11.50 CONCRETE
(STRUCTURAL, CLASS X, AND FLOWABLE MORTAR)
11.51 PCC PLANT PAGE (FORMS 800240E and 800240M)
11.52 USE OF READY MIXED STRUCTURAL CONCRETE
Inspector's Checklist
A. Specifications regarding plant inspection, equipment approval, and batching operations should be reviewed
for familiarity. In addition to proper plant calibration, the inspector should verify that each truck mixer
used on the job has a current certification as required by
Specification 2001.21, Paragraph B and Materials I.M. 528.
It is good practice to inspect a random sample of ready mix trucks that will be used on the job, verifying
that the certification accurately reflects the truck's condition. Truck certification numbers should be
recorded in the inspector's diary and will need to be reverified at least every 30 days. Required information
to be recorded on ready mixed concrete truck batch tickets shall be according to
Construction Manual Section 9.03.
B. Batching and mixing should be limited to the lead truck until slump and air content have been tested for conformance with specifications. Contractors may make preliminary tests at the plant, but project acceptance is based on job site tests. It is intended that the ready mix plant supply concrete to the construction site that conforms to all applicable specifications at the point where the acceptance sample is taken.
Specification 2403.03, Paragraph A states for Structural Concrete: "Concrete shall be placed with a slump between 25 mm and 75 mm (1 and 3 inches) as a target range, allowing a maximum of 100 mm (4 inches) ..."
Specification 2403.03, Paragraph B states for
Structural Concrete:
"... unvibrated structural concrete shall be 6.5 percent, as a target value, with a maximum variation
of plus 1.5% or minus 1.0%." Note: As stated in I.M. 318, an adjustment
to the target air content called an aggregate correction factor may be required for some aggregates obtained
from quarries in
Example: For structural concrete specified air content is 6.5% plus 1.5% or minus 1.0%. For an aggregate correction factor of 1.0%, the target would be 7.5% (7.5% equals a specified target of 6.5% plus aggregate correction factor of 1.0%) plus 1.5% or minus 1.0%.
If concrete is being delivered which deviates much from these target values, the contractor is responsible for taking corrective action to bring the mix to within target values. Even if the current mix is within specified limits. The intent of the tolerance is to provide latitude during placement for unforeseen changes in materials, mixes, and placement methods. Placing concrete "consistently" near a tolerance limit is not desirable and warrants additional sampling.
What is important, is the contractor's response to test results approaching tolerance limits. Continually having to add water and/or air agent to each load at the site will not be permitted. If such practice is occurring, the inspector shall notify the contractor (or whomever was designated as "the" responsible individual in charge of the concrete at the site). Ultimately, it is the contractor's responsibility to initiate immediate corrective action.
Non-responsiveness on the contractor's part is reason to initiate sampling and testing of each truck or halt placement. The purpose for additional testing is to ensure that no noncomplying materials are incorporated into the project.
In some cases admixtures, such as water reducers, are required to be added in split doses or sometimes totally at the site.
C. All Structural Concrete
If the first load is close to a limit value, it is recommended to sample and test the second load unless site experience indicates it is not necessary.
NOTE: Only the District Materials Engineer has authority to approve decreasing (less frequent) testing frequencies from those listed in Materials I.M. 204. PLAN AHEAD and obtain approval for those cases where a variance would be reasonable.
NOTE:
When concrete is placed by means other than directly from the back of the truck, the sample shall
be taken, if possible, after the concrete has passed through the conveyance method being used. (This
includes placement by bucket, belt, pumps, power buggies, etc.)
In an attempt to bring noncomplying concrete into compliance, the supplier may make field adjustments (i.e., add air entraining agent, add portland cement, or rotate the drum). Such "field" adjustments shall be an EXCEPTION and not the general rule and the 90 minute time restriction shall not be waived for any situation.
2. For all noncomplying test results the inspector shall immediately notify the contractor or their representative in charge of the concrete. This notification shall also inform the Contractor if noncomplying materials have been incorporated into the structure.
3. If test results indicated noncomplying materials have been incorporated, the inspector shall make a note in the diary indicating the test results, approximate volume incorporated, location the material was placed, and to whom the notification was given. The inspector should also note a noncomplying event on that particular truck's delivery ticket.
