Section 2407. Precast and Prestressed Concrete Bridge Units.

2407.01 DESCRIPTION.
The provisions of this section shall apply to production and construction of precast concrete and prestressed concrete as defined in Section 1101. Prestressed and precast concrete shall be produced in a plant for which equipment, procedures, and quality of concrete have been approved by the Contracting Authority. The Contractor or fabricator shall provide technical personnel, experienced and skilled in the application of the prestressing system being used. These personnel shall cooperate fully with the Engineer in all technical aspects of the work.

2407.02 MATERIALS.
The materials used in prestressed and precast concrete shall meet the requirements of Division 41 for the respective material, and the following:

A. Aggregates.
Sections 4110 and 4115 shall apply, except the gradation requirements of Articles 4110.02 and 4115.03. The aggregate gradations and proportions shall be submitted with the mix design to the District Materials Engineer for approval. Aggregates similar to Class V shall be used only when 30% or more of the total weight (mass) of aggregate is limestone.

B. Admixtures.
When authorized by the Engineer, approved admixtures complying with Section 4103 may be used.

C. Steel for Prestressing.
Article 4151.05 shall apply.

D. Reinforcement.
Article 4151.03 shall apply.

E. Steel Sole and Masonry Plates.
Section 2508 and Articles 2408.13, 2408.21, and 4152.02 shall apply.

F. Neoprene Bearing Pads.
Article 4195.02 shall apply.

G. Bolts and Other Metal Fastenings.
Unless otherwise indicated in the contract documents, fasteners shall be non-high-strength fasteners meeting requirements of Article 4153.06. Other fastenings shall be of structural steel meeting the requirements of Article 4152.02, except for anchors and ties for diaphragm connections and hold down devices for deflected tendons. These items will generally be proprietary products and will require approval by the Engineer. Samples submitted to the Engineer for approval shall show an ultimate strength of 50% in excess of the manufacturer's advertised safe loads. All of these fastenings shall be of a type to be cast in the concrete. Bolts, nuts, washers, and other metal fastenings shall be galvanized as specified for steel structures in Article 4100.07.

H. Cement.
Section 4101 shall apply. Type III Portland cement, when authorized, will be used in the same proportions as specified for Type I Portland cement.

I. Mineral admixtures.
Section 4108 shall apply.

Fly ash may be substituted for Portland cement. The substitution rate shall not be more than 15% by weight (mass).

GGBFS may substituted for Portland cement. The substitution rate for GGBFS as a mineral admixture shall not exceed 35% by weight (mass).

2407.03 CONCRETE.
Total cementitious material per cubic yard (cubic meter) of concrete used in precast and prestressed construction shall be not less than 610 pounds (360 kg) and the maximum water- cementitious ratio, including free moisture in the aggregate, shall not exceed 0.450 pound per pound (0.450 kg/kg).

If the units are to form curbs or floors of structures, air entrainment shall be required and be accomplished by addition of an approved air-entraining admixture. The intended air entrainment of the finished concrete is 6%. To allow for loss during placement, the air content of fresh, unvibrated concrete shall be 6.5%, as a target value, with a maximum variation of ± 1.0%.

Within these limits the concrete shall be properly proportioned, mixed, placed, and cured in a manner as to produce concrete of a minimum compressive strength specified below at the age designated.

Classification

Concrete Strength Before Moving
or Prestressing, psi (MPa)
Concrete Strength at Age
28 calendar days, psi (MPa)
Precast Sheet or Bearing Piles
Precast Bridge Deck Units
Prestressed Piles
Prestressed Deck Panels
All Other Prestressed Concrete*
3500 (24)
3500 (24)
4000 (28)
4000 (28)
4500 (31)
4500 (31)
5000 (35)
5000 (35)
5000 (35)
5000 (35)

* Unless otherwise noted in the contract documents.

NOTE: Beams shall not be shipped until the concrete has attained the 28 day strength.

2407.04 EQUIPMENT.
Equipment shall meet requirements of Section 2001 and the following:

A. Casting Beds.
Casting beds for precast concrete and for prestressed concrete shall be rigidly constructed and supported so that under the weight (mass) of the concrete and the vertical reactions of holdups and hold downs there will be no vertical deformation of the bed.

End anchorages for pretensioned work, whether self anchored or supported horizontally by the bed, shall be capable of resisting the maximum prestress force to which they will be subjected without permanent displacement.

