9.20 PAVEMENT JOINTS
In multi-lane construction, it is important that jointing be reviewed and discussed prior to the start of paving operations. Jointing in multi-lane construction can be very difficult especially when intakes and utility accesses are present. It is very important to establish correct jointing within the first pass of multi-lane paving to insure correct joint alignment in future, adjacent lanes of pavement.
9.21 JOINT SAWING
For transverse joints on a conventional pavement slab, the saw cut should be stopped before the blade reaches the edge of the slab. The joint opening at the surface of the pavement should come within an inch of the edge of the pavement. By stopping shy of the edge, there is less chance of the saw “blowing out” a spall on the edge of the slab. This also prevents the joint sealant from running down the face of the pavement.
9.22 CLEANING JOINTS
When sandblasting is required,
Specification 2301.25 requires the sandblast wand to have a means to positively
guide the nozzle along the actual joint line. This is to insure that sandblast passage does
not miss any of the joint face. Evidence of a non-guided nozzle can be seen when sandblast
passage shows as a wavy line on the pavement surface.
9.23 SEALING SAWED JOINTS
Joint Filling
Due to pavement crown, hot poured asphaltic joint material sometimes flows out of the joint
leaving an opening below the pavement surface which allows entrance of sand and dirt into the
joint opening. This will cause spalling of joint edges when pavement expands. To insure a properly
filled joint across the entire pavement width, the Contractor is required to seal the joint opening
at the pavement edge. This helps to prevent sealant from flowing out of the joint opening. Refer to
Standard Road Plan RH-51 for appropriate
joint edge treatments.
All joint sealant materials should be placed so that the top edge is from 3 to 9 mm (1/8 to 3/8 inch) below the pavement’s surface. Excessive filling of transverse and longitudinal joints can result in excessive sealant material being forced out of the joint and soiling the pavement surface.
Excess sealant material should be removed from the pavement surface prior to project acceptance.
Sealing Equipment
Hot poured asphaltic joint material can be overheated in hot pour kettles. An overheated sealant has
lost its elasticity and will prematurely fail. Tiny bubbles appearing on the surface of the sealant
after it is placed in the joint can be an indication of overheating. Thermometers on hot pour kettles
need to be checked and replaced if necessary. Calibrated thermometers are available from
the Office of Materials (515-239-1433) to use in checking contractor’s thermometers.
Backer Rod
Backer rod is approved on a brand name basis. Approved backer rods are found in
Materials I.M. 436.04. To monitor
manufacturer quality control, a 300 to 600 mm (1 to 2 feet) long piece of backer rod
may be sampled from each project and sent to the Office of Materials.
9.24 RESERVED FOR FUTURE USE
9.25 CD, ED, EE & EF JOINTS, AND OTHER DOWELED SUPPORT ASSEMBLIES
Expansion Joints
Cross-sectional shapes of preformed joint material different that the shape shown on
Standard Road Plan RH-52 are
available. These may also be used with Project Engineer approval. For pavements thinner
than 200 mm (8 inches) in depth, joint material may need to be shortened appropriately.
Material should be removed from the bottom side only to fit thinner pavement sections.
For thicker pavement sections, additional expansion joint material may be added to the
bottom of the joint to achieve the correct total joint depth.
For expansion joints that extend through a curb section, install preformed joint material the full width of pavement through the curb. Do not attempt to bend material to fit the shape of the curb. The opening in curb section above the top surface of the joint material may be filled with a solid piece of joint material cut to the same shape as the curb.
Bond Breakers
Specification 4151 requires smooth dowel bars to be coated with a bituminous
or paraffin based bond breaker prior to delivery to a project. A bond breaker is
necessary to prevent concrete from adhering to the dowel bars which cold lead to
locking of the joint and possible random cracking.
Often dowel assemblies are fabricated several months before they are incorporated into a project. The assemblies are then delivered to, and stored on, the project site, and the bond breaker becomes weathered. Bituminous bond breakers are especially susceptible to weathering.
Prior to being incorporated into a project, dowel assemblies should be inspected to ensure that the bond breaker is in good condition. If the bond breaker is cracked, dry or has a weathered appearance, steps should be taken to ensure that the dowels are adequately coated to prevent bonding with concrete. With approval of the Project Engineer, any of the following procedures may be followed to reestablish a bond breaking coating:
Note: Form oil may wash away during a rain event. Dowel assemblies should be recoated if a rain event occurs after application of form oil and before paving.
