Section 2530.  Partial Depth Finish Patches

 

2530.01     description.

 

A.    Remove pavement in areas designated in the contract documents or by the Engineer to be patches. This includes furnishing and placing patching material to provide a new traffic surface, and restoring the adjacent shoulder as shown in the contract documents. This work is in areas where the size, shape, and depth of patch depends on the extent of pavement deterioration and shall be determined during the removal operation.

 

B.    Partial depth finish patches may be identified and constructed as one of the following types:

 

1.     Partial Depth PCC Finish Patches.

These patches are square or rectangular in shape. They will be less than 6 feet in length when placed on a longitudinal or transverse joint or random crack. Removal may be by milling or other equipment. This type of patch will be identified by tabulation in the contract documents. The size and location for each lane will be shown.

 

2.     Partial Depth PCC Joint and Crack Repair Patches.

Joint and crack repairs are square or rectangular in shape. They will be placed at a longitudinal or transverse joint or random crack. They will be a minimum of 6 feet in length, and will be identified by tabulation in the contract documents. Size and location will be shown. Repair size and location may be adjusted to fit field conditions.

 

3.     Overdepth Patches.

Overdepth patches are irregular in shape. They are placed to the full depth of existing pavement in areas of unsound concrete as designated by the Engineer. Repair size and location will be determined at time of construction.

 

4.     Partial Depth Regular HMA Finish Patches.

These patches are in the shape of a square or rectangle. They have square corners and straight edges to allow almost all of the removal by a milling machine. An air hammer or saw may be necessary to complete removal along edges and at corners. This type of patch will be identified by tabulation in the contract documents. The size and location in each lane will be shown.

 

5.     Partial Depth Irregular HMA Finish Patches.

These patches are not square or rectangular in shape. They have at least one side that is not straight or one corner that is not square which will prohibit complete removal by a milling machine. Other equipment such as an air hammer or saw may be necessary to accomplish the removal. This type of patch will be identified by tabulation in the contract documents. This tabulation will be an estimate of the number of patches per lane mile, and the estimated total area of patch.

 

2530.02     materials.

Meet the requirements for the type of material specified.

 

A.    Hot Mix Asphalt Patching Material.

Unless stated elsewhere in the contract documents, use HMA meeting or exceeding Section 2303 requirements for a Standard Traffic (ST) 3/8 or 1/2 inch surface mixture. Use an asphalt binder that meets or exceeds PG 64-22S or PG 58-28S. For partial depth patches on HMA overlay projects, the binder grade specified for mainline intermediate or surface course may be substituted.

 

B.    Portland Cement Concrete Patching Material.

Meet one of the requirements below. When patching encroaches on an adjacent lane which is open to traffic or when there is patching on two lane pavements or other locations where overnight closures are not permitted, use Class A or Class B patching material. On pavements with three or more lanes and where overnight closure is permitted, use Class C patching material.

 

1.     Class A Patching Material.

a.     Use a modified Portland cement type manufactured to provide rapid set and high early strength. Meet the requirements of Materials I.M. 491.20.

b.     When a mortar is furnished, add the manufacturer’s recommended quantity of coarse aggregate.

 

2.     Class B Patching Material.

a.     Use high early strength rapid set (5 hour) PCC meeting the requirements of Materials I.M. 529 and the following requirements:

·         Use Class M mixture patching material with calcium chloride. Class M mixtures with calcium chloride are not to contain fly ash.

·         When calcium chloride is used in a mixture, place the concrete within 30 minutes after the introduction of the calcium chloride.

·         For coarse aggregate, use crushed carbonate stone chips or pea gravel, minimum Class 2 durability, meeting requirements of Section 4112.

b.     When Class B patching material is furnished for partial depth patches, it may also be furnished for full depth patches.

 

3.     Class C Patching Material.

a.     Use a PCC mixture with an early set that will allow time of opening to traffic in 24 hours to 36 hours as directed by the Engineer. For coarse aggregate, meet the requirements for Class B patching material. Use Class M mixture meeting the requirements of the current Materials I.M. 529 without the addition of calcium chloride.

b.     When Class C patching material is furnished for partial depth patches, it may also be furnished for full depth patches.

 

4.     Modifications to Mixtures for Class B and Class C Patching Material.

Apply the following modifications to the PCC mixtures for Class B and Class C patching material:

a.     Slump.

1)    Slump, measured according to Materials I.M. 317 prior to addition of calcium chloride solution, is to be between 1 inch and 2 1/2 inches as a target range, allowing a maximum of 3 inches. If calcium chloride solution is not to be added, the slump is to be between 1 inch and 3 inches as a target range, allowing a maximum of 4 inches.

2)    When a Type A Mid Range water reducing admixture is used, the slump, tested prior to the addition of calcium chloride, is to be between 1 inch and 4 inches as a target range, allowing a maximum of 5 inches.

b.     Air Entrainment.

The entrained air content of the unconsolidated concrete will be determined according to Materials I.M. 318, prior to addition of calcium chloride if it is to be added. When calcium chloride is to be added, air entrainment is to be 5.0%, with a tolerance of ± 2.0%. When no calcium chloride is to be added, air entrainment is to be 6.5%, with a tolerance of ± 1.5%.

c.     Temperature.

The temperature of Class B patching material, as delivered to the job site, is to be as required in Article 2530.02, B, 4, d below. Ensure the temperature of Class C patching material, as delivered to the job site, is greater than 65°F. Heating the water, aggregate, or both, may be necessary to meet this requirement. The cost of heating is incidental to patching.

d.     Cement.

1)    For Class M concrete mixtures, meet the requirements of Section 4101.

2)    Refer to Table 2530.02-1 for cement types and maximum allowable substitution rates. The maximum substitution for Type IS is not to exceed 25%.

 

Table 2530.02-1: Cement Types and Maximum Allowable Substitution Rates

Patch Class

Cement Type

 

Maximum Allowable Substitution

Minimum Mix Temperature

B

Type I, II, IL

Type IS, IT

0% Fly Ash

0% Fly Ash

75ºF

80ºF*

C

Type I, II, IL

Type IS, IT

10% Fly Ash

0% Fly Ash

65ºF

70ºF*

*       When a Type A Mid Range water reducing admixture is used, limit the minimum mix temperature to that required when Type I/II cement is used.

 

e.     Calcium Chloride.

1)    Where calcium chloride is required, furnish it in water solution form and add it to the mix at the job site. Use a commercial 32% calcium chloride solution, or equivalent, prepared according to Table 2530.02-2:

 

Table 2530.02-2: Proportions for 32% Calcium Chloride Solutions

Type of Solid Calcium Chloride

 

 

Pounds of Solid per Gallon of Water

Solution Produced per Gallon of Water

Type 1 – Regular Flake (77% material)

6

1.3

Type 2 – Concrete Flake or Pellets (94% material)

4.5

1.2

 

2)    The Engineer will check the solution concentration using a hydrometer according to Materials I.M. 373. Add the solution at the rate of 3.0 gallons per cubic yard of concrete. Calcium chloride solutions of different concentrations may be approved by the Engineer, provided appropriate adjustments in the total concrete composition are made.

3)    Agitate the mixture until the calcium chloride is completely in solution, and continue agitation, as necessary, to maintain uniformity.

4)    Except when using continuous mixing equipment described in Article 2001.20, E, ensure the calcium chloride solution is present in the mix for at least 2 minutes of mixing.

f.      Water Reducer.

A Type A Mid Range water reducing admixture may be used. Use one listed in Materials I.M. 403, at the manufacturer’s recommended dosage.

g.     Aggregate Durability.

Unless specified otherwise, use coarse aggregate of the proper class of durability, as defined in Article 4115.04.

h.     Transit Mix Concrete.

Use a mix from a plant from which the concrete can be delivered and placed within 60 minutes from the start of mixing. The time may be extended to 90 minutes when a retarding admixture, used according to Materials I.M. 403 including temperature dosage guidelines (and at no additional cost to the Contracting Authority), is added at the plant. Continuous mixing equipment using volumetric proportioning may be used according to Article 2001.20, E.

i.      Prepackaged Mixture.

A prepackaged mixture, proportioned as specified above for Class B or Class C matching material, may be furnished as a Class B or Class C patching material with the Engineer’s approval. The coarse aggregate for prepackaged mixtures is limited to that meeting the requirements of Article 4115.05. Mix prepackaged mixtures in an on-site paddle type mixer or proportion and mix with continuous mixing equipment using volumetric proportioning according to Article 2001.20, E.

 

C.    Joint Boards.

Comply with the following:

 

1.     Joint boards for recreating joints and cracks: use a resilient filler, cellulosic fiber, paraffin coated cardboard, or other compressible material of the proper shape to recreate the joint during placement of the patch material.

 

2.     Boards for recreating transverse joints: one piece. One piece boards will not be required in lengths exceeding 6 feet.

 

3.     Boards for recreating longitudinal joints: one piece. One piece boards will not be required in lengths exceeding 4 feet.

 

4.     Joints and open transverse cracks: use a board with a nominal width of 1/4 inch. Metal strips may be used for narrow cracks.

 

5.     Extend boards and metal strips into the pavement to the bottom of the patch.

 

6.     Use of a bond breaker on board surfaces is encouraged.

 

D.    Joint Sealer.

Use joint sealer and backer rod meeting the requirements of Section 4136. Unless specified otherwise, use only hot poured joint sealer.

 

E.    Tack Coat Bitumen.

For HMA patches, use tack coat bitumen as specified in Article 2303.02, E.

 

2530.03     construction.

 

A.    Equipment.

 

1.     Remove existing surface material using a milling machine, jack hammers, or similar equipment. Hand equipment may be necessary to achieve a vertical edge and the designated shape.

 

2.     The following additional equipment is required for PCC patches:

a.     Sandblasting equipment for cleaning of the prepared patch area on PCC pavements.

b.     15 pound (or less) air chisel to complete patch area preparation. A 30 pound air chisel may be used if its use does not result in significant damage to the patch area and edges.

c.     Air compressor that emits oil and moisture free air for cleaning the prepared area.

d.     On-site paddle type concrete mixer for mixing Class A patching material or other prepackaged mixtures.

 

B.    Partial Depth Finish Patch Construction.

 

1.     General.

a.     The tabulations for partial depth finish patches shown in the contract documents are for estimating purposes only. The Engineer will designate the location and limits of these patches.

b.     The shape and depth may be irregular so that hand operated equipment may be necessary for all or some of the removal.

c.     Remove the existing pavement material within the designated area to sound concrete as determined by the Engineer. All material removed not designated for salvage becomes the property of the Contractor and shall be removed according to Article 1104.08.

 

2.     Hot Mix Asphalt Patches.

Construct partial depth HMA finish patches as follows:

a.     Preparation of Patch Area.

1)    Remove material to a minimum depth of 3 inches. Where this depth is adequate, make the prepared surface relatively even. The maximum depth is 75% of the pavement thickness, but no more than 9 inches.

2)    Remove material so that the edges of all patch areas are vertical to a depth of 1 1/2 inches. Minor rounding of the bottom edge is permissible. Cut and remove exposed reinforcing steel. Clean the patch area.

3)    Where removal to the depth described above leaves unsound concrete within the limits of the patch area, the Engineer may designate a part of the patch area as a full depth patch. Remove the concrete for the full depth, but removal to a depth greater than 12 inches will not be required. Consolidate the subgrade or subbase material with a mechanical tamper or other compaction equipment as directed by the Engineer.

b.     Placing HMA Patch Material.

1)    After removal of the old pavement, lightly tack the edges and bottom of the patch area. Deposit and compact the HMA patch mixture in layers as follows:

a)    Deposit the upper 5 inches in at least two layers, with the top layer not exceeding 2 inches in thickness, when compacted. Lifts should be at least 3 times the mixture size.

b)    Thoroughly compact each layer, while hot, using appropriate compaction equipment. Succeeding layers may be placed as soon as the preceding layer has been properly compacted.

c)    Smooth the final layer with a steel tired finish roller meeting requirements of Article 2001.05, B or F. A roller meeting requirement of Article 2001.05, F, may be a small roller suitable for this type of operation.

d)    Ensure the final compacted surface is level with, or not more than approximately 1/4 inch above, the surrounding pavement.

2)    Open the patch to traffic after the mixture has cooled to provide stability; however, on two lane roadways, do not leave barricades in place overnight. If the patch becomes distorted beyond the smoothness requirements for any reason, smooth the surface within 1 working day by blading, scraping, filling, or by other approved means.

3)    Prior to final acceptance, a finish patch shall be level with, or not more than 1/8 inch above, the adjacent pavement, and have a smooth riding surface.

c.     Sealing Joints and Cracks.

1)    Seal all edges of HMA patches to a width of 3 inches centered on the edge. Use CRS-2 bitumen applied with a "V" shaped squeegee tool. Blot excess bitumen material with sand.

2)    When joint and crack sealing work is part of the contract, saw joints and cracks that cross areas of HMA finish patches to a width of 1/8 inch to 1/4 inch. Saw to the depth of the patch with a maximum depth of 3 inches. Perform this work within 3 working days after placement.

 

3.     Portland Cement Concrete Patches.

a.     Preparation of Patch Area.

1)    Remove concrete in designated repair area to a minimum width of 12 inches using either of the following methods:

a)    Mill transversely or longitudinally matching general alignment of patch. Use a mill that produces patch edges with a 30 to 60 degree angle or chip back patch edges to a 30 to 60 degree angle. Chip out secondary spalling resulting from milling at no additional cost to the Contracting Authority. 

b)    Place 2 inch saw cuts along perimeter of patch area and chip back patch edges to a 30 to 60 degree angle. 

2)    If a joint or crack is within a patch area, construct the bottom edge of that patch to be at least 6 3 inches beyond the joint or crack.

3)    Form or saw patch edges to prevent them from protruding beyond edge of existing pavement by more than 3/8 inch.

4)    Each patch will have a generally rectangular area. Remove the PCC concrete in that area to a minimum depth of 3 2 inches. Many areas will require removal of unsound PCC concrete to a greater depth to reach sound concrete. The maximum depth is one half of the pavement thickness.

5)    Do not damage steel reinforcement during removal process. Damaged steel will be the responsibility of the Contractor. If the end of a dowel bar is exposed, cut or remove dowel.  Place duct tape, form oil, grease, or other method approved by the Engineer as a bond breaker on exposed dowels not removed. 

6)    When removal to the maximum depth leaves unsound concrete within the patch area, the Engineer may designate a part of the patch area as an overdepth patch. Remove the concrete for the full depth of the existing pavement. Consolidate the subgrade or subbase material using a mechanical tamper or other compaction equipment as directed by the Engineer. Furnish and install No. 4 tie bars at mid-depth of existing pavement using an approved non-shrink grout. Place bar to provide a minimum 2 inch concrete cover.

7)    When it is necessary to go below reinforcing steel to reach sound concrete, cut the reinforcing steel flush with the perimeter edges of the patch and remove.

8)    Clean the patch area by sandblasting, followed by cleaning with compressed air. The completed surfaces are to appear surface dry to visual examination.

9)    Recreate a joint or crack in the patch area with a joint board of the proper size and shape. Extend the board to the bottom of the area to be patched, so as to separate completely all patching material on both sides. Use a board of a width approximately equal to the joint or crack. For wide openings, several thicknesses may be used. Longitudinal joints for patches 6 feet or greater in length may be reestablished by sawing to a depth of 1/3 the pavement thickness.

b.     Placing PCC Patch Material.

1)    Scrub a cement-sand-water grout of creamy consistency onto the patch surfaces, including the edges. Grout shall consist of two parts of Type I or Type I/II Portland cement and one part sand mixed with water. Mix grout by mechanical means. Place the patch material before the grout dries. If grout dries before placement of patch material, clean patch area again by sandblasting and air blasting, then reapply grout.

2)    Place the properly mixed material in the patch area. Consolidated and work into place in a manner that will provide good bonding. Level it with the adjacent pavement to provide a smooth riding surface not varying from existing pavement surface by more than 1/8 inch when measured with a 10 foot straightedge placed over patch. Replace or grind patch to correct deficiencies. Apply broom finish to patch surface and then apply a heavy application of grout around perimeter of patch. Position grout so 1 inch is over surrounding pavement and 3 inches is over the patch.

3)    For Class A patching materials, perform this work according to the patching manufacturer's recommendations and limitations, subject to approval of the Engineer. Furnish these recommendations to the Engineer.

c.     Protecting and Curing.

1)    Class A patching material.

        Cure according to the manufacturer's recommendations.

2)    Class B patching material.

a)    Cure as specified in Article 2529.03, G.

b)    Cure these patches for the minimum time specified in Article 2529.02 for the mixture used.

3)    Class C patching material.

a)    Cure patches with an approved white pigmented curing compound meeting the requirements of Section 4105. Apply curing compound within 30 minutes after placement of patching material.

b)    Cure patches with Class M concrete a minimum of 36 hours or as directed by the Engineer.

c)    Cure according to Article 2529.03, H, when overnight low temperatures are forecast to be below 35°F.

d.     Surface Finish.

Level partial depth finish patches with the adjacent pavement. Trowel toward edge of the repair when finishing. Ensure they have a smooth riding surface.

e.     Joint and Crack Sealing.

Where joints and cracks cross areas of partial depth PCC patches, saw, seal, and clean the patch according to Article 2301.03, P. Complete sealing within 5 working days after the patch is placed. When joint and crack sealing is included in the contract, perform sealing as part of that work.

f.      Failure Repair.

Repair failed patches that appear within 30 calendar days of original construction or subsequent repair at no cost to Contracting Authority. Failures may include, but are not limited to, loss of bond between patch and underlying pavement or random cracking.

 

C.    Limitations of Operations.

 

1.     Unless the road is closed, maintain traffic during construction operations. Conduct all operations with minimum inconvenience to traffic. On two-lane roads, limit operations to one traffic lane at a time, except for minor encroachment in the adjacent lane for sawing and installing forms when traffic is maintained. For multiple lane roadways, the work area may include one lane in each direction.

 

2.     An adjacent lane shall be opened to traffic prior to the old pavement being removed from a patch area.

 

3.     When approved by the Engineer, patch areas may extend up to 2 feet into an adjacent lane as allowed by the contract documents.

 

4.     Adjust the work schedule so all work for each patch, including removal of barricades and equipment (except the cure period for PCC Class C concrete), will be completed on the same day it is started between the hours of 30 minutes after sunrise to 30 minutes before sunset. If unforeseen conditions result in excavated areas being left overnight, assign a sufficient number of flaggers to warn and direct traffic until the patches are placed. Extra payment will not be made for the necessary flaggers.

 

5.     Place PCC patching material only when the ambient air and pavement temperatures are 45°F or above.

 

6.     The Engineer may limit advance sawing.

 

7.     If an emergency makes a DW joint necessary, temporarily fill the excavated area following the joint with a suitable hot or cold paving mixture or stable granular material, as directed by the Engineer. The Engineer may direct that the lane remain closed to traffic overnight. Provide traffic control.

 

8.     When PCC patches without calcium chloride are constructed, place two drums meeting the requirements of Article 2528.03, C, in front of each patch location where there is a possibility of turning into or returning to the closed lane. Additional drums need not be placed for patches spaced closer than 150 feet. 

 

9.     Apply Articles 1107.08, 1107.09, and 1108.03.

 

D.    Area Restoration.

When the patch is completed, remove forms if they have been used. Fill all excavated space along the outside pavement edge with material similar to that in the existing shoulder, satisfactory to the Engineer. Thoroughly compact the material before the section is opened to traffic.

 

2530.04     method of measurement.

The Engineer will determine the quantities involved in satisfactory construction of partial depth finish patches for the areas specified as follows:

 

A.    Partial Depth PCC Finish Patches.

 

1.     The Engineer will calculate the area of each patch in square feet from surface measurements. The area of each patch less than 1 square foot will be counted as 1 square foot for payment purposes. If the patch area is increased by the Contractor to accommodate milling equipment, only the area designated by the Engineer will be measured for payment.

 

2.     Removal and repair of areas up to one half existing pavement thickness will be included in this payment.

 

B.    Partial Depth PCC Joint and Crack Repair Patches.

 

1.     Measurement for Partial Depth PCC Joint and Crack Repair Patches will be to the nearest 0.1 linear foot on the basis of 12 inch width of repair. Areas designated for repair outside the 12 inch repair width will be measured as Partial Depth PCC Finish Patches per Article 2530.04, A, 1.

 

2.     Removal and repair of areas up to one half existing pavement thickness will be included in this payment.

 

C.    Overdepth Patches.

Engineer will calculate area of each Overdepth Patch in square feet at the mid-depth of the pavement. Area of each patch less than 1 square foot will be counted as 1 square foot for payment purposes.

 

D.    Partial Depth HMA Finish Patches.

 

1.     The Engineer will measure the area for each patch and the weight of HMA placed in partial depth patches according to Article 2303.04. Regular patches and irregular patches will be calculated and totaled separately. If the patch area is increased to accommodate milling equipment, only the quantities for the area designated by the Engineer will be measured for payment.

 

2.     Asphalt binder and tack coat will not be measured separately for payment.

 

3.     The Engineer will also calculate the area and weight of patch material placed in HMA patches which have been directed to be constructed full depth. The Engineer will deduct quantities not used.

 

2530.05     basis of payment.

Payment for construction of the various types of partial depth finish patches, satisfactorily constructed, at the areas specified, will be the contract unit price as follows:

 

A.    Partial Depth PCC Finish Patches.

 

1.     Per square foot.

 

2.     Payment is full compensation for removal of all pavement, preparing the patch area, furnishing and placing all material, construction of joints, sawing, finishing, curing, and restoration of the area.

 

B.    Partial Depth PCC Joint and Crack Repair Patches.

 

1.     Per linear foot.

 

2.     Payment is full compensation for repairs up to one half existing pavement thickness and includes removal of pavement, preparing the patch area, furnishing and placing material, construction of joints, sawing, finishing, curing, and restoration of area.

 

C.    Overdepth Patches.

 

1.    Per square foot. Payment for Overdepth Patches will be in addition to Partial Depth PCC Finish Patch or Partial Depth PCC Joint and Crack Repair Patch quantities for the same area.

 

2.     Payment is full compensation for repairs designated in lower half of existing pavement and includes removal of pavement, preparing the patch area, and furnishing and placing material.

 

D.    Partial Depth HMA Finish Patches.

 

1.     Payment will be for both the patch area and the quantity of HMA placed in the patch.

a.     Regular Partial Depth HMA Finish Patches, by Area.

Per square yard.

b.     Irregular Partial Depth HMA Finish Patches, by Area.

Per square yard.

c.     Hot Mix Asphalt Mixture.

Per ton. Includes mixture designated for full depth patches.

 

2.     When parts of regular or irregular partial depth HMA finish patches are constructed to full depth at the direction of the Engineer, payment will be for the areas of those parts at two times the contract price per square yard for regular or irregular partial depth HMA finish patches. 

 

3.     Payments are full compensation for:

·         Removal of the old pavement,

·         Preparing the patch area,

·         Furnishing and placing the HMA patching material, including asphalt binder in the mixture and necessary tack coat bitumen,

·         Sawing and sealing,

·         Sealing the patch edges, and

·         Restoration of the area.

 

4.     When joint and crack sealing is included in the contract, it will be paid for as a part of that work.