Section 1111. Incentive/Disincentive for Early Completion.

1111.01 GENERAL.
Incentive/Disincentive (I/D) provisions for early completion of specific highway construction projects with critical closure activities may be assigned by the Department. Early completion may be specified for an entire project or for designated portions of a project.

Projects on which I/D provisions will apply have the I/D daily rates, the critical closure activity, the number of closure days allowed, the total working days for the project, and the maximum incentive payment shown on the proposal form.

1111.02 DEFINITIONS.

1111.03 CONSIDERATION FOR EXTRA WORK OR DELAYS DURING THE CRITICAL CLOSURE ACTIVITY.
The duration of a critical closure activity will be in closure days. Closure day credits will not be given within the assigned critical closure activity.

Additional closure days may be added when approved by the Engineer for extra work, overruns of contract items, or extraordinary circumstances.

1111.04 WORK OUTSIDE THE CRITICAL CLOSURE ACTIVITY.
The contract period may specify a number of working days. These days are provided to complete work prior to and/or following the critical closure activity. Working days will not be charged on any calendar day that a closure day is charged.

The liquidated damage rate shown on the proposal will be assessed for each working day used in excess of the number of working days specified.

1111.05 I/D PAYMENT OR ASSESSMENT.