11.20 FOUNDATIONS
11.21 STAKING AND CHECKING LOCATIONS OF STRUCTURES
The following steps are very important to ensure clearly understood staking control and correct use of the staking provided throughout the construction process:
Any checks suggested by the contractor should be considered, since the site superintendent usually has a good idea of the structure layout in relation to existing features such as trees, old structures, etc. Each stake must be clearly marked to denote its function. Pier numbers must correspond with plan designations. The "INSPECTOR'S HANDBOOK for CONSTRUCTION SURVEY" is a good reference for layout and staking procedures.
Documentation
A staking diagram for each structure must be recorded in a permanent survey field book. This
sketch must show exact location of each hub and the markings made on each guard stake. IT
IS NOT COMPLETE UNLESS IT SHOWS THE MEASUREMENTS MADE AS CHECKS ON THE ACCURACY OF THE STAKING
LAYOUT. Names of those in the staking party should be entered as well as the date, design
and project numbers, location, type of structure, and any other pertinent information.
Common Survey Errors to Avoid
A. Turning the wrong skew angle
B. Errors in measuring from piers to abutments (This should be detected by an overall check from
abutment to abutment.)
C. Centerline of bridge is not always on centerline of road (This is quite common on interstate
bridges.)
D. When using a bench elevation, confirm elevation on prior completed work before setting elevations
for new work. This can eliminate the potential error resulting from incorrect instrument setup, incorrect
instrument readings or the possibility that the bench control has been disturbed.
Encountering Old Substructures
Specification 2401.03 requires the removal
of old structures that interfere with the new work. Existing substructures are usually shown on
the plans. If the designer intended to miss some of these old substructures and the contractor
later encounters them, payment will be made to the contractor by extra work order (EWO) to remove
that portion in conflict. Payment will "NOT" be made if plans indicate the new substructure
would hit the old.
Setting Bench Marks (Post Construction)
During construction many bench marks may be destroyed, and new ones must be set for future use.
Reestablishing bench marks after construction is a responsibility of the project engineer's
survey party. These bench marks must be placed in accessible and readily seen locations. Best
results are obtained by delaying this work until after initial settlement has occurred. It is
recommended to wait for up to one year after construction.
A. Bench Marks for Bridges
B. Bench Marks for Culverts
Inspectors must either physically set the bench mark during parapet finishing or make arrangements to have it set.
11.22 PILING AND PILE DRIVING
B. Cap Weight
C. Pile Length
D. Production Pile Driving
Driving of piling (i.e: concrete, steel H-pile or wood) should typically progress from the interior (center) of the foundation to the outside. This is to reduce the effect of displaced soils becoming trapped and compacted in the center of a pile group. This increasingly compacted soil could cause problems with driving the piles in the center of the group.
Vibratory Hammers
There has been an increase in the number of requests from contractors for approval to use
vibratory hammers to expedite pile installation.
Specification 2501.09, Paragraph D
states that vibratory hammers shall not be used unless approved in writing by the engineer.
Office of Construction and Soils Design have defined the following general criteria to be used in their evaluation of requests for approval of vibratory hammers:
Gravity Hammers
Gravity hammers have been given an upper limit of 2,700 kg (6,000 lbs) by
Specification 2501.09, Paragraph A.
Minimal latitude is allowed, therefore, check the Hammer Data sheet for completeness before
forwarding a request for wave equation development.
A good check for size of gravity hammer is provided in Specification 2501.09, Table "J." Use this table as a guide when checking maximum and minimum size of hammer being requested by the contractor.
For a listing of Gravity Hammers and Caps for both gravity and diesel hammers, refer to Appendix 11-1.
Diesel Hammers
Generally, single acting diesel hammers are the mainstay of contractors for pile driving.
Occasionally however, a contractor will request the use of an "air" or "hydraulic"
operated hammer. In addition there are a few "double acting" hammers in use. A wave equation
analysis will be required for approval of these hammers.
One manufacturer of hammers uses one size hammer barrel and places different sized rams inside. This hammer barrel height has been increased on newer model hammers (ie: Serial Number 911203 and after). Therefore, the MKT "DE" series hammers need to be field verified for ram mass (weight). A check is accomplished by having the contractor stand the hammer upright (in the driving position) and measuring down from top of the barrel to top of the ram. Verify the ram mass (weight) shown on the Hammer Data sheet based on the hammer name and serial number as follows:
MKT DE 33/30/20 |
Prior to S/N 911203 |
Including & After S/N 911203 |
|||
Ram Mass |
Ram Distance± (mm) (in.) |
Ram Distance± (mm) (in.) |
|||
907 | 2000 | 1880 | 74 | 1955 | 77 |
1270 | 2800 | 1220 | 48 | 1320 | 52 |
1497 | 3300 | 790 | 31 | 890 | 35 |
1814 | 4000 | 180 | 7 | 280 | 11 |
MKT DE |
All Serial Numbers |
||
Ram Mass |
Ram Distance± |
||
1 587 | 3 500 | 1371 | 54 |
1 905 | 4 200 | 736 | 29 |
A good check for size of diesel hammer is provided in Specification 2501.09, Table "J." Use this table as a guideline when checking maximum and minimum size of hammer being requested by the contractor.