B. Forms.
Forms for precast and prestressed concrete shall be true to dimensions as shown in the contract documents, true to line, mortar tight, and of sufficient rigidity to not sag or bulge out of shape under placement and vibration of concrete. Inside surfaces shall be smooth and free of any projections, indentations, or offsets that might restrict differential movements of forms and concrete.

On long beds for multiple pretensioned beam production where continuous forms and pallets are used, precautions shall be taken to prevent damage to the beams from differential movements of forms and concrete due to temperature changes.

C. Stressing Equipment.
Equipment used to tension tendons shall be of a type such that the prestressing force may be accurately known. Load cells, dynamometers, and hydraulic gages of hydraulic pump and jacking systems shall be capable of measuring the force applied to the tendons within 2% of the actual force. This equipment shall be calibrated at least once every 12 months or anytime the tensioning system indicates erratic results. Hydraulic gages, pumps, hoses and connections shall be calibrated as a system.

All tensioning equipment calibrations shall be preformed using load cells calibrated by a testing laboratory or calibration service. Equipment used for calibration purposes shall have current calibration references. The Engineer shall be allowed opportunity to witness calibration of equipment during the Engineer's normal working hours or at a mutual agreeable time.

D. Weighing and Proportioning Equipment.
Article 2001.20 shall apply except that a vibrator will not be required on the cement batch hopper.

E. Mixing Equipment.
Article 2001.21 shall apply.

F. Bins.
Article 2001.06 shall apply.

2407.05 PLACING REINFORCEMENT.
All reinforcement shall be carefully and accurately placed and secured in the proper position according to the contract documents. Articles 2404.03, 2404.04, 2404.05, 2404.06, 2404.07, and 2404.08 shall apply.

If welding is employed in placement of reinforcing steel, or the interconnection of plate connectors, sole plates, or masonry plates, the welders shall be qualified in accordance with Article 2408.13. For tack welding reinforcing bars, all other requirements shall be as outlined in the latest edition of AWS D1.4, including Table 5.2, Minimum Preheat and Interpass Temperature, except the minimum preheat and interpass temperature shall never be below 50°F (10°C). The minimum preheat and interpass temperature for structural steel shall remain as in Article 2408.13. The period of effectiveness for all welders shall be as specified in Article 2408.13. Prestressing tendons shall be carefully protected from heat and weld spatter. Tack welding of reinforcing steel at noncritical stress areas in combination with sacrificial reinforcing bars, if required, will be allowed without regard to preheat and interpass temperature restrictions; any such modification shall be subject to approval of the Engineer.

2407.06 PRESTRESSING STEEL STRESSES.
The number, size, and position of individual tendons (7-wire strand) and the prestressing force shall be as shown in the contract documents.

If anchored at other than 70°F (20°C), the initial prestressing force shall be adjusted as follows:

Temperature of Strands Initial Prestressing Force
70°F (20°C)
Below 70°F (20°C)
Above 70°F (20°C)
As shown in the contract documents
Increase 1.0% per 10°F (5°C)
Decrease 1.0% per 10°F (5°C)

After tendons have been positioned, an initial force between 1,000 and 4,500 pounds (4.5 kN and 20 kN) shall be applied to each tendon. The initial force shall be measured within a tolerance of ± 100 pounds (0.5 kN) for initial forces under 3,000 pounds (13 kN) and a tolerance of ± 200 pounds (1 kN) for initial forces of 3,000 pounds (13 kN) or more.

The theoretical elongation of the tendons is calculated from material properties furnished by the manufacturer and allowable losses. Allowable losses may include seating losses, bed shortening, abutment movement, and temperature adjustments.

The pretensioning shall be measured by the net elongation of the tendons. The calculated theoretical net elongation shall be considered the target. A tolerance of + 1/2 inch (13mm) from the calculated net elongation, after seating, may be allowed.

The tensioning procedure shall be conducted so the indicated stress, measured by the tensioning system, is within 5% of the calculated stress, based upon the corresponding elongation. The distribution of the stress shall be within 5% of the calculated stress at all points along the tendon or when measured at the end of the bed.

Temporary overstressing of the tendons is allowed, but shall at no time exceed 80% of the specified tensile strength of the tendons. Tendons shall not be seated in this overstress condition.

Tendons shall be tensioned between fixed end anchorages by means of jacks either separately or in a group. Several units may be cast in one continuous line in which case they shall be tensioned simultaneously.

Deflected tendons may be tensioned in place. Alternatively, deflected tendons may be partially tensioned and then raised to the predetermined final position at the beam ends, achieving the required prestressing force. Tendons may be raised simultaneously to the predetermined final position or at any one point, in a single lift, provided the sequence of lifting commences at the point nearest the center of the bed and then progresses alternately at points equidistant from the center to the ends.

