6.30 EXCAVATION
The inspector should be familiar with all the "Standard Road Plans" listed, in particular RA standards for sewer construction, RB standards for incidental construction, RC standards for erosion control, RE standards for guardrail, RF standards for drainage, and RL standards for excavation and embankment.
Grading plans show cut equals fill plus/or minus shrink or swell respectively. Shrink is the change in quantity from cut to fill and includes subsidence, change from in situ density to compacted density, incidental loss, and all other factors changing density. Swell is the increase in class 12 excavation from ledge rock to broken rock in the fills. The swell factor will include other losses or increases.
SOILS CLASSIFICATION CRITERIA
Class 10
Includes all normal earth materials, such as loam, silt, gumbo, peat, clay, soft shale,
sand, and gravel. Class 10 is subdivided into Unsuitable Soil and Suitable Soil.
UNSUITABLE SOIL - Use Standard Road Plan RL-1
Slope Dressing Only
Type C Disposal - Placed 1 m (3 feet) below top of subgrade in Fills
Type B Disposal - 1.5 m (5 ft) below top of subgrade in fills
Type A Disposal in Fills – 1.5 m (5 ft) below top of subgrade in fills but placed in alternate layers with Type C Unsuitable or Suitable Soil
SUITABLE SOIL
Class 12
Includes granite, quartzite, chert, limestone, sandstone, hard shale and slate. Includes
estimated or measured volumes of boulders.
Class 13
Commonly referred as "Unclassified Excavation." The contract documents will
specify the limits for Class 13.
Select Soils
Must meet all criteria, except proctor, if proctor was not taken.
Cohesive Soil
Granular Soil
These are desired select soil criteria, but may be overridden by Office of Design (Soils Section) if soils meeting these requirements are not found within the project.
6.31 PEAT EXCAVATION
Total Removal of Peat
In this method, the peat is removed entirely down to an identifiable soil layer. Soil sheets in
the plans will identify the soil type found below the peat. If problems in identifying this soil
class are encountered, the Office of Design (Soils Section) or the Office of Construction should
be contacted for assistance.
Partial Removal of Peat
In areas where the peat is very deep, partial removal is designed with an overload
specified to remove most of the settlement which will occur due to the remaining peat.
The Office of Design (Soils Section) has calculated the stability of the area under the
plan requirements; therefore, the plan should be explicitly followed to prevent possible
failure.
To fill the excavated area below water, material with 85% or more sand may be placed without de-watering. Placement of material with less than 85% sand requires de-watering and Type A compaction.
6.32 ROCK EXCAVATION
Because Class 12 excavation requires field judgment, overburden removal should begin near the centerline so the backslope can be adjusted to meet the design template in case the rock elevation is not uniform.
The backslope on rock excavation is usually 1/2:1 except where presplitting is indicated on the plans.
Presplitting is a multiphase blasting operation:
Phase 1: Drill holes into rock ledge
Phase 2: Detonate a "light" explosive charge to prefracture the ledge
Phase 3: Production blasting to remove material and develop a uniform rock face
Presplitting is a part of the Class 12 excavation quantity with the locations shown on the soil cross sections by the 1/4:1 slope. This work may also be tabulated on the "C" plan sheets.
Since Class 12 excavation is a measured item, elevations are required before and after rock excavation.
The “Blasters' Handbook”, a good source of information about explosives, is available from:
Shale is classified as Class 12 excavation and in many cases can be moved in a manner normal to Class 10. Where shale can be handled in a manner normal to Class 10, the shale should be measured and paid for as Class 10. Shale cuts are usually benched and covered with topsoil in accordance with the plans. If unexpected shale is found, the shale should be covered with topsoil if possible.
Payment for "rock pick-up" during stabilizing crop seeding and fertilizing should be measured and paid for as Class 12. If Class 12 is not included as an item in the contract documents, the quantity should be paid for at 10 times the contract price of Class 10 excavation or embankment-in-place item.
6.33 USE OF AND PAYMENT FOR WATER USED FOR EXCAVATION AND EMBANKMENT
and mixed into the backfill material prior to compaction. If water is added, and there is no contract item for water, then it should be paid for as extra work if in accordance with Specification 2102.14E.
For fugitive dust control, see Construction Manual 2.12.
6.34 CONTRACTOR FURNISHED BORROW AREAS
Approval for soil type may be obtained by:
Assuming that the proposed alternate borrow site meets the design criteria for the intended soil type, that all archaeological/historical clearances have been obtained and that the plan site is not a mandatory borrow, an alternate borrow site may be approved as follows:
6.35 PRESERVATION OF CULTURAL RESOURCES
The Code of Iowa, Chapter 263B, requires action be taken to insure that cultural resources are not damaged nor destroyed.
If a cultural site is discovered during construction, the contractor is required to temporarily discontinue work at the site. This is according to the Code of Iowa and to Specification 2102.10. Upon discovering such a site, the project engineer shall notify the Office of Location and Environment (515-239-1225) and the Office of Construction (515-239-1352) of the finding. Iowa Department of Transportation Policy and Procedure 500.17 outlines the procedures to follow.
Contractor Acquired Borrow
The contractor is required to obtain a report from an approved archaeologist concerning
cultural resources on any undisturbed ground to be used for their "contractor acquired"
borrow. The archaeologist’s report shall be provided to the project engineer for review.
The RCE must furnish a copy of the archaeologist’s report to the Office of Location and Environment and receive approval from that office prior to authorizing work to take place in the proposed alternate borrow.
Contact the Office of Location and Environment for a list of approved archaeologists.
The expense of the archaeologist is the contractor's responsibility.