At the end of each day or each placement event (whichever is sooner) the inspector shall prepare a Noncompliance Notice (Form 830245) for all noncomplying material incorporated and not removed/replaced during that day or placement event. This notice shall be given to the Contractor yet that day (Materials I.M. 204).
4. When noncomplying materials are found, the inspector will a) hold each truck, and b) initiate sampling and testing of each truck until two consecutive loads meet specifications. At this point, sampling and testing may return to normal project acceptance frequency.
D. Specifications and Materials I.M.s spell out requirements that materials must meet to be acceptable. Further, Materials I.M. 204 identifies a frequency for sampling/testing and whether the test is an acceptance or assurance test.
Authority for initially rejecting noncomplying materials and poor quality work performance is given to the inspector in Specification 1105.07. This rejection authority is only superseded by the project engineer. There is an old saying to the effect, "We shall not knowingly incorporate noncomplying material into a project." This means exactly what it says and there is ample support in the specifications for this position.
E. During placements, the inspector should alternate sampling among the various trucks involved in the operation.
F. If there is a specific truck which is identified as causing a problem with consistency, that truck shall be rejected from further use. (Refer to Specification 2001.21, Paragraph B.)
G. Transit mixers shall be completely emptied of wash water before reloading. If the truck's top fill hopper is washed after loading, no wash water shall be allowed to enter the mixer.
H. When it is not practical to sample at the last point prior to incorporation, then a method of correlation between point of placement and the actual point of sampling must be developed. While such cases should be the EXCEPTION and NOT THE GENERAL RULE, one approved method is as outlined below:
When concrete reaches a stable consistency and is within target ranges, correlation tests can be run between the last practical sampling location and the place of deposition. If differences are consistent, then correlated tests can be taken at the last practical sampling location.
The following is a guideline if tests are not consistent:
Test a minimum of three loads of concrete sampled from the "last practical sampling location" and at the point of discharge. Average the difference between the test results. This average (correction factor) is used until another correlation is determined. Correlation tests should be determined, as a minimum, at the beginning, middle, and toward the end of a pour. The inspector needs to factor in situations such as size of pour, changing weather conditions, changes in conveyor length, changes in pumping configuration or pipe angles, and changes in batch proportions when determining frequency of correlation tests.
All subsequent "acceptance" tests are taken at the last practical sampling location and are adjusted using the correlation factor.
All correlation tests and correction factors are to be documented in the field books and noted on the "PCC Plant Page" (Forms 800240E and 800240M) or on a sheet attached to the form. Results reported using correction factors shall be identified with an asterisk (*) or written note.
I. The inspectors will need to satisfy themselves regarding compliance with the specifications for the number of drum revolutions at mixing speed.
J. If water, air entrainment, or other admixtures are added at the project site, acceptance testing will not be performed until all additions have been made AND 30 revolutions at mixing speed have been completed following the change.
11.53 ADMIXTURES
The amount of any admixture used in a mix should be as recommended by the manufacturer and verified through laboratory testing or trial mixes. Effectiveness of an admixture depends upon such factors as type, brand, and amount of cement; water content; aggregate shape; gradation and proportions; mixing time; slump; and temperatures of concrete and air.
Air Entraining Admixtures
Air entraining admixtures are used to purposely entrain microscopic air bubbles in concrete. Air
entrainment will dramatically improve the durability of concrete exposed to moisture during cycles
of freezing and thawing. Entrained air greatly improves concrete's resistance to surface scaling
caused by chemical deicers.
Water Reducing Admixtures - Regular
Water reducing admixtures are used to reduce the quantity of mixing water required to produce concrete
of a certain slump or reduce the water-cement ratio. Regular water reducers reduce water content by about
5% to 10%.
Adding a water reducing admixture to a mix without reducing water content can produce a mixture with a much higher slump.
