6.10 SITE PREPARATION
6.11 CLEARING AND GRUBBING
Indiana Bats (Myotis sodalis) are included on both the federal and state endangered species list. The U.S. Fish and Wildlife Service considers all counties south of Interstate 80, including those portions of Dallas, Polk, Jasper, Poweshiek, Iowa, Johnson, Cedar, and Scott counties south of Interstate 80, as being within the potential range of the species in Iowa.
Projects south of Interstate 80 requiring tree removal are subject to review for Indiana bat habitat. No action is necessary for projects south of I-80 that do NOT involve tree removal. It is intended that during the project development process, project corridors located in these counties be assessed for possible Indiana bat habitat if clearing or grubbing is needed.
Refer to Appendix 6-1(a) for the Iowa DOT Indiana bat habitat documentation form and Appendix 6-1(b) for the procedure guide based on guidance from the Iowa DNR and US Fish and Wildlife Service.
If suitable Indiana bat habitat is present, the US Fish and Wildlife Service and the Iowa DNR must be contacted by the Office of Location and Environment. In addition, clearing of trees is not allowed between April 15 and September 15. The Office of Location and Environment should be contacted if suitable habitat is present and may be consulted if there is any question regarding the assessment for Indiana Bats.
A copy of the completed Iowa DOT documentation form, Appendix 6-1(a), is to be submitted to the Office of Location and Environment. Additionally, the District may request that Office of Location and Environment complete habitat surveys and data forms.
There may be considerable elapsed time between an estimate of clearing and grubbing and the actual work. If actual site conditions are different than those shown in the contract documents, the following suggested resolutions are provided:
The rules prohibit open burning of any material in the following specific localities: Cedar Rapids, Marion, Hiawatha, Council Bluffs, Carter Lake, Des Moines, West Des Moines, Clive, Windsor Heights, Urbandale, Pleasant Hill and portions of Cerro Gordo County.
Local ordinances may be more restrictive than the Iowa DNR rules, and not allow burning of any clearing and grubbing waste.
Other options for disposing of grubbing and clearing waste include:
The contractor shall formally request permission to bury stumps within the project limits. The Department is not obligated to provide a location on the project to bury the stumps. The project engineer may allow disposal by burial on the project based on the following:
Area Clearing
This method of clearing and grubbing is intended for use in heavily timbered areas such
as relocated alignments and borrow areas. Area clearing is not usually intended for use on
reconstruction projects or where individual trees need to be cleared and/or grubbed.
The locations for area clearing and grubbing are to be specifically identified. Example of location identification may be "From Station 100 to Station 250, Right Side, Borrow A."
The unit of measurement for clearing by area is hectare (acre). If the identified area is right-of-way line to right-of-way line, this is the area to be measured for payment even though the actual clearing and grubbing may be less.
Selective Clearing
All desirable trees between the right-of-way line and the need line shall be preserved,
provided they are not within the clear zone or cause restricted sight distance. Trees which
have more than one-third of their root system removed will normally not survive, therefore,
these trees should be cleared and grubbed.
Trees are important for erosion control and slope stabilization, as well as enhancing the appearance of the completed highway.
Desirable trees and shrubs include oak, hackberry, cherry, maple, hickory, ash, sycamore, linden, walnut, plum, all evergreens, as well as many other trees. In most cases cottonwood, willow, and box elder should not be preserved unless they serve to reduce soil erosion. If there are any questions concerning trees to be saved, the project
engineer should consult the Office of Design (Roadside Development Section) for guidance.
The method of measurement for selective clearing is units. The quantity for payment is a calculation derived from measurements taken of the various sized trees and stumps, hedge rows, bushes, growing corn, and field fence.
Preliminary
Estimate for Clearing Right of Way (Form 650014)
The project engineer shall arrange to have a preliminary estimate made of the clearing
and grubbing required for a proposed construction project. The project engineer is to
transmit this information to the "designer in charge" on the form entitled
"Preliminary Estimate for Clearing Right of Way" (Form 650014). The "designer
in charge" is usually from the Office of Design, but on selected projects may be from
the Office of Bridges and Structures. Plan sheets detailing the proposed clearing "by
area" should also be included. The Office of Design or the Office of Bridges and
Structures must receive this information at least 12 weeks prior to the project letting.
Clearing and grubbing should be discussed on the design field exam.
A separate preliminary estimate for clearing shall be made for each project and broken down into divisions as shown on the plans. Use "Statement of Clearing and Grubbing" (Form 830312) or Computer Form 103 as "work sheets." Retain these "work sheets" in the project engineer's file. Do not forward copies of these work sheets to the Office of Design or the Office of Bridges and Structures.
Method of Payment
The method of payment for clearing and grubbing is based on the contract unit price multiplied
by the measured quantity (hectares/acres or units).
Contract Unit Price Contract Quantity Total Item |
= = = |
$2.50 2,149.50 Units $2.50 X 2,149.50 = $5,373.75 |
For progress payments, the number to be entered on the progress vouchers will be that portion of the 2,149.50 which was completed.
6.12 REMOVAL AND DISPOSAL OF OLD PAVEMENT
Where existing PCC pavement would be located within 1.2 m (4 feet) and 1.8 m (6 feet) of the proposed profile grade, the PCC pavement will be required to be broken up and left in place. If the existing pavement has been resurfaced, the hot mix asphalt resurfacing will be removed by scarification.
PCC pavements may be used as Class D or Class E Revetment, if requirements of Article 4130 are met. Use should be approved by the District Materials Engineer.
For pavements where the existing PCC pavement will be more than 1.8 m (6 feet) below the proposed profile grade, the pavement will normally be left in place. If asphalt resurfacing is present, it shall be removed.
6.13 DISPOSAL OF HOT MIX ASPHALT PAVEMENT
Salvaged hot mix asphalt (HMA) pavement may be used as special backfill material. When intended for special backfill material, the HMA pavement is normally removed by scarification. The material must pass a 50 mm (2-inch) sieve. A vibratory steel wheel roller or pneumatic tired roller is commonly used for compaction.
6.14 DEMOLITION