Bearing and Penetration
A. Penetration Requirements
A depth of expected scour is typically shown on the Bridge Situation sheet in the plans. In general, streams with large drainage areas and sand or gravel stream beds are quite susceptible to scour while streams with small drainage areas and heavy clay stream beds are less susceptible to scour.
When doubt exists concerning the amount of probable scour or minimum pile penetration required, the Office of Construction should be consulted. If greater penetration is required, it will be achieved either by boring holes to receive the piles or by jetting. If penetration achieved is satisfactory, piles will be cut off.
B. Practical Refusal
C. Bearing is Not Achieved
Refer to the Flow Sheet in Appendix 11-2 for information on evaluation of low bearing pile.
Retaps
A retap will be required any time pile do not achieve design bearing. (Refer to
Specification 2501.13, Paragraph E for retap procedure and
number of retaps required). A retap is taking the bearing on pile with the lowest driving resistance
after it has "set" for a period of time. Twenty-four (24) hours is required, however, overnight is acceptable
and sufficient in most cases.
To conduct a retap with a diesel hammer, the hammer should be warmed up on another pile before setting on the pile to be retapped. After two blows to set the cap, count the next 10 blows and measure the distance driven. Convert this to blows per 0.25 m (blows per foot) and determine bearing from the graph. If this meets or exceeds the required design bearing, that pile may be accepted. Indicate on the Log of Piling form a retap value in the appropriate column. There is no need to compute a "set" value and apply this to other piling in that particular foundation. In no case should an average set value be computed and applied to all piling in that foundation. If a retap is conducted on a pile with the lowest driving resistance and it achieves at least design bearing, then all other piling in that foundation may be accepted based on the retap. However if any piling fail to achieve design bearing during retap, the Office of Construction shall be notified.
Dynamic Pile Analyzer
The Office of Construction has a pile analyzer available for driving evaluations. This equipment has
been recently upgraded to include the most current technology in pile analysis. The pile analyzer will
evaluate pile bearing, based on energy delivered to a pile, through the analysis of soil and pile properties
during production pile driving. It will be used not only to verify the driving graph and hammer system,
but also to collect field data to be used to better understand soil conditions during driving. Refer to
Appendix 11-2, Flow Sheet.
There are two situations where the analyzer should be used:
In Case 1, the project engineer needs to contact the Office of Construction to arrange for the analyzer. This contact must allow adequate time (typically at least one week) to schedule the work.
In Case 2, the Office of Construction will determine a need for the analyzer during discussions with the
project engineer to resolve low bearing values. If the analyzer is needed to verify driving results, the
contractor will be paid a lump sum of $250.00 for each pile evaluated. This will be by extra work order to
cover any delay in driving and any extra work needed to help hook up the analyzer to the pile.
A. Mounting Analyzer Sensors
Static Load Tests
The use of Static Load Tests has become almost nonexistent since the Office of Materials
purchased the Dynamic Pile Analyzer and since the Office of Construction switched driving
control to the Wave Equation. However, the only "true" way to know a pile's capacity
is to conduct a static load test.
Today the load test is used to develop comparative data on something new. In 1994, the Office of Bridges and Structures investigated the use of 305 mm (12 inch) concrete pile. Plans where these pile were used had specific directions for location, tip elevation, and driving criteria. For situations where a load test is required that has not been included in contract documents, the Office of Construction will provide guidance for location and driving conditions.
A. Performing Load Test
When a load test is completed, the Office of Materials will provide a test report. Interpretation of the results and any recommendations for the piling will be made by the Office of Construction.
B. Payment for Load Tests
11.23 SPLICING PILE
Only Shielded Metal Arc Welding (SMAW) and Flux Cored Arc Welding (FCAW) will be permitted for welding steel piles.
The welding electrode must be on the approved list published by the Office of Materials semiannually or be specifically approved by the Office of Materials.
