PCC PAVING - FIELD AND PLANT SAMPLING AND TESTING GUIDE

(See Specifications for Complete Details.)

 

 

 

 

Field Acceptance

Plant Acceptance

 

Article

Work Type

Air & Slump

Gradation QC

Gradation Verification

 

 

(No slump for slipform paving)

 

 

2122

PCC Shoulders

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2301

PCC Pavement

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2301

PCC Pavement - QMC

1/700 yd3: 1/200 yd3 RM

If >500 yd3/day S/T 1/1500 yd3,

If <500 yd3/day S/T 1/wk

S/T 1st/day, S 1/day >500 yd3, Test 2/week,

If <500 yd3/day, S/T 1 wk

2301

Bridge Approaches,

Gores, tapers, radiuses

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

n/a

2302

PCC Widening

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2310

PCC Overlay

1/700 yd3: 1/100 yd3 RM

S/T 1st day, then 1/day>500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3 & T 1/wk,

If <500 yd3/day S 1/wk & T 20% (4)

2310

PCC Overlay - QMC

1/700 yd3: 1/100 yd3 RM

S/T 1/1500 yd3,

If <500 yd3/day 1/wk

S/T 1st/day, S 1/day >500 yd3, Test 2/week,

If <500 yd3/day, S/T 1 wk

(4)  If less than 500 yd3 per day / intermittent construction continues for more than two weeks, obtain verification samples weekly and test 20% of the samples obtained.