Section 1110. Progress Scheduling.

1110.01 GENERAL.
When specified in the contract documents, the Contractor shall submit a progress schedule of construction activities based on the CPM by the principles defined in the most current issue of THE USE OF CPM IN CONSTRUCTION published by the Associated General Contractors of America. The CPM progress schedule may be hand or computer developed.

The CPM progress schedule shall be used for coordination and monitoring of all work under the contract including all activity of subcontractors, vendors and suppliers. The CPM progress schedule shall include provisions for traffic control, any staging, and other events to complete a project or tied projects. This schedule shall be the Contractor's intended working schedule and shall be used to plan, organize and execute the work; record and report actual performance and progress; and forecast remaining work.

1110.02 SUBMITTAL OF A CPM PROGRESS SCHEDULE.
When a submittal of a CPM Progress Schedule is specified in the proposal form, the successful bidder for the project must submit 5 copies of a satisfactory CPM progress schedule to the Contracts Engineer with the signed contract. Failure to submit a CPM progress schedule may result in suspension of bidder qualifications in accordance with Article 1102.03, A.

1110.03 REQUIREMENTS FOR THE CPM PROGRESS SCHEDULE.
The CPM progress schedule submitted shall be a network diagram with a numerical tabulation for each activity.

1110.04 USE OF CPM PROGRESS SCHEDULE IN CONSTRUCTION OPERATIONS.
No contract work shall be done without a CPM progress schedule approved by the Engineer. The items in the activities for the denoted critical path will determine the controlling operations of the work for the charging of working days.

During the life of the project, the Contractor shall review the CPM progress schedule with the Engineer biweekly unless otherwise specified. The Contractor shall submit a revised CPM progress schedule within 5 working days of the review meeting if the Contractor is behind schedule or if the schedule has been modified. All revised CPM progress schedules must be approved by the Engineer. For each revised CPM progress schedule, the Contractor shall submit 3 copies to the Engineer.

If the Contractor deviates from the current approved CPM progress schedule by not following the logical sequence of the critical path, payment will be withheld for the pay items for the affected activities until the Contractor submits a revised CPM progress schedule and this schedule is approved by the Engineer.

A revised CPM progress schedule will be required if the controlling operation falls 10 working days behind schedule, the Engineer then may take steps specified in Article 1108.02, H, to insure satisfactory completion of the project. If the controlling operation falls 20 working days behind schedule and it appears that the completion of the project in the specified time is in jeopardy, the Contracting Authority may take action described in Article 1102.03, B, and Article 1103.01 and may take further action described in Article 1108.02, H.

1110.05 METHOD OF MEASUREMENT AND BASIS OF PAYMENT.
The cost of preparing and revising the CPM Progress Schedule shall be included in the bid item for Mobilization.