Dowel Tolerances
To permit pavement slabs to move longitudinally on the subgrade during expansion and
contraction, dowels must be parallel to both centerline and the surface of the pavement.
Specification 2301.12 discusses dowel
placement tolerances. Dowel assemblies should not be permitted to remain in place if wire
supports cannot hold dowels in correct alignment.
Dowel Assembly Placement
When placing assemblies on subgrade, contractors use the bottom support wires of the
assembly to serve as a guide for bar alignment. This is not objectionable provided bars
are fabricated at proper angle to he wire supports. Assemblies should be inspected for
proper fabrication when delivered to the project.
Contractors shall not be permitted to block up or support the assemblies on bricks or other means to obtain proper height of dowel bars. When a paving project has two different slab thicknesses requiring load transfer devices, the Contractor shall furnish correct height basket dowel assemblies specifically fabricated to position bars at mid-depth in slab for each slab thickness.
At the Contractor’s option, the temporary wire fasteners, which hold some assemblies together for shipping, may or may not be cut after installation and prior to paving. This applies to baskets fabricated in accordance with the RH-55 Road Standard with only three #10 gauge tie wires per basket. Often baskets are fabricated with additional tie wires to ensure stability of the basket when handling and placing. This is an acceptable practice as long as the tie wires in excess of the 3 required are cut prior to paving. The Contractor is responsible to insure both proper alignment of the bars and the prevention of random cracks. Therefore the decision as to whether to cut or not cut the wire fasteners should be made with the goal of preventing both misalignment and random cracks.
Check for movement of assemblies during passage of the slipform paver. If properly set, side forms of the paver should not come in contact with the ends of wire bar supports. Check to insure vibrators on the paver or finishing equipment are set to proper height so vibrators do not touch steel during passage over assemblies.
Workers who position steel and vibrate concrete must not step on joint assemblies. Assemblies must be firmly anchored to subgrade or subbase with a minimum of eight stakes per 3.6 m (12 foot) width (Standard Road Plan RH-58) to resist horizontal and vertical movement during concrete placement and subsequent finishing operations.
Marking Joint Locations
Prior to paving, a point or line representing the midpoint of the dowels in an assembly must
be marked on
Dowel midpoint markings should then be transferred to the concrete surface. This may be accomplished with a string line marking plastic concrete or by use of a chalk line after concrete has hardened. This should insure that the transverse joint will be sawn over the center of the dowel bar basket assembly. Do not permit the saw operator to “eyeball” joint sawing from one edge of slab to the other.
Blanking Bands
Specification 2301.16A requires a
blanking band be used to blank out the transverse texture over the center of the dowel
assemblies. Care needs to be taken to ensure that the blanking band is correctly located
over the center of dowel assemblies. Using a blanking band will ensure a smooth, nontextured
pavement surface at midpoint on the dowel assembly. When longitudinal texturing is used,
no blanking band is required.
9.26 LONGITUDINAL JOINT DESIGN
Joints should be constructed as shown on plans, unless the Standard Road Plans allow for alternates. Any requests by the Contractor for joint substitution should be submitted to the Office of Construction for review.
The Standard Road Plans show the required joint dimensions for the various types of pavement joints. It should be noted for longitudinal joints that only a single T/3 depth sawcut is shown. This depth can only be sawn by a conventional type of concrete saw. Longitudinal joints should not be sawn by an early green-concrete saw.
Standard Road Plan RH-51 details the different types of longitudinal joints. This Standard Road Plan discusses the only joint types that may be interchanged. All other joints shall be constructed as shown on the plans.