Water Reducing Admixtures - Super Plasticizers
Super plasticizers are simply "high-range water reducers." They are added to concrete with
low-to-normal slump and water content to make high slump "flowable" concrete. Flowable concrete
is a highly fluid, but workable concrete that can be placed with little or no vibration and can
still be free of excessive bleeding or segregation. Flowable concrete has applications:
Retarding Admixtures
Retarding admixtures (retarders) are used to delay the initial set of concrete. High temperatures
of fresh concrete 30oC (85oF) and up often cause an increased rate of hardening.
Since retarders do not decrease the initial temperature of concrete, other methods of counteracting
the effect of temperature must be used.
Retarding admixtures require a concrete temperature of 13oC (55oF) or greater in order to activate and effectively retard the set of concrete. If the proposed placement cannot be accomplished within the initial set time for non-retarded concrete, the concrete mix temperature will have to be increased through the use of heated materials. When heated materials are used, it is recommended that a concrete mix temperature of 18oC (65oF) be targeted for effective activation of retarding admixtures.
Accelerating Admixtures
Accelerating admixtures (accelerators) are used to accelerate the setting time and strength
development of concrete at an early age. Strength development can also be accelerated by using:
Calcium Chloride (CaCl2) is the material most commonly used in accelerating admixtures. Besides accelerating strength gain, calcium chloride also causes an increase in drying shrinkage, potential reinforcement corrosion, discoloration, and potential scaling.
Corrosion Inhibiting Admixtures
Concrete protects embedded steel from corrosion through its highly alkaline nature (12.5 pH).
This causes a passive and non-corroding protective oxide film to form on steel. However, carbonation
or the presence of chloride ions from deicers, can destroy or penetrate the protective film. Once
this happens, an electronic cell (very small battery) is formed and an electro-chemical process
of corrosion begins. This process ultimately forms rust. Rust is expansive (up to 4 times original
volume). This induces internal stress and eventually causes spalling to occur.
Corrosion inhibiting admixtures chemically inhibit the corrosion reaction. Calcium nitrite, the most commonly used inhibitor, blocks a corrosion reaction by chemically reinforcing the concrete's passive film.
Finely Divided Mineral Admixtures
These admixtures are powdered or pulverized materials added to concrete to improve or change the
properties (plastic or hardened) of concrete. Based on the mineral's chemical or physical properties,
they are classified as: (1) Cementitious, (2) Pozzolans, (3) Pozzolanic and Cementitious, and (4) Nominally
inert. Typical PCC mix designs use #3 above.
Pozzolanic Materials
A pozzolan is a siliceous or aluminosiliceous material that in itself possesses little or no
cementitious value but will, in finely divided form and in the presence of water, chemically react
with the calcium hydroxide released by the hydration of portland cement to form compounds possessing
cementitious properties. Pozzolans include fly ash and silica fume.
Fly Ash (Class C & F)
Fly ash is a finely divided residue that results from the combustion of pulverized coal in electric
power plants.
Silica Fume
Silica fume, also referred to as micro-silica or condensed silica fume, is another material
that is used as a pozzolanic admixture. This light to dark gray powdery product is a result of
the reduction of high-purity quartz with coal in an electric arc furnace.
Fly ash and silica fume have a spherical shape. Silica fume has an extremely small particle size (about 100 times smaller than the average cement particle). Although silica fume is normally in powder form, because of its small size and increased ease of handling the product is commonly available in liquid form.
Cementitious Materials
Cementitious materials are substances that alone have hydraulic cementing properties (set
and harden in the presense of water). Cementitious materials include ground granulated blast
furnace slag.
Ground Granulated Blast Furnace Slag
(GGBFS)
GGBFS made from iron blast-furnace slag is a non-metallic product consisting essentially of
silicates and aluminosilicates of calcium and other bases developed in a molten condition
simultaneously with iron in a blast furnace. The molten slag is rapidly chilled in water to
form a glassy sandlike material which is ground to a particle size similar to fly ash. Unlike
fly ash and silica fume which have a spherical shape, GGBFS is rough and angular-shaped.
11.54 USE OF INSULATED FORMS FOR PROTECTION
Concrete must be between 7oC and 27oC (45oF and 80oF) when placed. To ensure a concrete temperature of at least 10oC (50oF) for 48 hours after placement, the concrete for thin sections such as culvert walls, end posts, piling encasements, etc. should be 18oC (65oF) or higher, since the only additional heat source is the heat of hydration. Concrete for massive sections such as stub abutments, heavy piers, and footings should be in the 13o to 18oC (55o to 65oF) range.
