7.60     SPECIAL DITCH CONTROL

Special ditch control is to be placed in conjunction with seedbed preparation and planting times as specified in Specification 2601.03, B.

 

The limits of ditches should be staked with flats or flags, and markers should be placed to one side of the ditch to remain visible during construction.  The centerline of the ditch is determined by the low point of the ditch.  It may be necessary to shift the ditch in order to maintain the best possible alignment and to avoid sharp turns in sod ditches.

 

7.61     PLACEMENT

The suggested sequence of work for special ditch control is as follows:

 

Shape

Shape the ditch and prepare the seedbed to a depth of no less than 3 inches.  If ditches are unstable and equipment leaves them in a rough condition, the seedbed must be prepared by hand.  The ditches should be shaped so that the ditch drains without water ponding and has a minimum depth of 6 inches.  Minor irregularities in ditch alignment must be corrected so the completed ditch will follow the ditch line constructed during the grading operation.  This may not be possible in cases of severe washing of the ditch bottom.  All rocks and clods 1 1/2 inches in diameter, and all sticks and other materials, which prevent contact of the special ditch control materials with the seedbed, shall be removed.

 

Check Slots

Install check slots as required.  Take care that all check slots are carefully and properly installed.  The success of the ditch may be dependent on proper installation of the check slots.

 

Finish

Smooth disturbed areas adjacent to ditch control.  Make sure that no ridge of dirt remains alongside the ditch, and that material excavated from the ditch channel is properly shaped and sloped to allow water to run onto the special ditch control material.  This area should be raked.

 

Fertilize

Fertilizer should be applied at the proper rate with a mechanical spreader.  A cyclone seeder may be used to secure a uniform rate of application.

 

Seed

Seed mixture and rate of application are specified in addition to acceptable methods of application.

 

Special Ditch Control Material

Special ditch control materials must be applied without tension and in the direction of the flow of water since there may be some settling of low or filled portions of the ditch and some shrinkage of the material.  Do not stretch the material.  Install staples as specified in the Design Standards.

 

7.62     WATERING

Special ditch control should be watered initially by the end of the day following installation.  Water should saturate the soil to a depth of approximately

2 inches with the maximum of 50 gallons of water per 100 square feet. This is roughly equivalent to a ¾ inch rainfall but depends on soils conditions, rate of rainfall, and topography of land.  Three additional waterings are required at one week intervals, depending on weather conditions.  The scheduled waterings may be deleted if precipitation has moistened the soil to a depth of 2 inches.

 

The specifications provide for a price adjustment per calendar day if the Contractor does not complete the watering.

 

7.63     PAYMENT

Payment for watering will be based on the predetermined contract unit price per 1000 gallons.

 

Typically, projects that have a contract item for Watering should also include a contract item for Mobilization for Watering, unless they are identified as erosion control or landscaping.  Initial watering required at installation will not be counted for payment of Mobilization for Watering.