5.30 MULTILANE HIGHWAY TRAFFIC CONTROL ISSUES

Median Crossings

Most projects on four-lane divided highways include Standard Plan Note 253-1 which states "Contractor is prohibited from using any established or other type median crossover on the project unless specifically designated for the contractor's use by this plan." This note must be strictly enforced. Only in accord with the following conditions may contractors use a median crossover:

These conditions should limit unnecessary median crossings and should provide a safer traffic control zone for the public. This also applies to any inspection vehicles.

Interstate Lane Closures

The Iowa State Patrol has relayed concerns to the Office of Construction regarding possible unnecessary lane closures for interstate work zones.

Typical situations brought to our attention include:

Traffic Control Removal for Head-to-Head (two lane, two way) Projects

The procedure to remove traffic control devices from head-to-head (two lane, two way) projects has been accomplished differently across the state. To achieve uniform removal practices across the state, the Work Zone Traffic Safety Committee discussed the removal procedure and recommends the following steps be used to remove traffic control devices from head-to-head projects:

The entire removal operation shall proceed upstream towards traffic. This will ensure that motorists will have two clear open lanes once they pass traffic control removal operations. Tubular markers shall not be removed in any area until the double yellow lines are removed, unless they are replaced with 42 inch channelizers.

Tubular Markers

Specification Article 2528.03 requires tubular markers be covered with reflectorized sheeting. The specified height range is between 700 to 850 mm (28 to 34 inches), so most traffic control subcontractors reuse tubular markers hit by vehicles by cutting off the bottom 150 mm (6 inches). Since the bottom 150 mm (6 inches) of the tubular marker will eventually be cut off, this area does not need to be covered with reflectorized sheeting.

Many tubular markers used on projects are manufactured extruded plastic shapes. These shapes typically are not exactly round in order to provide for greater strength for the tubular marker. When non-round tubular markers are used on projects, care needs to be taken in their initial installation so that the tubular markers are placed on the centerline of the highway with the non-round side placed facing alternating directions from one tubular marker to the next. This placement orientation will optimize the overall retroreflectivity of the TLTWO (two-lane, two-way) delineation system.

Raised Pavement Markers

Many interstate or other complex project traffic control plans include the use of raised pavement markers to supplement the temporary pavement markings for the project. Raised pavement markers are used in lane shifts or at crossover locations to enhance visibility of correct travel path through these areas. Raised pavement markers are very effective if they stay in correct location on pavement surface.

Off-tracking rear wheels on semi-trailers often dislodge raised pavement markers from the pavement surface. It is permissible to offset the location of the raised pavement markers up to 225 mm (9 inches) laterally away from the temporary pavement marking line to avoid the off-tracking rear trailer wheels. See Standard Road Plan TC-61 for typical applications for median crossovers.

5.31 CHANGEABLE MESSAGE SIGN GUIDELINES

More projects are using Iowa DOT or contractor furnished changeable message signs. These CMS units are intended to be used for incident management traffic control, advance lane closure information or other additional motorist information that needs to be timely, emergency response, temporary road closures for bridge beam replacement, temporary utility crossing requiring road closure, and for other emergency related road closings.

If CMS units are used according to detail sheets contained in project plans, the word message shall be according to the plan sheet requirements. CMS units used for incident management traffic control for major interstate reconstruction projects should have the word message approved by the State Traffic Engineer, since the appropriate message will vary from project to project. CMS units used for all other situations should also have the word messages approved by the State Traffic Engineer. Proposed word messages should be limited to a maximum of 2 panels and usually 8 words or less per panel.

Additional information relating to the use and operational guidelines for the Department's CMS units is included in the Guidelines for Changeable Message Signs. This guideline is available form the State Traffic Engineer, Office of Traffic and Safety at (515)239-1513.

If CMS units are used according to detail sheets contained in project plans, the word message shall be according to the plan sheet requirements. CMS units used for incident management traffic control for major interstate reconstruction projects should have the word message approved by the State Traffic Engineer, since the appropriate message will vary from project to project. CMS units used for all other situations should also have the word messages approved by the State Traffic Engineer. Proposed word messages should be limited to a maximum of 3 panels and usually 8 words or less per panel.