Tendons shall be supported at each deflection point on a freely rotating metal pulley not less than 3/4 inch (19 mm) in diameter.

The number of broken strand wires shall not exceed 2% of the total number of strand wires nor one broken wire of any one strand.

2407.07 PROPORTIONING, MIXING, AND PLACING CONCRETE.
Proportioning and mixing of concrete shall be in accordance with applicable requirements of Article 2403.06.

Concrete shall not be placed when the ambient temperature is below 35°F (2°C) unless the plant has been approved by the Engineer for cold weather concrete placement. When necessary, the aggregate or water or both shall be heated so that the temperature of concrete when deposited in the forms is 40°F to 90°F (4°C to 32°C) . In no case shall any frozen material be used in concrete. When a series of units is cast in a line, the entire series of units shall be cast in one continuous operation, or as directed by the Engineer. Successive batches shall be placed before the preceding batch has perceptibly hardened or dried. In no case shall the interval in placement of successive batches of concrete in a unit exceed 45 minutes. There shall be no retempering of the concrete, nor shall any water be added to the interface of the concrete between batches.

Concrete shall be carefully worked and consolidated around reinforcement without displacing it. Care shall be used to prevent formation of honeycomb, stone pockets, or similar defects. Concrete shall be consolidated by small diameter vibrators or by other means approved by the Engineer. Forms shall be overfilled during the consolidation. Excess concrete shall be screeded off, and the surface shall be finished to the desired texture.

On specific request and approval, provisions may be made for inserts in beams as an aid to stripping floor forms. This shall be done according to the conditions of such approval.

2407.08 PRESTRESS TRANSFER.
When accelerated heat curing is used, prestress transfer shall be preformed immediately after the curing period is completed and while the concrete is warm and moist.

Deflected tendons, if any, are to be released first, either by lowering holdup devices at beam ends as nearly simultaneously as practical, or if this is not feasible, deflected tendons shall be flame cut in each beam interval in rotation until all deflected tendons are released. The procedure for flame cutting deflected tendons shall be subject to approval by the Engineer.

The hold down devices shall then be released from the bed and the straight line tendons released simultaneously and gradually with the jack. If this is not feasible, heating of individual tendons shall be employed as follows:

Heating of each individual tendon shall be done simultaneously on the tendon at a minimum of two locations along the casting bed. Heating shall be done along the tendon over a minimum 5 inch (125 mm) distance. The application of heat shall be controlled so that failure of the first wire in the tendon does not occur for at least 5 seconds after heat is applied, followed by gradual elongation and failure of the remaining wires. The tendon shall also be heated until failure occurs at each beam interval before proceeding to the next tendon. The sequence of prestress transfer between individual tendons shall be such that there is minimum eccentricity of prestress load. Alternate procedures for releasing deflected or straight line tendons may be submitted for the Engineer's approval.

The camber due to prestress shall be measured while the beam is on the bed by checking the beam profile within three hours after prestress transfer.

2407.09 CURING.
The method of curing shall prevent loss of moisture and maintain an internal concrete temperature of not less than 40°F (4°C) during the curing period. It shall be subject to approval of the Engineer.

When accelerated heat curing is used, it shall be done under a suitable enclosure. Equipment and procedures shall be to insure uniform control and distribution of heat and prevent local overheating. The curing process shall be under the direct supervision and control of competent operators.

When accelerated heat is used to obtain temperatures above 100°F (38°C), the temperature of the interior of the concrete shall be recorded by a system capable of automatically producing a temperature record during the entire curing period for a minimum of one location per 100 feet (30 m) of length per unit or fraction thereof, with a maximum of three locations along each line of units being cured. The temperature record shall show the temperature at each location at intervals of not more than 15 minutes. Any unit, when calibrated individually, shall be accurate within ± 5°F (3°C). The temperature of the concrete shall not be artificially raised above 100°F (38°C) for a minimum of 2 hours after the units have been cast. After the 2 hour period, the temperature of the concrete may be raised to a maximum temperature of 160°F (71°C) at a rate not to exceed 25°F (15°C) per hour. The maximum temperature shall be held for a period sufficient to develop the strength required for release of prestress or for post tensioning, as the case may be. The temperature of the concrete shall be lowered at a rate not to exceed 40°F (22°C) per hour by reducing the amount of heat applied until the interior of the concrete has reached the temperature of the surrounding air.

