6.50 PIPE CULVERTS BY THE GRADING CONTRACTOR
The culvert inspector should be familiar with the following:
6.51 MATERIAL
Specifications allow the use of corrugated polyethylene pipes for unclassified entrance pipes. The use of polyethylene pipes requires Class B (sand cushion) bedding according to Specifications 2417.02 and 2417.05.
6.52 PIPE INSTALLATION
Bedding
Roadway pipe culverts are bedded according to Class B or Class C requirements depending
on design conditions. Where Class B bedding is specified, the contractor is to overcut
the area on which the pipe is to be placed so a minimum 50 mm (2-inch) layer of sand is
placed between the soil and the pipe. Class B bedding requires that 15 percent of the
pipe height rest on the sand below the bottom of the pipe.
Class C bedding requires that a saddle be constructed on compacted or natural earth so that 10 percent of the height is below the bottom of the pipe. Class C bedding is to be shaped by a template or cut by other means and checked with a template to insure that the pipe culvert is supported for its full length. Proper shaping of the saddle is needed to develop the strength of the pipe and prevent washout.
Unless specifically addressed in the contract documents, Class C bedding is not required for entrance pipes 600 mm (24 inches) or less in diameter.
Class B bedding may be substituted for Class C bedding at the contractor's option.
Joints
Allowable joint openings for Rigid Pipe Culverts are described in Specification 2106.04.E.
If pipe joints are not within these tolerances, the joints are to be encased with concrete
collars (Type C-1 connections).
Joints for corrugated steel pipe let-down structures (Typicals 1401, 1402, 1403, 1501 & 1602) will be made with positive type joint couplings as identified in Materials I.M. 441.
Backfilling
This operation may involve Specifications 2107,
2402.08,
2402.09 and 2416.04D. The inspector
should insure that all applicable sections are followed.
Special attention should be given to culvert wingwalls and flumes to insure proper compaction to prevent erosion and possible washout. The soil should be brought up even with these walls so the surface water will flow over these walls and not along them. Heavy equipment should be kept 1 m (3 feet) or more away from these wingwalls. Compaction within 1 m (3 feet) of the wingwall shall be with pneumatic hand tampers or small hand operated vibratory plate compactors.
Compaction with moisture control is sometimes specified for locations where a culvert is being placed in an existing roadway. This is intended to insure proper compaction thereby reducing settlement. The limits of the moisture control area are detailed in the plans or an area 2 m (6 feet) wide on each side as described in Specification 2402.12A. The 2 m (6 feet) width is specified so type "A" compaction (Specification 2107) is used for this backfill.
Flowable mortar is sometimes included in the plans for backfilling culverts. The plans will identify the locations and show the details for using the flowable mortar. Refer to Construction Manual Chapter 11 for flowable mortar.
6.53 CULVERT ABANDONMENT
6.54 LOAD LIMITS OVER CULVERTS
Note that the equivalent metric units are not included in this section.
Axle loads from hauling equipment shall not exceed the values shown in the following table:
Span (Feet) |
Design Fill (Feet) |
Depth of Fill in Place (Feet) |
Maximum Axle Load (Pounds) |
Under 8 | 0 | 0 | 50,000 |
8 or more | 0 | 0 | 45,000 |
6 or less | 0 or more | 4(minimum) | 80,000 |
8 or more | 4 or more | 4 (minimum) | 80,000 |
6 or less | 0 or more | 5 (minimum) | 100,000 |
8 or more | 5 or more | 5 (minimum) | 100,000 |
6 or less | 0 or more | 6.5 (minimum) | 120,000 |
8 or more | 7 or more | 7 (minimum) | 120,000 |
6 or less | 0 or more | 8 (minimum) | 140,000 |
8 or more | 8 or more | 8 (minimum) | 140,000 |
6 or less | 0 or more | 9 (minimum) | 150,000 |
8 or more | 9 or more | 9 (minimum) | 150,000 |
The “designed fill” or “minimum depth of fill in place” must be in place before scrapers may cross over box culverts. The following are several example explanations:
Hauling with scrapers over pipe culverts is permitted only after the height of fill over the pipe is as tabulated below for scrapers of given weight.
Axle Load | Height of Fill |
80,000 pounds maximum | Equal to its inside diameter but not less than 2 feet |
Over 80,000 pounds to 100,000 pounds maximum |
Equal to its inside diameter but not less than 3 feet |
These restrictions do not relieve the contractor of the responsibility for damage to reinforced concrete box culverts or pipes during the hauling operation.
Axle loads greater than 100,000 pounds may be allowed after specific evaluation. The contractor is to provide the equipment weight information to project engineer. The project engineer then forwards the request to the Office of Construction for evaluation.