Since only dry insulation is effective, any insulation that has a propensity to adsorb water or become saturated must be protected with a waterproof membrane. The insulation system must provide complete coverage and be secured to provide maximum protection during the full curing period.
For typical protection applications, insulated forms must be left undisturbed for 96 hours before being removed. (Refer to Specification 2403.11.)
Checking Temperature of Concrete
For checking compliance with minimum temperature requirements during the 48-hour period after placement,
thermometer wells should be cast in the concrete during the pour. The following procedure for checking
temperature is suggested:
NOTE: The thermometer stem should be inserted about 75 mm (3 inches) into the concrete because the sensitive portion of stem is about 70 mm (2 3/4 inches) below the groove.
Other acceptable methods for monitoring concrete temperature are the use of maturity meter with temperature probe wires embedded in the concrete or use of thermal ‘iButtons’ embedded in the concrete with exposed wires for data collection and recording.
Record temperature daily for 48 hours following the pour. Temperature readings below 10oC (50oF) during the first 48 hours should be reported to the Office of Construction for evaluation of possible damage or price adjustment.
11.55 DECK PLACEMENT AND HEAT OF HYDRATION
Deck Placement
Sometime ago the Office of Bridges and Structures, Office of Materials, and Office of
Construction began evaluating the phenomena of bridge deck cracking. Measures have been
implemented to manage bridge deck placement and prevent cracking through the use of Evaporation
Rate Controls.
Research continues in the management of quality bridge deck placements and deck cracking control. To provide needed site specific data for this research, Forms E122, E139, M122 and M139 were developed. These reporting forms were initiated during 1991. Since that time, the information provided from the field has been compiled into a database for evaluation. The evaluation of this data is ongoing and includes review of the effectiveness of Evaporation Rate Controls and possible trends which may lead to a better understanding of crack development.
Forms E122, E139, M122 and M139 are included in Appendix 11-16. Since they are not available in Office Supplies, please photocopy as needed. Submit completed forms to the Office of Construction.
Deck Concrete Temperature and Curing
Specification 2412 identifies requirements for placing and curing concrete bridge floors.
Of importance for this section are:
NOTE: A theoretical evaporation chart is included in
Specification 2412.05. As an alternative, a computer program has been developed for calculation
of theoretical rate of evaporation using Excel. This program incorporates the charts from the specifications
in a formula table included on report Forms E122 and M122. The program simplifies the determination of the
theoretical rate of evaporation and enables the user to perform trial evaluations for possible changes in
air temperature, relative humidity, plastic concrete temperature, and wind velocity. A copy of the Excel
program for theoretical rate of evaporation is available at
English -
http://www.iowa.dot.gov/construction/structures/theoretical_evaporation_rate.xls
or
Metric -
http://www.iowa.dot.gov/construction/structures/theoretical_evaporation_rate_metric.xls
The placing of concrete will require close monitoring to comply with the specification. The contractor or ready mix plant should determine temperature of previously placed concrete to project a mix temperature prior to a deck pour. Further, they should obtain a weather report to determine predicted air temperature, wind velocity, and relative humidity for the pour day. Based on this information, you will be able to reasonably predict an evaporation rate.
The above information should be discussed by the inspector, contractor, and ready mix plant operator before a deck pour. The pour should not be attempted if concrete temperature is predicted at 29o C (85oF) or higher and predicted air temperature is above 32oC (90oF). Also, the pour should not be attempted if an evaporation rate would exceed 1 kg/m2/hr. (0.2 lbs./sq.ft./hr.).
District Materials Office has sling psychrometers and wind gauges available for usage the day of the pour. A sling psychrometer is used to determine the relative humidity by finding "wet" and "dry" bulb temperatures. (Refer to Charts in Appendix 11-17.) With these values, compute temperature difference and locate the "Difference Between Readings..." column. Then locate the row labeled with appropriate dry bulb temperature. The value at the intersection of "Difference" column and "Dry" bulb temperature is the relative humidity.
