CHARGING OF CONTRACT TIME
References: Sections 1108 & 11111108 & 1111
Days (Working or Calendar) |
TYPICAL CONTRACTS |
CONTRACTS WITH INCENTIVE/DISINCENTIVE |
||||||||
Non-Accelerated |
Accelerated |
Non-Accelerated |
Accelerated |
I/D Portion |
||||||
Working Days Charged? |
Working Days Charged? |
Working Days Charged? |
Working Days Charged? |
Calendar Days Charged? |
||||||
Yes* |
No |
Yes* |
No |
Yes* |
No |
Yes* |
No |
Yes |
No |
|
Monday – Friday |
X |
|
X |
|
X |
|
X |
|
X |
|
Saturday |
|
X |
X |
|
|
X |
X |
|
X |
|
Sunday |
|
(A) |
|
(A) |
|
(A) |
|
(A) |
X |
|
HOLIDAYS: |
|
|
|
|
|
|
|
|
|
|
State-Observed Holidays |
|
(A) |
|
(A) |
|
(A) |
|
(A) |
X |
|
Thursday Before a Holiday (1) |
|
(A) |
|
(A) |
|
(A) |
|
(A) |
X |
|
Fri. or Sat. Before A Holiday (2) |
|
(A) |
|
(A) |
|
(A) |
|
(A) |
X |
|
OTHER SITUATIONS: |
|
|
|
|
|
|
|
|
|
|
Inclement Weather (3) |
|
X |
|
X |
|
X |
|
X |
(B) |
|
Site Restrictions (4) |
|
X |
|
X |
|
X |
|
X |
(B) |
|
Cure Time (5) |
X |
|
X |
|
X |
|
X |
|
X |
|
Winter Free Time (6) |
|
X |
|
X |
|
X |
|
X |
X |
|
Natural Disaster |
|
X |
|
X |
|
X |
|
X |
(B) |
|
|
|
|
|
|
|
|
|
|
|
|
TABLE NOTES:
(*) Assumes work can occur on the controlling operations.
(A) “Unless” work is pre-approved by the project engineer. If working is allowed, a working day will be charged.
(B)
Refer to Specification 1111Specification
1111, and Chapter 2Chapter 2 of the Construction Manual for guidance.
(1) For holidays which occur on a Friday.
(2) For holidays which occur on a Saturday, Sunday, or Monday.
(3) Assumes weather affects the controlling operation.
(4) If restriction is outside the contractor’s control, and it affects controlling operation.
(5) If it is the controlling operation.
(6) Assumes time is remaining on the contract.