6.60 SUBDRAINS
Subdrains are used for tile relocations, backslope drains, longitudinal and cross drains under the roadway area.
Subdrains are also used with granular blankets to develop a drainage layer in areas where the soil has a high moisture content and poor stability.
6.61 TILE RELOCATION
Where two or more lines cross the right-of-way, it is better to keep them separate. If the tiles are flowing the same and elevations are nearly the same, a single pipe crossing may be used with junction boxes on both sides, provided the single pipe has adequate capacity.
Be sure the downstream tile exits the junction box at the same elevation.
Inspection pipes with caps are required to be installed in subdrains near each right-of-way line. The purpose of the inspection pipes is to allow access to the subdrain line to verify flow within the right-of-way. The vertical pipe is to be a 100 mm (4-inch) diameter PVC pipe. These inspection pipes are incidental to the price bid for subdrain.
A useful resource is the final report of “Field Tile Issues in Highway Construction” by the Benchmark Steering Team, DOT Office of Construction. A copy is available on in the “Construction/Process Improvement Teams” folder on the Local Area Network. Also available in each RCE Office is an Iowa State University Extension agricultural drainage manual entitled “The Iowa Drainage Guide”.
6.62 BACKSLOPE DRAINS
6.63 LONGITUDINAL DRAINS
Inspection considerations must include:
Outlets
All outlets should be inspected prior to backfilling. The pipe coupling
should be inspected to assure proper installation. The flow line of the
outlet should be checked for uniform downward grade toward the ditch. All
outlets are to be marked with an orange fence post.
Some projects require that existing subdrain outlets be extended, for example, on a shoulder widening project. On these projects, the contractor must remove the existing rodent guard before extending the pipe.
Porous Backfill
Porous backfill material must be in contact with the base of the pavement
for the subdrain system to operate correctly. This may require handwork by
the contractor. No soil shall remain between the pavement edge and the subdrain
trench.
Pipe Stretch
Specifications require that subdrain pipe shall not be stretched in excess
of 105%. Polyethylene pipe is delivered to the project in rolls of an identified
length. Periodic inspections should be made to insure the pipe is not stretched
more than 5% during installation. Excessive stretching will weaken the pipe and
possibly cause the pipe to rupture or crush during backfilling.
Moisture Content of the Porous Backfill
The porous backfill material is to be in a surface wet condition. If the material
is too dry, the contractor shall be required to add water to the material.
The Office of Materials (Special Investigations Section) possesses a video camera with a 90 m (300-foot) probe. The camera is capable of being placed into subdrains for the purpose of monitoring and inspecting the installation. The project engineer may request a video inspection by contacting the Special Investigations Engineer.