Section 2310. Portland Cement Concrete Overlay.

2310.01 DESCRIPTION.
This work consists of overlaying an existing pavement with a PCC overlay. The various types of PCC overlay are as follows:

1. Bonded overlay consists of placing a PCC overlay over an existing PCC pavement.
2. Unbonded overlay consists of placing a PCC overlay over an existing pavement where a stress relief layer is placed on top of the existing PCC pavement or an existing PCC pavement that has been overlaid with HMA (composite pavement).
3. Whitetopping consists of placing a PCC overlay over an existing, full depth asphalt pavement.

The requirements of Section 2301 shall apply to this work with the modifications for each type of work identified below.

2310.02  MATERIALS.

A. Concrete.
Class C concrete shall be used for PCC Overlays as specified in Materials I.M. 529, except a C-3WR or C-4WR mix design shall be required for Bonded Overlays.

The Gradation of coarse aggregate shall meet the requirements of Section 4109, Aggregate Gradation Table, Gradation No. 3 or 5. The nominal maximum coarse aggregate size shall be no greater than one-third of the overlay thickness.

Unless otherwise specified, the coarse aggregate for bonded overlays shall be the same type of aggregate as the existing pavement.

B. Hot Mix Asphalt Stress Relief Course.
The HMA stress relief course for unbonded overlays shall consist of a nominal 1 inch (25 mm) course of HMA meeting the requirements of Section 2303. Asphalt binder shall be PG 58-28. Mixture shall meet 300,000 ESAL, 3/8 inch (9.5 mm), HMA mix requirements, target air voids is 3.0%, no maximum film thickness restriction, and no minimum filler/bitumen ratio restriction. Aggregate shall be Type B with no percent crushed particle requirements and gradation shall fall below the restricted zone.

2310.03  CONSTRUCTION.

A. EQUIPMENT.
Surface preparation equipment used shall be subject to approval of the Engineer and shall comply with the following:

1. Scarifying or Shotblasting Equipment.
Equipment shall be a power operated, capable of uniformly scarifying or removing the existing surface to depths required in a satisfactory manner. Other types of removal devices may be used if their operation is suitable and if they can be demonstrated to the satisfaction of the Engineer. The contract documents will include a pay item for such work.

2. Sand Blasting Equipment.
Sand blasting equipment shall be capable of removing rust, oil, and concrete laitance from the existing surface of the pavement.

B. PREPARATION OF SURFACE.
If full depth base repair is included in the project, it shall be completed prior to surface preparation.

Surface preparation shall include the entire surface to be resurfaced. Materials removed in the preparation operation may be placed in the shoulder area unless otherwise specified in the contract documents.

1. Bonded Overlays.
The surface shall be prepared by shot blasting, or shall be scarified and followed by either shot blasting or sand blasting. Scarification shall be to a nominal depth of 1/4 inch (5 mm).  In either case, the preparation shall be of an extent to remove all dirt, oil, and other foreign materials, as well as any laitance or loose material from the surface and edges against which new concrete is to be placed.

2. Unbonded Overlays.
When jointing is specified in which panels are smaller than a normal lane width, the entire surface shall be scarified to create a roughened surface. This will not apply when a new HMA stress relief layer is constructed as a part of this contract.

Any high spots found in the existing HMA pavement shall be trimmed at the direction of the Engineer. This work would be accomplished during the scarification operation, only at isolated locations, and would be considered incidental to the surface preparation.

3. Whitetopping.
When jointing is specified in which panels are smaller than a normal lane width, the entire surface shall be scarified using a cold-milling operation to create a roughened surface.

Any high spots found in the existing HMA pavement shall be trimmed at the direction of the Engineer. This work would be accomplished during the scarification operation, only at isolated locations, and would be considered incidental to the surface preparation.

C. PLACING AND FINISHING OVERLAY.
The Contractor shall construct the pavement in a manner that will provide a smooth riding surface. Section 2316 shall apply to smoothness of the completed overlay for Primary projects and when specifically required for Secondary projects.

