11.20 FOUNDATIONS

11.21 STAKING AND CHECKING LOCATIONS OF STRUCTURES

11.22 PILING AND PILE DRIVING

11.23 SPLICING PILE

11.24 PILING ACCEPTANCE

11.25 WAVE EQUATION

11.26   PREBORED HOLES

    Often pre-bored holes are required as a preparatory step before driving. Preboring involves an augered hole which is a minimum of 100 mm (4 inches) larger than the maximum pile cross-section. Limits of this hole will be shown on the plans.

    Typical Preboring
    One purpose of preboring is to reduce and/or eliminate additional load on the pile as a new grade settles. This phenomenon is referred to as "negative skin friction" because it acts to drag the pile down and increases required bearing capacity.

    Another purpose is to provide lateral movement at the abutment for thermal differences in a moveable abutment structure. In these situations the prebored hole is to be filled with bentonite.

    Special Prebore Situations

    • Another application of a type of prebore would be when driving conditions make it difficult to hold piling "on spot" during driving. Example of such a condition could be a previous demolition site where existing foundations are encountered. In this type of situation the holes are to be filled with dry sand.
    • Yet another application is when subsurface rock is sloped. At such sites there will be a plan note requiring prebored holes. Often these holes will be drilled into the rock, creating a "socket" for the pile to sit in. In these situations the socket and often a portion of the hole will be filled with concrete.

    NOTE: In the two examples above (special situations) the hole will be filled with either sand and/or concrete. When preboring is required for penetration, holes will not be filled with bentonite. Also, it will often be necessary to use some type of casing to maintain an open hole. "Sonotubes" or corrugated metal pipe have been used successfully and are recommended when there is a potential for soil collapse.

    Bentonite
    There are two approved methods for filling prebored holes in non-collapsing soils with Bentonite:

      1. Use powdered Bentonite, mix with water, and fill the hole with a slurry. In this method, the powdered bentonite product used shall be thoroughly mixed with water according to the manufacturer’s recommendations to achieve a minimum of 20 percent solids content.
      2. Use granular bentonite and hydrate the material in the hole. Filling the hole with granular bentonite and adding water can be accomplished by one of the following processes:

      Process 1
      Placing a pipe, extending to the bottom of the hole, on each side of the pile. Filling the hole about one-third full of bentonite chips and pumping (or pouring) water down the pipe until free water comes to the top of the bentonite. Waiting about 10 to 15 minutes before starting the next layer. The time delay allows for initial water absorption. Also the fill pipe can be raised with each repeat process. (Refer to Appendix 11-10, Cartoon #1.)

      Process 2
      Placing water in an empty hole until there is about 0.6 m (2 feet) of standing water.  Then add 0.6 to 1 m (2 to 3 feet) of bentonite chips to the standing water.  Wait 10 to 15 minutes and repeat the process until the hole is filled with bentonite. (Refer to Appendix 11-10, Cartoon #2.)

    No matter what method of filling prebored holes is used, the holes should set overnight prior to placing footing concrete. This is to allow time for the bentonite to fully "hydrate" and allow time to check for settling. Holes which have more than 150± mm (6± inches) of settlement will have to be topped off with additional bentonite, while holes which have settled less than 150± mm (6± inches) may be filled with embankment fill.

    As per Specification 2501.19, the contractor also needs to provide a rigid cover over the bentonite filled hole to prevent concrete intrusion during foundation pouring.

11.27   DRILLED SHAFTS

    Drilled shaft foundations are being used for bridges, light towers, and sign trusses.  Simply speaking, drilled shafts are holes of "X" diameter and "Y" depth filled with concrete. These shafts carry loads in much the same way as do piling, i.e., through skin friction and end bearing.

    Currently, a Supplemental Specification specifies how drilled shafts for bridges are to be constructed.

    A. General Types of Drilled Shafts

      Cased
      This type of shaft is constructed by either first installing a steel casing and removing all soil from within the casing, or advancing a steel casing during a soil removal process.

      NOTE:  These casings may or may not remain in place after concrete is placed.

      Un-Cased
      The un-cased shaft can be one of two types:

        1. Un-cased in non-collapsing soils. This type is commonly encountered where the shaft is rather shallow in depth and the soil will maintain its sidewall integrity.  Here a soil auger is used to drill a hole, required steel is placed, and the hole is filled with concrete.
        2. Un-cased in collapsing soils. This type can be encountered in almost any construction situation. To drill a hole in collapsing soils, the contractor has to keep the hole full of bentonite or polymer and water mixture. The mixture, called drilling fluid/mud, has a unit mass (weight) slightly above that of water and keeps the sidewall from collapsing during construction.

      Several special considerations are required when using drilling mud. Some of these are:

      • The mud must have a known specific gravity.
      • Sand content of mud must be maintained below a specified percentage.
      • All concrete must be tremied or pumped.

    B. Inspection of Drilled Shafts

      Field offices which have a project involving drilled shafts, but no previous drilled shaft experience, may contact the Office of Construction for two videotapes produced by the National Drilling Association.

      In addition the Office of Construction has specific reporting forms developed for inspection reporting involving drilled shafts. Blank forms are included in Appendix 11-11. Since they are not available through Office Supplies, please photocopy as needed.