There are also electronic pocket weather meter/station devices (ie: Ketsrel) which is a hand-held instrument for air temperature, wind speed, and relative humidity determination which can be used for evaluation of the theoretical evaporation rate.
Placement Considerations
A. If there is any doubt about the concrete temperature exceeding 29oC (85oF),
the contractor needs to identify measures which will be implemented to keep mix temperatures within
specifications. If the contractor is not prepared to maintain a mix temperature below specifications,
the pour should be postponed.
NOTE:
1. No payment will be made for methods taken to keep concrete temperatures and evaporation rates
within specifications.
2. If pour has to be delayed because of temperature, and pouring is the controlling operation,
no working days will be charged.
B. Location of permissible headers should be discussed with the contractor. If during the pour, it appears:
Case B. (Noncontinuous beams, negative section)
Case C. (Noncontinuous beams, negative section)
Case D. (Continuous beams, negative section)
See Appendix 11-24 for case illustration.
In every case listed above, contact the Office of Construction for curing times and beam break strengths before allowing the contractor to resume deck placement.
Field Documentation
The temperature of concrete should be taken as soon as concrete is placed. It should be taken
when the first load is placed and at intervals shown on Forms E122 and M122,
Appendix 11-16. Additional checking is warranted if
temperature is running at or near maximum. Air temperature should also be taken about the same
time as the concrete temperature.
Heat of Hydration
Occasionally, projects will require placement of large volumes of concrete for individual
concrete elements (ie: bridge footings, columns, pier caps, etc.). Controlling the temperature
of this large volume is important to reduce cracks and potential premature deterioration from
thermal cracking that can result from a large temperature difference between the center of the
concrete element and its surface. In these cases the contract documents may require monitoring
the "heat of hydration." There will also be requirements for the differences between specified
monitoring locations. For example: "The temperature difference between the edge of the concrete
and the center shall not exceed 10oC (35oF)."
The cooling of large volumes of concrete can take considerable time, and during that time monitoring is required. A form to record these temperatures has been developed. (Refer to "Heat of Hydration" form in Appendix 11-18.) Since this form is not included in Office Supplies, please photocopy as needed. Submit completed forms to the Office of Construction.
11.56 PLACEMENT METHODS (PUMPING, BELTING, AND CRANE BUCKET)
General conditions which must be avoided, or at least severely minimized, are as follows. If one of the following cannot be avoided, at least be aware of the condition, and be sure to conduct additional testing should any of the conditions present themselves.
Crane and Bucket
In the past it was felt the crane and bucket placement method did not adversely affect concrete.
This is now in question when viewed from loss of air and potential segregation. Therefore, this
method will now also require testing at the placement location, if practical.
Belt Placement
Belt equipment is typically used to convey concrete to a (1) lower, (2) horizontal, or (3) somewhat
higher level.
Pump Placement
The modern mobile pump with hydraulic placing boom is economical to use in placing both large
and small quantities of concrete. These units are used to convey concrete directly from a truck
unloading point to the concrete placement area.
Rules-of-Thumb for Pumping
11.57 FORM REMOVAL
B. No beams may be set on pedestal (T or P10A) piers until the cap concrete is 7 days old and modulus of rupture is at least 3,800 kPa (550 psi) or more. The contractor has the option under Specification 2403.03 to substitute Class M concrete mix for Class C except in bridge floors. When Class M concrete mix is used, beams may be set when the cap concrete is 3 days old and the modulus of rupture is at least 3,800 kPa (550 psi) or more. (Refer to Specification 2403.19 .) If no test beams are made, the time must be extended to 14 days. (Refer to Specification 2403.18.)
There have been special situations where the contractor has been allowed to set beams on piers that have not attained the above strengths. In these cases, the bottom forms have remained in place for an extended period of time. Before approving any variance, contact the Office of Construction for approval.
C.On stub abutments or integral abutments, steel beams and girders may be set as under A above. Concrete beams on stub abutments or integral abutments, same as A above. (Stub abutments are abutments with battered piling, sliding bearings, and the abutment does not move. Integral abutments have vertical piling in prebored holes, beams are rigidly connected to the abutment, and the abutment moves.) On full abutments (solid and continuous from spread footing), same as A above.