The placing equipment shall be controlled to the proper elevation by string line. Cross sections shall be taken and a grade line established. The Engineer will review and approve the new grade lines.  Information detailing the pavement design thicknesses at the various survey points and material quantities will also be provided. During construction, these grades shall not be altered solely to account for concrete overruns. Some overrun is normal and only with approval of the Engineer will they be adjusted.

1. Bonded Overlays.

a. Surface Cleaning.
Prior to placing concrete onto the surface, the entire surface shall be cleaned with an air blast. After cleaning, no traffic will be permitted on the cleaned surface except that necessary for overlay construction.

b. Surface Condition.
The prepared surface shall be dry to allow some absorption of the concrete mortar.

c. Joints.
The exact location of each contraction and expansion joint in the existing pavement and the joint to be sawed at each full depth patch shall be identified on both sides by a reliable method.

Joints shall be sawed in the resurfacing directly over existing transverse joints. Transverse joints shall be sawed to the full depth of new resurfacing concrete, including depressions created in the existing surface, and as specified in the widening areas. Transverse joints shall be sawed as soon as possible without causing excessive raveling. Joints shall be sawed directly over existing longitudinal joints to a depth of one-half the overlay thickness, with a maximum depth of 3 inches (75 mm).

2. Unbonded Overlays.

a. Hot Mix Asphalt Stress Relief Course.
Compaction shall be in accordance with Article 2303.03, E, Class 1C Compaction except only static steel wheeled rollers shall be used.

b. Surface Cleaning.
The Contractor shall clean the existing surface of all loose or adhering foreign material prior to placement of the PCC over HMA pavement. Normally this will be accomplished with a power broom and shall be available during paving operations to clean loose material that may be tracked onto the surface by the construction equipment.

c. Surface Condition.
The prepared surface shall be dry when concrete is placed on the surface of the HMA pavement to allow some absorption of the concrete mortar. If the surface of the HMA is above 110ºF (40ºC), the Contractor may apply water to the surface of the HMA ahead of the paving operation in order to cool the surface. The water shall be applied far enough in advance of the paving operation that the surface will dry from evaporation before concrete is placed. No water shall be applied to the surface of the pavement when the HMA surface temperature is below 100ºF (38ºC).

d. Joints.
When jointing is specified in which panels are smaller than a normal lane width, the joints shall be 1/8 inch (3 mm) wide with no cleaning or sealing required.

3. Whitetopping.

a. Surface Cleaning.
The Contractor shall clean the existing surface of all loose or adhering foreign material prior to placement of the PCC over HMA pavement. Normally this will be accomplished with a power broom and shall be available during paving operations to clean loose material that may be tracked onto the surface by the construction equipment.

b. Surface Condition.
The prepared surface shall be dry when concrete is placed on the surface of the HMA pavement to allow some absorption of the concrete mortar. If the surface of the HMA is above 110ºF (40ºC), the Contractor may apply water to the surface of the HMA ahead of the paving operation in order to cool the surface. The water shall be applied far enough in advance of the paving operation that the surface will dry from evaporation before concrete is place.  No water shall be applied to the surface of the pavement when the HMA surface temperature is below 100ºF (38ºC).

c. Joints.
When jointing is specified in which panels are smaller than a normal lane width, the joints shall be 1/8 inch (3 mm) wide with no cleaning or sealing required.

D. LIMITATION OF OPERATIONS.
At forecasted air temperatures below 55°F (13°C) the opening time shall be determined using the maturity method. Resurfacing concrete shall not be placed when the air or pavement temperature is below 40°F (4°C).

The Contractor will be permitted to use the shoulders for construction activities. It will be the Contractor's responsibility to repair the shoulders at no additional cost as deemed necessary by the Engineer, to restore the shoulders to a condition acceptable for shoulder work. The Contractor may elect to limit the use and vehicle loadings to minimize this work and its cost.