B. Shell Pile
C. Pipe Piles
D. Steel H-Piles
If a backing plate thickness of more than 10 mm (3/8 inch) is used, weld the backing plate all around with a fillet weld. A backing plate 6 mm to 10 mm (1/4 to 3/8 inch) thick may be tack welded in place. Backing plates must be bent or ground to fit snug against the flanges, web, and have chambered corners to fit between the flanges and web. The required root opening is 6 mm (1/4 inch) with a tolerance of plus 6 mm (1/4 inch) and minus 2 mm (1/16 inch).
The top of the pile being extended must be cut square with flat ends; the lower end of the extension, both flanges and web, must be beveled to a 45o angle (Figure B, Appendix 11-4). The groove angle in the flat position is to be cut to a 45o included angle as shown in Figure C, Appendix 11-4. The tolerance of a groove angle joint is ±5o. The root face of the weld joints in Figures B and C shall be no greater than 2 mm (1/16 inch). When welding H piles, the web must be welded first.
E. Surface Roughness
F. Pile Alignment
G. Welder Certification
H. Welding Electrode and Preheat Requirements
NOTE: Preheating of electrodes requires an "electrode oven" to be on-site and used!
1. Welding must be done with the same process (SMAW or FCAW) used for qualification.
2. If the operator has qualified on welding ASTM 36 steel,
that same operator is qualified to weld on steel meeting the requirements of ASTM A572 grade 50
(H-pile), ASTM A328 (sheet pile) and ASTM A252 (pipe pile) grade 2 or 3.
3. A welder qualified for manual shielded metal-arc welding with an E 7018 electrode may also weld with
E 7016 and E 7028 electrodes. For welding steel piles, E 7018 and E 7016 electrodes are preferred.
Identifying electrode numbers are as follows:
Preheating of the base metal means that the surfaces of the parts being welded, within 75 mm (3 inches) laterally and in advance of the welding, must be at or above the following prescribed temperature:
Welding when the ambient temperature is below –18o C (0o F) is not permitted. In inclement or windy weather, suitable shielding must be provided to permit welding in the normal manner.
All electrodes having low hydrogen coverings shall be purchased in hermetically sealed containers or shall be dried for at least two hours between 232o C and 260o C (450o F and 500o F) before being used. Immediately after drying or removal from hermetically sealed containers, electrodes shall be kept in storage ovens of at least 121o C (250o F). Electrodes not used within four hours after removal from the drying or storage oven must be redried before use. For the ordinary field pile welding job, electrodes should be purchased in small packages, allowing for use within the prescribed time limit, unless provision for storage at 121o C (250o F) is made.
Preference of E 7016 and E 7018 electrodes for field welding may now be apparent. The digit 1 permits welding in all positions. These electrode coatings are low in hydrogen, permitting use on A36 and SAE 1010 steels without preheating the base metal unless the temperature is below 10o C (50o F). These electrodes are also required for making the prequalification test.
The restrictions and rules for preheating as outlined above cover the welding of all of our steel piling, since they apply to steel up to 19 mm (3/4 inch) thick. If welding is required on thicker plates, other special rules apply. In such case, the Office of Materials should be contacted for assistance.
Electrodes that are allowed for Flux Cored Arc Welding are E60T-1, E60T-5, E60T-6, E60T-8, E70T-1, E70T-5, E70T-6, or E70T-8. When welding ASTM A588 steel, only the E70 series may be used.
Concrete Pile
A. Extending Concrete Pile
After the extension steel is wired securely in place, the forms may be set. Care must be taken to prevent concrete leakage along the face of the pile and to prevent any bulging of the forms. Concrete used in the extension must be of the same quality as used in the original piling. Just prior to placing concrete, the top must have a grout coating to help assure bonding.
B. Splicing 305 mm (12 inch) Concrete Piles
Field evaluation conducted in the summer of 1993 indicates the splicing method is very successful.
11.24 PILING ACCEPTANCE
Steel piling will not be tested for acceptance on every project. Monitor sampling on a random basis will be coordinated by each District Materials Engineer. Testing of random monitor samples will be processed in the Central Laboratory.
Any random test sample that fails to comply with the requirements and tolerances (dimension and mass) will be handled on an individual basis as directed by the Materials Engineer.
Wood Pile
A. Documentation and Acceptance
One or both ends of the piling have 3 marks which identify:
1. Treatment charge number (hammer mark or metal tag - could be on the face of a pile)
2. Inspection agency mark
3. Length of piling
Materials IM-462, Appendix B has a list of inspection agencies approved to supply wood piling to Iowa DOT projects. The piles are identified by the initials of these inspection agencies and the inspector's number. It is important that these inspection identification marks be listed in the inspectors field book, along with a record of material and test reports received for the project.