The KT-2 and KT-3 joints include both a keyway and a tie bar to hold two adjacent lanes together. It is the combination of the keyway and tie bars that provides proper load transfer between adjacent pavement lanes. It is important to check that the proper sizes of keyway and tie bars are being provided to insure proper performance of the joint. Keyway and tie bar sizes are shown on Standard Road Plan RH-51. The end of the bar that is placed in the concrete during the first pass shows an optional bent detail. This detail is included to support the end of the bar on the subgrade when it is placed in the plastic concrete. An alternate support would be to place the horizontal bar on a chair in the plastic concrete. Supporting the end of the bar with a shovelful of plastic concrete or a rock will not ensure that the tie steel remains horizontal during its passage through the slipform paver. This practice
Tie Bar Placement
Because the steel placed in L and KT joints is intended to hold two adjacent
lanes together, it is very important that the bars be placed in a manner
that will assure that they will perform as intended. The most important
aspect of placing tie steel reinforcement is to ensure that the concrete is
consolidated around the bar after being placed so that adequate pull out
strength is achieved to resist the tendency for the two pavement sections to
pull away from each other over time. Whether the bars are straight or bent,
or placed by a mechanical inserter or by hand, the concrete must be
consolidated around the bar to ensure proper anchorage of the bar in the
hardened concrete.
Typically steel for L joints is inserted by mechanical methods in front of the finishing machine or directly behind the vibrators and in front of the pan on the finishing machine when using slip form placement methods. This is an acceptable practice and achieves the desired end result since the finishing machine imparts vibration into the pavement through the pan which consolidates the concrete around the bar.
When placing steel for KT joints, contractors often insert the steel through a side form on the finishing machine when slip form placement methods are used. Other methods have included use of formed steel keyway slipped through the side form of the finishing machine from front to back. Either method is an acceptable practice as the concrete is consolidated around the bars either through vibration imparted into the mix from the side forms or the vibrators themselves.
Tie steel should not be inserted behind the finishing machine by mechanical or hand methods without consolidation of the concrete around the bar.
9.27 LONGITUDINAL JOINT (L JOINT) TIE-STEEL INSPECTION
Procedure
The following “L” joint tie-steel inspection procedures will be required on all
paving projects where centerline or lane line tie steel is either manually or
mechanically placed in plastic concrete:
Frequency
To insure compliance with proper joint design parameters, use the following minimum
frequencies:
The checked areas of hardened concrete should not overlap previously checked plastic concrete areas.
Tolerance
Minimum placement tolerances for purpose of initiating retrofit correction only are as follows:
a. The centerline L-1 and L-2 joints and any lane line joint of multilane pavements should have a minimum of
Out-of-Tolerance
If previously mentioned inspection procedures discover out-of-tolerance tie steel, the Contractor
has the following options to remedy the problem:
Contractors may do any combination of these remedies, at their own expense, to avoid retrofitting tie steel. Any remedies described above shall be approved by the Project Engineer.
After two days of inadequate correction procedures, the Contractor will be required to use positive placement procedures (basket assemblies or bar supports) for remaining "L" joint tie-steel areas on project.
The Office of Construction should be immediately informed of any tie-steel placement problems.
Retrofit
If a project is determined to have out-of-tolerance tie steel according to previously mentioned
guidelines, the Contractor is required to suggest a tie-steel retrofit procedure. All retrofit
corrections shall include replacing tie steel such that the final retrofit panel has the required
number of bars per panel as shown on Standard Road
Plan RH-51. Prior to correction, the Project Engineer shall submit the Contractor's retrofit
correction procedure to the Office of Construction for approval. The Contractor may suggest retrofit
correction by any method, such as bar-in-slot or the cross-stitch procedure described as follows:
Drill 22 mm (7/8 inch) diameter hole transversely across joint at a horizontal angle of approximately 0.6 radians (35 degrees) measured from pavement surface. Use a low impact hydraulic drill, mounted on a guide that will assure hole is drilled at proper angle. Drill hole deep enough to properly accept a #20 (#6) x 300 mm (12 inch) epoxy coated bar. Use care not to over drill so that drill does not break through underside of pavement. Drill holes on alternating sides of joint line at designed tie-steel spacing, taking care to avoid any in-place bars. Epoxy grout shall meet requirements of Materials I.M. 491.11, Appendix A.
Air blast hole free of drill residue with oil free air. Place epoxy grout in hole in a quantity that will fill hole to within 6 mm (1/4 inch) of pavement surface when bar is inserted.
Pavement can be opened to construction or public traffic when grout is tack free.
Price Adjustments
In addition to the retrofits required above, all areas of pavement with out-of-tolerance tie steel
shall be price adjusted according to Construction Manual 2.53.