kept at the plant until all documentation is completed. Normally, this
will be the day following the end of the reporting period. Review and distribution of the reports
will be made by the project engineer. This distribution will include a copy to be returned to the
certified technician. Prompt consultation with the certified technician and monitor shall follow
any significant error or omission.
A copy of this documentation must be furnished to the District Materials Engineer (DME) at the time of project acceptance. Also include the certified technician's name, certificate number, and statement from the monitor regarding the work performance of certified technician. It may be necessary to consult with the DME regarding contractor technician performance for Marshall testing duties on a QM-A project. A sample format for providing this documentation is contained in Appendix 3-6.
Specification Violations
Failing test results are to be recorded on the daily plant report by the plant inspector. Verbal
notification of such failing results shall precede completion of paperwork to assure timely changes.
Failing test results on QM-A projects related to specified moving averages will be noted on the certified HMA technician data sheets and quality control charts. Special notes on these failures will also be reported in the comment section of the daily plant report. When average points move outside the specification limit, HMA mix production operations shall cease until the contractor proposes meaningful corrective action. The corrective action must be discussed with the DME prior to production start-up.
The plant monitor will convey to the responsible project inspector all specification violations, discrepancies in results with the plant inspector, and improper procedures and equipment used by the plant inspector. The project inspector will issue noncompliance notices for failing test results and inadequate testing procedures or equipment.
In order to use the contractor quality control test results for the acceptance decision, they must be validated by agency verification tests. It is important to notify the contractor and the DME when the results do not compare within the validation criteria in the Materials IM. The lot of material cannot be accepted until the validation issue is resolved by the DME.
All improper procedures, unresolved test discrepancies, or failure to perform inspection duties will be considered by the DME for possible decertification or other appropriate corrective action.
The role of the plant monitor is vital in assuring the DME is aware of any deficient or otherwise unsatisfactory work of the certified technician.
Testing Equipment & Supplies
Certain testing equipment is available for purchase from Department stock. Producers should
refer to HMA and PCC Plant Inspection Manuals for specific information and Office of Materials
Lab contacts. A list of equipment suppliers is included in the plant manuals.
Necessary plant inspection forms will be furnished to the producer at no cost. The producer can request these through the DME or project engineer. It is a good idea for the plant monitor to carry a supply of forms and make these available to the producers as needed.
The plant monitor can utilize contractor-furnished equipment for testing required at the plant site. HMA core density testing will most likely be done using the same balance, water bath, and thermometer as the contractor. Verification gradation testing should be done at a separate laboratory from the contractor's if possible.
Samples
Verification samples are to be taken by agency personnel or by contractor
personnel when directed and witnessed by agency personnel. Materials I.M. 204 will indicate when
contractor sampling assistance is required.
Verification samples that are not tested should be retained until the lot has been accepted.
If required by contract documents, transportation of secured verification samples to the District Materials Lab shall be performed by the contractor.