11.58 CLASS 3 CONCRETE SURFACE FINISH (RAIL AND BEAMS)
Approvals of this material will be on the basis of legible brand markings on the containers. Periodic sampling and testing will be the responsibility of the Office of Materials. The type used on any structure should be included in the project documentation.
Application of Finish
Surfaces to be given a Class 3 finish must first be given a Class 2 strip down finish immediately
after removal of forms. Successful application and adhesion of any type of finish to concrete
surfaces is dependent on concrete condition and concrete surface preparation. Factors such as
pH of the concrete, concrete moisture content, cleanliness of the concrete surface, and concrete
surface profile are all critical to ensuring any coating being applied will securely adhere.
For additional information and guidance contact the Office of Construction.
Materials for a special surface finish should be mixed to a uniform condition, preferably with a power mixer. When using a power mixer, add dry ingredients to the liquid. One worker should place the material with a steel trowel, making sure it is pressed firmly into all voids and leveled. When the surface is set so it will not roll or lift, a second worker should smooth the surface uniformly with a rubber float.
Concrete Railings
Surfaces of concrete for barrier rails placed against fixed forms, either on site or in precasting,
shall be given a surface finish described for exterior beams in
Specification 2407.14 before application of curing. This should be done
as the forms are removed. The contractor may opt to broom (brush) finish the slipform barrier rail.
11.59 FLOWABLE MORTAR
Depending on the application, samples of sand, cement, and fly ash may need to be submitted to the Office of Materials for a mix design. (Refer to Specification 2506.02 for information as to when material will meet the required flow time as measured with a flow cone.) Free water in the sand pile must be considered as mix water because a mix design uses oven dried sand.
Refer to Appendix of Materials I.M. 491.17 for approved fly ash sources and classes.
The success of all flowable mortar projects depends on establishing uniform under-drainage.
Where flowable mortar is to be placed against joints, the joints should be: (1) wrapped with a fabric as per Specification 4196.01, Paragraph B, or (2) sealed with a gasket, or (3) sealed with roofing cement.
If the contractor uses crushed limestone for granular backfill, it shall meet the requirements for Granular Backfill. (Refer to Specification 4133.01.)
Remember flowable mortar is a liquid which has a density of about 2,136 kg/m3 (3,600 lbs./cu yd.) until the water has dissipated. Bulkheads should be strong enough to withstand those pressures.
Under normal conditions, flowable mortar should be set-up sufficiently within 24 to 48 hours for placement of the final lift of either earthfill or special backfill. If "set-up" does not occur or if it seems slow, typically the problem relates directly to drainage of the granular backfill. Often contamination or "dirty" granular backfill is the culprit. Check to be sure it is draining. If not, additional time will help. If time is critical, you may have to physically cut trenches (drainage paths) into the flowable mortar.
Backfilling Culverts - Typical Grading
For backfilling culverts, flowable mortar is used above the granular backfill elevation
identified on the plans. There should be a 100 mm (4 inch) subdrain typically located at the
culverts flow line elevation. This subdrain is placed to facilitate draining water from the
flowable mortar. Therefore, for culverts with buried flow lines, the subdrain will need to be
placed in the granular backfill at the lowest elevation possible and yet allow drainage.
Flowable mortar will nominally be placed 0.6 m (2 feet) thick over the entire culvert excavation. Plans, or typicals, define the area used to calculate plan quantities for flowable mortar and granular backfill. (Flowable mortar plan quantities should include 30% additional for anticipated consolidation of the granular backfill and shrink due to loss of water.) If the Contractor opts to excavate a larger area than assumed for plan quantity, additional excavation, backfill, and flowable mortar will not be considered for pay. We will however, require additional excavation to be backfilled in a manner as identified by the plans or typicals.
Placement of flowable mortar shall always be computed from "top down." This means allow for:
There are two general installation situations.
Situation 1:
Distance between the top of culvert and bottom of pavement is greater than 0.9 m (3 feet), but less
than or equal to 2.5 m (8 feet). In this situation, the top of granular backfill will vary from
0.6 m (2 feet) below top of culvert to 1.5 m (5 feet) above the culvert top.