Distribution of Department owned CMS units used for project purposes will be under control of the district traffic technicians. The traffic technicians will coordinate the logistics and placement of the portable CMS units used on construction projects statewide. Repair costs for Department owned CMS units used for project related incident management can be charged against project funds using the appropriate documentation.

Additional information relating to the use and operational guidelines for CMS units is included in the  Guidelines for Changeable Message Signs. This guideline is under the auspices of the Office of Traffic and Safety. Comments regarding the Guidelines should be directed to the State Traffic Engineer at 515/239-1513.

5.32 ARROW DISPLAYS

Solar Assisted Arrow Displays

Solar assisted arrow displays have been effectively used in Iowa since 1991. A listing of approved solar assisted arrow displays is found in Materials I.M. 486.12. Manufacturers of solar assisted arrow displays not currently approved for project use may contact the State Traffic Engineer at 515/239-1513 to schedule a field review in order to be on the approved list.

If any solar assisted arrow display fails to perform adequately in a field situation, it shall immediately be removed and replaced with a different arrow display. The Office of Construction should be informed if any approved solar assisted arrow display fails to perform so that the deficient arrow display model can be deleted from the approved list.

Vehicle Mounted Light Bars

Some traffic control manufacturers are producing small, vehicle mounted light bars to be used as an arrow display. Typical units are the ArrowstikTM or Traffic GuideTM. These types of arrow displays do not meet the minimum requirements of the specifications which require the use of Type C arrow displays. A Type C arrow display is required to be 2.4 m x 1.2 m (96 inches x 48 inches) in size. Therefore, these smaller light bars are not acceptable for use on our projects as arrow displays. They may be used in a wigwag or non-directional mode as an additional warning device.

5.33 TEMPORARY CONCRETE BARRIER RAIL

Temporary barrier rail is used on projects to protect the work area from traffic intrusion. Traffic that contacts the barrier is deflected along the barrier without being bounced back into open traffic with minimal barrier offset. Iowa uses an F-shape temporary concrete barrier rail system that is NCHRP 350 approved. This barrier uses a pin/loop connection between sections and is capable of being tied down to the underlying pavement.

Temporary concrete barrier rail is typically used in the following applications:

Temporary barrier rail is a hazard in itself. Temporary barrier rail should not normally be used where it is a greater hazard than what it is protecting. At least 0.6 m (2 feet) clearance should be provided behind the rail for drop-offs less than 600 mm (24 inches). At least 1.2 m (4 feet) clearance should be provided behind the rail for drop-offs greater than 600 mm (24 inches). When these conditions cannot be met, the temporary barrier rail should be tied down to the underlying pavement according to details provided in Standard Road Plan RE-71.

If location is such that Standard Road Plan RE-71 cannot be used to properly anchor the temporary barrier rail, contact the Office of Construction for additional details. On projects where field conditions result in a drop-off as described above but do not include Standard Road Plan RE-71, the tie-down devices necessary will be extra work.

5.34 SIGN MOUNTING TYPES

Specification Article 2528.02 states that signs for traffic control zones in duration for 4 calendar days or longer are required to be post mounted. Signs for traffic control zones in duration shorter than 4 calendar days may either be post mounted or skid mounted. The intent of this specification is to require post mounting of signs where the project is not a moving or temporary situation. The 4 calendar days should be based on the planned construction operation for the specific traffic control zone setup. Weather delays shall not require that skid mounted signs be changed to post mounted signs to meet the intent of this specification. All post mounted signs are required to be mounted 2.15 m (7 feet) above the surface of the pavement according to the specifications.

In urban areas, signs that require post mounting may be skid mounted at the post mounting heights required in the MUTCD provided that skid mounting devices are NCHRP 350 compliant, so they would not become a hazard if hit by vehicles.

U Channel Posts

Specification 2528.02 allows 3 pound per foot U Channel posts as one of the three post mounting options for work zone signs. An easy way to determine if the supplied post is a 3 pound per foot post, use the image at right and dimensions as a guide.

5.35 REMOVAL OF TEMPORARY PAVEMENT MARKINGS

Temporary pavement markings are necessary for most construction projects. Typical locations include runarounds, diversions, stage construction, etc. When temporary pavement markings are placed, they will eventually be removed as part of the project.

Removal depends on the type of pavement marking material placed and type of surface to which it is attached (new or old, HMA or PCC). Two types of temporary pavement markings are currently used: removable pavement marking tape and heavy metal free waterborne paint.

Pavement Marking Removal Characteristics

Each temporary pavement marking material has its own removal characteristics:

Disposal of Removed Pavement Marking Materials

All pavement marking removal operations shall be completed in accordance with Specification Article 2527.03.B. This article requires that removal operations be essentially dust free and collect all of the removed product from the road surface. Typical pavement marking removal operations consist of dry vacuum grinding, shot blasting, or water blasting. All removed pavement marking materials shall be disposed according to the following Iowa DNR requirements:
 

5.36 NCHRP 350 CRASHWORTHY WORK ZONE DEVICES

NCHRP 350 (National Cooperative Highway Research Program 350) Report is the national standard for crash testing work zone signs and devices. The FHWA, in a letter to the Department on August 28, 1998 mandates that all work zone signs and devices being used on the National Highway System be NCHRP 350 compliant. The letter divided the various types of signs and devices into four categories. The Department has determined that all work zone signs and devices used on the entire Department administered highway system be NCHRP 350 compliant. This DOES NOT include county roads or city streets.

The four categories of work zone devices are defined as follows:

Specification requirements for NCHRP 350 compliant devices are found in Specification Article 2528.01, sixth and seventh paragraphs. A list of FHWA approved NCHRP 350 compliant devices can be found through the Internet at:

http://safety.fhwa. dot.gov/fourthlevel/hardware/wzd.htm

Contractors have the responsibility to provide documentation to the administering RCE Office that all work zone signs and devices used on the contract are NCHRP 350 compliant.  This documentation should be on contractor letterhead and shall include the vendor's self-certification for Category I signs and devices and the FHWA "WZ-XX" acceptance memorandum for Category II signs and devices. A sample documentation letter is included in Appendix 5-4.

5.37 INSTALLATION OF TRAFFIC CONTROL ZONES

Temporary traffic control devices are always installed in the direction that traffic flows...that is, "downstream." The first device placed on the roadway is the first advance warning sign, typically the "ROAD WORK AHEAD" sign. The installation then proceeds with the signs in the advance warning zone and continues through the transition zone into the actual work area and finishes in the termination zone.

All vehicles used to carry the temporary traffic control devices need to be parked in a safe location such as on the shoulder or at a field entrance, or parked legally at a marked parking stall or on the curb line in urban areas. These vehicles should display their four way flashers and any amber flashing or rotating warning lights.

All semi-permanent or permanent traffic control zones should be reviewed prior to the actual installation time. This review should consist of "pre-marking" the location of all signs and devices. Pre-marking sign and device locations early should help to determine if corrections or modifications need to be made to the traffic control plan included in the contract documents. Any corrections necessary should be according to Construction Manual Section 5.22.

5.38 SIGNALIZED VS. FLAGGER CONTROLLED HAUL ROAD CROSSINGS

The Office of Design typically determines the need for haul road crossings during project design. These crossings are decided to be either a signalized or flagger controlled crossing based on factors such as economic analysis, safety concerns, and project uniformity. Occasionally necessary haul road crossings are not included in the plans or field conditions are different from plan details and additional haul road crossings need to be added.

When haul road crossings are added in the field, RCE offices should review the flow chart in Appendix 5-7 to determine the appropriate haul road crossing to use. Questions pertaining to haul road crossings should be referred to the Office of Construction.

5.39 TRAFFIC CONTROL EVALUATION REPORTING FORM

The Construction Traffic Control Process Improvement Team has developed the Traffic Control Evaluation Report (Form 830437) to help foster better communication between the contracting authority and the contractor regarding traffic control operation and effectiveness. A copy of this form is found in Appendix 5-10.

The intent of the form is to provide contractors with an easily understood evaluation during any point of time while a project is under construction. Use of this form should help modify a contractor’s performance by documenting the engineer's concern during a project. As stated on the form, the use of this form and its distribution is solely between the engineer and contractor. Additional distribution is not needed.

Instructions for completing the form are shown on the backside of the form.