B. Treating Wood Pile
C. Purchase and Return of Piling
NOTE: On primary projects, it will be Iowa DOT's general policy not to purchase unused piling.
Steel Pile Cutoffs
If the contractor feels the cutoff is long enough that they may use it on some future project, the
Heat number should be placed on the cutoff and a number to indicate the project it came from.
11.25 WAVE EQUATION
Completed data sheets shall be returned to the project engineer for forwarding to the Office of Construction at least 20 days prior to driving piling. Prior to forwarding, the project inspector needs to review the forms for completeness. Such screening will help to eliminate delays later. Check the following:
If a "HAMMER DATA" form is lacking any of the above information, contact the contractor and obtain the missing data before forwarding the data sheet to the Office of Construction.
Once the driving graphs have been produced, the "HAMMER DATA" sheet will be returned with a graph number added in the "FOR OFFICIAL USE ONLY" column. This ties the data sheet to a particular driving graph. Use the data sheet as a field "equipment" checklist.
NOTE: It is mandatory that the inspector verify all hammer data prior to beginning pile driving.
All information is important. Make certain the type, dimension, and thickness of the hammer cushions are correct. If there are doubts about the cushion, check it in the field. Hammer cushions should be inspected periodically during the project to verify thickness and condition. Damaged or deteriorated cushions must be replaced.
Refer to HAMMER DATA forms in Appendix 11-5. Since these forms are not in the Office Supply system, please photocopy as needed.
Driving Graphs
The curves of driving resistance versus blow count, and stress versus blow count, are plotted from
the summary output generated by a computer analysis. Since the results of analysis depend on 1) pile
length, 2) embedded pile length, and 3) the soil "N" values, curves usually are generated for
embedded lengths in 3 meter (10-foot) increments. If the addition of pile causes the length to penetrate
into a new "N" value, a new graph should be developed. If a variable stroke hammer is to be used,
curves will be generated for several stroke heights.
For inspection purposes, the use of driving graphs is extremely easy. Inspectors only need to record the number of blows required to move the pile an equivalent of 0.25 m (1 foot), find that number of blows per 0.25 m (foot) on the "X" axis, read upward to the graphed line representing the appropriate drop height, and record the driven resistance which corresponds on the "Y" axis.
EXAMPLE: Assume: |
(Refer to Example in Appendix 11-6.1) (Given in U.S. units) 1. Hammer drop = 5' 2. Inspector records 80 blows per foot 3. HP 10 x 42 pile |
Question: | What is the driven resistance? |
Procedure: | 1. Find 80 BPF on the "X" axis (Point A) 2. Move vertically upward to the 5' stroke line (Point B) 3. Move horizontally to the "Y" axis (Point C) 4. Read and record 48 tons |
EXAMPLE: Assume: |
(Refer to Example in Appendix 11-6.2) (Given in metric units) 1. Hammer drop = 2.25 m 2. Inspector records 98 blows per 0.25 m 3. HP 250 x 62 pile |
Question: | What is the driven resistance? |
Procedure: | 1. Find 98 blows per 0.25 m on the “X” axis (Point A) 2. Move upward to the 2.25 m stroke line (Point B) 3. Move horizontally to the “Y” axis (Point C) 4. Read and record 712 kN |
NOTE: Driving graphs are produced for a particular location, using a specific hammer, and type of pile. In this example, HP 10 x 42 pile are being driven. Since there are no restrictions listed in the upper left-hand corner of the driving graph, the inspector may use the entire graph. The lack of restrictions means that this hammer is not capable of over-stressing the pile for the plotted strokes and listed blows per foot.
Several important aspects of the driving graph should be noted and observed:
EXAMPLE: Assume:
|
(Given in U.S. units only.) 1. Hammer drop = 5' 2. Retap condition 3. Inspector records 17 blows per 6 inches of penetration |
Question: | 1. What is the value in "blows per foot?" 2. What is the driven resistance for this retap? |
Procedure:
|
1. Convert to blows per foot (BPF) X = 12" 17 6" X = 34 BPF 2. Find 34 BPF on the "X" axis and proceed as in previous example to determine driven resistance |
Log of Piling Driven
The "Log of Piling Driven" form is used on all projects to document relevant "as
constructed" pile information. This report shows a bearing obtained for each individual pile
driven and overall length incorporated into the structure. The project engineer should prepare two
photocopies of the original report:
Before signing the report, the project engineer should be sure the report has been verified through an independent check. A copy of the driving graph needs to be included when information is forwarded for future reference. One way to do this is to photocopy the driving graph on the back of each "LOG OF PILING DRIVEN" sheet. The bearing value of the piles should be recorded to the nearest "readable" graphed bearing value.