Example:
In this example, cover is less than 2.5 m (8 feet), granular backfill is placed from bottom of excavation up to elevation 29.1 m (97 feet).
Situation 2:
Distance between "top of culvert and bottom of pavement" is greater than 2.5 m (8 feet). In this situation:
A) the top of granular backfill will be fixed at the elevation of culvert top, B) 0.6 m (2 feet) of flowable
mortar will be placed directly on top of the granular backfill, and C) compacted earthfill will be placed
between flowable mortar and special backfill. In this example, the earthfill will have a minimum thickness
of 1.5 m (5 feet) and no theoretical maximum thickness.
Example (Using English units only)
At this point you must now calculate from the culvert top, up to the bottom of the earthfill.
4. Top of culvert, for this example, is assumed to be Elevation 86.
5. Granular backfill is fixed at the culvert top (Elevation 86).
6. 2 feet of flowable mortar is required. (Elevation is 86 + 2 = 88.)
In this situation, earthfill is placed from the top of flowable mortar (Elevation 88) to bottom of special backfill (Elevation 99). Specifically, 11 feet of earthfill is required. (Elevation 99 - 88 = 11 feet)
Plugging Culverts
For culverts 20 m (60 feet) or less in length, flowable mortar may be placed into the
outlet first, then the inlet. For culverts more than 20 m (60 feet) long, the desirable
spacing for placing flowable mortar should be 20 m (60 feet). The optimum travel of flowable
mortar is 10 m (30 feet) with approximately 75 mm (3 inches) of fall in the surface. To avoid
drilling through pavement, the spacing can be increased to 25 m (80 feet) if necessary.
Backfilling Culverts - Under Bridges
Prior to installing flowable mortar, the culvert must be backfilled with granular backfill
to at least 75 mm (3 inches) over the culvert or 1.5 m (5 feet) below the lowest bridge elevation.
As this granular backfill is placed, the outside fill should be brought up at the same time with
soil.
Flowable mortar used for backfilling culverts under bridges is placed in two stages.
In the first stage, flowable mortar is placed to an elevation about 150 mm (6 inches) below the bottom of bridge deck or the beams whichever is lower. Bridge beams should be fitted with Styrofoam filler to full width of the flanges. Refer to illustration in Appendix 11-25. This will prevent adding dead load to the beams with flowable mortar.
In the second stage, flowable mortar is placed through holes drilled in the deck at spacings identified in the plans or specifications. Typically, begin at one abutment and continue longitudinally down the bridge until the other abutment has been reached, filling all holes on one side of the centerline. Then begin on the other side of the bridge and work holes nearest the centerline and proceed to the outside.
After flowable mortar has been placed, the contractor is required to saw a minimum of 75 mm (3 inches) deep cut into the original deck before any sidewalk, curb, or handrail is removed. It is important that this 75 mm (3 inch) saw cut be done prior to any curb removal, thereby preventing damage to the deck.
Placing flowable mortar under a bridge can be accomplished during staged construction. The specification requires a 72-hour delay between stage 1 and stage 2 placement of flowable mortar to allow for settlement of the granular backfill.
Filling Voids Between Culverts
If there is room to place granular backfill between culverts, do so to one-half the new culvert height.
In situations such as multiple barrels, or a new pipe inside a box, the granular backfill will adequately
maintain pipe location during flowable mortar placement.
If granular backfill cannot be used, culvert(s) should be blocked at 3 m (10 foot) intervals or less and flowable mortar placed as usual. If a pipe inside a culvert has to be blocked in place, the blocking must be situated in a manner to prevent damming and causing voids in the mortar. All blocking placed on the top of the inside culvert must be saddle shaped to fit the culvert. This distributes the buoyant forces over a larger area and reduces chance of pipe buckling. To further reduce buoyant forces:
In all cases, a drainage system must be established on each side of the culvert(s). The drainage system should be a 100 mm (4 inch) slotted drain with a minimum of 150 mm (6 inches) of granular backfill cover. The drainage system reduces buoyancy effects and allows for dewatering of the flowable mortar.
Inspect all pipe joints and lifting holes for looseness and voids. Two approved repair methods are: