Division 1 Table of Contents

 

Section 1010 - Definitions

 

1.01        Description

 

1.02        Abbreviations

 

1.03        Definitions and Terms

 

Section 1020 - Proposal Requirements and Conditions

 

1.01        Qualification of the Bidders

 

1.02        Contents of the Proposal Forms

1.03        Quantities and Unit Prices

1.04        Examination of the Contract Documents and Site of Work

1.05        Interpretation of the Contract Documents

1.06        Addendum

1.07        Preference for Labor and Materials

1.08        Taxes

1.09        Preparation of the Proposal

1.10        Bidders Certification

1.11        Irregular and Nonresponsive Proposals

1.12        Submission of the Proposal, Identity of Bidder, and Bid Security

1.13        Withdrawal or Revision of the Proposal Prior to Opening of Proposals

1.14        Opening of Proposals

1.15        Limitation on Withdrawal of Proposals After Opening of Proposals

 

Section 1030 - Approval for Award and Award of Contract

 

1.01        Acceptance or Rejection of Proposals

 

1.02        Release of Bid Security

 

1.03        Award of Contract

 

Section 1040 - Scope of Work

 

1.01        Intent of the Contract Documents

1.02        Correlation of the Contract Documents

1.03        Coordination of Specifications, Plans, and Special Provisions

1.04        Conformity with the Contract Documents

 

1.05      Plans

1.06      Increase or Decrease of Work

1.07      Change Orders

1.08      Site Conditions

1.09      Changed Site Conditions

1.10      Disputed Claims for Extra Compensation

1.11      Delays Caused by the Jurisdiction

1.12      Oral Agreements, Conversations, and Informal Communications

1.13      Errors or Omissions

 

Section 1050 - Control of Work

 

1.01      Authority of the Engineer

1.02      Authority and Duties of the Engineer’s Authorized Representative

1.03      Cooperation by the Contractor

1.04      Cooperation with Other Contractors

 

1.05      Shop Drawings, Certificates, and Equipment Lists

1.06      Conflict Avoidance

1.07      Examination of Materials and Work

1.08      Removal of Defective Work and Materials

1.09      Unauthorized Work

1.10      Line and Grade Stakes

1.11      Providing Job Site Utilities

1.12      Salvage

1.13      Protection of Water Quality and Wetlands

1.14      Final Inspection and Acceptance

1.15      Additional Contractor Responsibilities

 

Section 1060 - Control of Materials

 

1.01      Materials Source of Supply and Quality Requirements

1.02      Alternate Processes, Equipment, or Materials and Other Substitutions

1.03      Samples and Testing

1.04      Storage of Materials

 

1.05      Unacceptable Materials

1.06      Materials Supplied by the Jurisdiction

1.07      Materials Supplied by the Contractor

 

Section 1070 - Legal Relations and Responsibility to the Public

 

Part 1 - Legal Relations

 

1.01        Municipal Regulations, State, and Federal Laws and Regulations

1.02        Governing Law

1.03        Permits and Licenses

1.04        Patents and Royalties

1.05        Use and Occupancy Prior to Completion of Contract

1.06        Contractor’s Responsibility for the Work

1.07        Responsibility for Damage Claims

1.08        Personal Liability of Public Officials

1.09        Waiver of Legal Rights

1.10        Acceptance by the Jurisdiction - Not a Waiver of Contractor’s Obligations or a
Waiver of the Jurisdiction’s Rights

1.11        Business Organization Requirements

1.12        Consent to Jurisdiction of Iowa District Court or Federal District Court in Iowa

1.13        Severability

 

Part 2 - Responsibilities to the Public

 

2.01        Sanitation

2.02        Convenience and Safety

2.03        Work Area

2.04        Project Area for the Work

2.05        Explosives

2.06        Traffic Control

2.07        Protection of Aboveground and Underground Facilities

2.08        Protection of Property

 

2.09        Land Monuments

 

2.10        Dust Control

2.11        Environmental and Historic Items

2.12        Railroad Crossings

2.13        Borrow and Waste Sites

2.14        Maintaining Postal Service

2.15        Finishing and Cleanup Requirements

 

Part 3 - Bonds and Insurance

 

3.01        Performance, Payment, and Maintenance Bond

3.02        Insurance Requirements

3.03        Contractor’s Indemnity - Contractual Liability Insurance

3.04        Contractor’s Insurance for Other Losses; Waiver of Subrogation

3.05        Property Insurance

3.06        Endorsement Naming Jurisdiction as an Additional Insured / Cancellation and
Material Change / Governmental Immunities Endorsement

3.07        Proof of Insurance

3.08        Notification in Event of Liability or Damage

3.09        Sample Insurance Forms - See www.iowasudas.org

 

Section 1080 - Prosecution and Progress

 

1.01        Subletting or Assignment of Contract

1.02        Contract Time

1.03        Work Progress and Schedule

1.04        Preconstruction Conference

1.05        Notice to Proceed

 

1.06        Weekly Record of Working Days

1.07        Work on Sundays or Legal Holidays

1.08        Temporary Suspension of Working Days

1.09        Extension of Time

1.10        Contractor’s Employees, Methods, and Equipment

1.11        Contractor’s Equipment Identification

 

1.12        Liquidated Damages

1.13        Breach of Contract

1.14        Termination of Contractor’s Responsibility

 

Section 1090 - Measurement and Payment

 

1.01        Measurement

1.02        Scope of Payment

1.03        Lump Sum Breakdowns

1.04        Payment for Change Orders

1.05        Progress Payments

1.06        Payment of Retainage

1.07        Sales and Use Tax Statement

1.08        Acceptance and Final Payment