The length of piles shown on plans or ordered by the project engineer indicates the desired penetration. Although the specified bearing may have been obtained prior to "full" penetration, driving shall be continued until full penetration is secured so long as a pile can be driven without damage. If specified bearing is not achieved or full penetration is not obtained to within 3 meters (10 feet) of the plan pile length, contact the Office of Construction for review of driving results.
Log down one piling in each foundation of every structure. Logging the first pile in each foundation will provide beneficial information for the contractor and inspector during production pile driving. The logged results represent the actual driving resistance for the full length of the pile as it is driven through successive soil layers. This logged pile driving resistance can be compared with the plan soil profile and soil boring sheets to evaluate driving conditions during production pile driving. This logged pile information will also be important when pile capacity and/or pile penetration problems are discussed with the Office of Construction.
The following are general guidelines for logging pile. If driving is hard, record intervals at 0.6 to 1 m (2 to 3 feet) If little resistance to driving is encountered, 1.3 to 1.5 m (4 to 5 foot) intervals would be sufficient. This information should be entered on a separate log of piling form and forwarded with the production "Log of Piling Driven." The logged piling data should include all the usual information required on the regular Log of Piling Driven.
Refer to "LOG OF PILING DRIVEN" report in Appendix 11-7. These forms are available from Office Supplies (Form 830209). The metric version of the "Log of Piling Driven" (Form 830209M) is included in Appendix 11-7 and is available from the Office of Construction.
A. Filling Out the Report
If welding of piling is necessary (i.e., splicing), add the following information to the
"Log of Piling Driven" form:
1. Name of certified welder(s)
2. Certificate number(s)
3. Date(s) piles were welded
B. Numbering of Piles on Foundation Sketches
Number piles in abutment footings from left to right when facing up station. Also facing up station, number piles in pier footings starting at the upper left corner from left to right and continuing for each row in the footing. Multiple footings can be numbered in the same manner. Single row pile pier bents can be numbered from left to right.
11.26 PREBORED HOLES
Typical Preboring
One purpose of preboring is to reduce and/or eliminate additional load on the pile
as a new grade settles. This phenomenon is referred to as "negative skin friction"
because it acts to drag the pile down and increases required bearing capacity.
Another purpose is to provide lateral movement at the abutment for thermal differences in a moveable abutment structure. In these situations the prebored hole is to be filled with bentonite.
NOTE: In the two examples above (special situations) the hole will be filled with either sand and/or concrete. When preboring is required for penetration, holes will not be filled with bentonite. Also, it will often be necessary to use some type of casing to maintain an open hole. "Sonotubes" or corrugated metal pipe have been used successfully and are recommended when there is a potential for soil collapse.
Bentonite
There are two approved methods for filling prebored holes in non-collapsing soils
with Bentonite:
Process 1
Placing a pipe, extending to the bottom of the hole, on each side of the pile. Filling
the hole about one-third full of bentonite chips and pumping (or pouring) water down
the pipe until free water comes to the top of the bentonite. Waiting about 10 to 15 minutes
before starting the next layer. The time delay allows for initial water absorption. Also
the fill pipe can be raised with each repeat process. (Refer to
Appendix 11-10, Cartoon #1.)
Process 2
Placing water in an empty hole until there is about 0.6 m (2 feet) of standing water.
Then add 0.6 to 1 m (2 to 3 feet) of bentonite chips to the standing water. Wait 10 to 15
minutes and repeat the process until the hole is filled with bentonite. (Refer to
Appendix 11-10, Cartoon #2.)
No matter what method of filling prebored holes is used, the holes should set overnight prior to placing footing concrete. This is to allow time for the bentonite to fully "hydrate" and allow time to check for settling. Holes which have more than 150± mm (6± inches) of settlement will have to be topped off with additional bentonite, while holes which have settled less than 150± mm (6± inches) may be filled with embankment fill.
As per Specification 2501.19, the contractor also needs to provide a rigid cover over the bentonite filled hole to prevent concrete intrusion during foundation pouring.
11.27 DRILLED SHAFTS
Currently, a Supplemental Specification specifies how drilled shafts for bridges are to be constructed.
A. General Types of Drilled Shafts
NOTE: These casings may or may not remain in place after concrete is placed.
Un-Cased
The un-cased shaft can be one of two types:
Several special considerations are required when using drilling mud. Some of these are:
B. Inspection of Drilled Shafts
In addition the Office of Construction has specific reporting forms developed for inspection reporting involving drilled shafts. Blank forms are included in Appendix 11-11. Since they are not available through Office Supplies, please photocopy as needed.