SECTION 11,020 - MOBILIZATION
Project Mobilization
Mobilization includes preparatory work, operations performed, or costs incurred prior to beginning work on the various items on the project site.
Comply with Division 1 - General Provisions and Covenants.
Comply with Division 1 - General Provisions and Covenants.
1.05 DELIVERY, STORAGE, AND HANDLING
Comply with Division 1 - General Provisions and Covenants.
Comply with Division 1 - General Provisions and Covenants.
A. When a bid item for mobilization is included on the proposal form, comply with this section for measurement and payment.
B. When the proposal form does not include a bid item for mobilization, all costs incurred by the contractor for mobilization are incidental to other work and no separate payment will be made.
1. Measurement: Lump sum item; no measurement will be made.
2. Payment:
a. When 5% of the original contract amount has been completed, 25% of the contract price for mobilization will be paid.
b. When 10% of the original contract amount has been completed, 50% of the contract price for mobilization will be paid.
c. When 50% of the original contract amount has been completed, 100% of the contract price for mobilization will be paid.
3. Includes: The unit price for mobilization may include the following.
a. The movement of personnel, equipment, and supplies to the project site.
b. The establishment of offices, buildings, and other facilities necessary for the project.
c. Bonding, permits, or other expenses incurred prior to construction.