Bonded concrete overlays shall be placed between June 1 and September 30.

Unbonded overlay and whitetopping materials shall not be placed on any HMA when the pavement surface temperature exceeds 120° F (50°C).

2310.04 METHOD OF MEASUREMENT.
The quantity of the various items of work involved in the construction of PCC overlay will be measured by the Engineer in accordance with the following provisions:

A. Portland Cement Concrete Overlay, Furnish Only.
The quantity of resurfacing concrete furnished will be measured in cubic yards (cubic meters), using a count of batches incorporated. This quantity will include concrete placed in widening sections and partial depth patches.

B.  Portland Cement Concrete Overlay, Placement Only.
The quantity of Portland Cement Concrete Overlay, Placement Only, in square yards (square meters), will be the quantity shown in the contract documents. The area of PCC overlay placement will be determined from the longitudinal surface and the nominal pavement width, including widening sections.

C.  Surface Preparation.
The quantity of Surface Preparation, in square yards (square meters), will be the quantity shown in the contract documents.  The area of surface preparation will be determined from the longitudinal surface and the nominal width of existing pavement.

D.  Hot Mix Asphalt Stress Relief Course.

1. Measurement by Weight (Mass).
When measurement is by weight (mass), the quantity of Hot Mix Asphalt Stress Relief Course will be expressed in tons (megagrams) and determined from the weight (mass) of individual loads, including fillets, measured to the nearest 0.01 tons (0.01 Mg). Loads may be weighed in trucks, weigh hoppers, or from the weight (mass) from batch plants computed by count of batches in each truck and batch weight (mass). Article 2001.07 shall apply.

The asphalt binder will be measured in accordance with Article 2303.05, B.

2. Measurement by Area.
When payment is based on square yards (square meters), the quantity of Hot Mix Asphalt Stress Relief Course, in square yards (square meters), will be the quantity shown in the contract documents.

The quantity of asphalt binder used will not be measured separately for payment.

2310.05  BASIS OF PAYMENT.
For the performance of acceptable work, measured as provided above, the Contractor will be paid the contract unit price in accordance with the following provisions:

A. Portland Cement Concrete Overlay, Furnish Only.
The Contractor will be paid the contract unit price per cubic yards (cubic meters) for Portland Cement Concrete, Furnish Only, as measured above. This payment shall be full compensation for furnishing all raw materials, and for proportioning, mixing, and delivery of concrete to the paving machine.

B. Portland Cement Concrete Overlay, Placement Only.
The Contractor will be paid the contract unit price per square yard (square meter) for Portland Cement Concrete Overlay, Placement Only. This payment shall be full compensation for furnishing all materials, labor, and equipment necessary to place, finish, texture, and cure the concrete, including the placement of tie bars for widening, if required; sawing, cleaning, and sealing the joints, if required; and surface cleaning.

C. Surface Preparation.
The Contractor will be paid the contract unit price per square yard (square meter) for Surface Preparation. This payment shall be full compensation for preparation of the existing pavement, sandblasting or shot blasting, and for removal of the existing pavement surface material in accordance with Article 1104.08.

D. Hot Mix Asphalt Stress Relief Course.
The Contractor will be paid for the asphalt binder in accordance with Article 2303.06, B.

1. Measurement by Weight (Mass).
The Contractor will be paid the contract unit price per ton (megagram) for Hot Mix Asphalt Stress Relief Course as measured above. This payment shall be full compensation for furnishing and placing the HMA stress relief course. The Contractor will be paid separately for the asphalt binder in accordance with Article 2303.06, B.

2. Measurement by Area.
The Contractor will be paid the contract unit price per square yard (square meter) for Hot Mix Asphalt Stress Relief Course constructed.  This payment shall be full compensation for furnishing and placing the HMA stress relief course, including the cost of the asphalt binder.