In all cases, the concrete shall be covered and remain covered until curing is completed. Side forms and pans forming the underside of channel shapes may be removed during this period if the cover is immediately replaced. In no case shall units be removed from the casting bed until the strength requirements are met.

For pretensioned beams, the temperature of the beams and exposed strands shall be maintained at normal curing temperature until the stress has been released from the end anchorages.

2407.10 REMOVAL OF FORMS.
If forms are removed before the concrete has attained the strength which will permit the units to be moved or stressed, protection shall be removed only from the immediate section from which forms are being removed, and the protection shall be immediately replaced and curing resumed after the forms are removed. Protection shall not be removed at any time before the units attain the specified compressive strength when the surrounding air temperature is below 20°F (-7°C).

2407.11 POST TENSIONED PRESTRESSED CONCRETE.
When post tensioned construction is designated, detailed procedures will be included in the contract documents.

2407.12 TOLERANCES.
Tolerances for precast and prestressed units shall be as follows:

A. Precast Nonprestressed Units.
In general, units shall not vary from dimensions shown in the contract documents by more than 1/8 inch (3 mm) in all dimensions, but for overruns, greater deviation may be accepted if, in the opinion of the Engineer, it does not impair the suitability of the member for its intended use. Beam seat bearing areas at each end of the unit shall be flat and true and perpendicular transversely to the vertical axis of the beam. The difference of cambers between two adjacent units, as assembled, shall not be more than 1/8 inch (3 mm).

B. Precast Prestressed Units.
Precast prestressed units shall not vary from dimensions shown in the contract documents in excess of the following tolerances:

Length: ±1/4" per 25' and ±1" max. for beams 100' or longer
(±6 mm per 8 m and ±25 mm max. for beams 30 m or longer)
Width (flanges and fillets): +3/8" or -1/4" (+10 mm or -6 mm)
Depth (overall): +1/2" or -1/4" (+13 mm or -6 mm)
Width (web): +3/8" or -1/4" (+10 mm or -6 mm)
Depth (flanges and fillets): ±1/4" (±6 mm)
Bearing plates (ctr.-ctr.): 1/8" per 10' of beam length, max. ±3/4"
(1 mm per 1 m of beam length, max. ±20 mm)
Sweep (deviations from straight line parallel to center line of member): L/80 (L in feet, sweep is in inches (L (L in meters, sweep is in millimeters))
Camber deviation from design camber: ±30% of plan camber
Stirrup bars (project above top of beam): +1/4" or -3/4" (+6 mm or -20 mm)
Individual tendon position:  
Straight strands ±1/4" (±6 mm)
Draped strands at end of beam ±1/2" (±13 mm)
Tendon position:  
Center of gravity of strand group: ±1/4" (±6 mm)
Center of gravity of depressed strand group at end of beam: ±1" (±25 mm)
Deviation from net theoretical elongation after final seating: ± 1/2 inch (13 mm)
Position of deflection points for deflected strands: 5% of beam span toward end of beam
Position of handling devices: ±6" (±150 mm)
Bearing plates (ctr. to end of beam): ±3/8" (±10 mm)
Side inserts (ctr.-ctr and ctr. to end): ±1/2" (±13 mm)
Exposed beam ends (deviation from square or designated skew):  
Horizontal ±1/4" (±6 mm)
Vertical ±1/8" per foot of beam depth (±10 mm per 1 m)
Bearing area deviation from plane: ±1/16" (±2 mm)
Stirrup bars (longitudinal spacing): ±1" (±25 mm)
Position of post tensioning duct: ±1/4" (±6 mm)
Position of weld plates: ±1" (±25 mm)
Elongation (standard gauge length to be a minimum of 20 feet (6 m)): ±5% (±5%)

2407.13 HANDLING AND STORAGE.
In lifting and handling precast or prestressed units, they shall be supported at or near the points designated in the contract documents. In no case shall the overhang exceed 5% of the length of the beam, unless otherwise specified in the contract documents. Units shall not be lifted or strained in any way before they have developed the strength specified. In storage, units shall be supported at points adjacent to the bearings, and piles shall be supported near the one-fifth points measured from the ends. In stacking units for storage, the bearings shall be arranged one directly above another.

Piles shall be legibly marked with the casting date in fresh concrete near the head of the pile, using numerals only.

Care shall be taken during fabrication, storage, handling, and hauling to prevent cracking, twisting, unnecessary roughness, or other damage. Particularly, tiedowns shall not be in direct contact with concrete surfaces, and units should not be subjected to excessive impact. Units damaged in a way to impair their strength or suitability for their intended use, in the opinion of the Engineer, shall be replaced by the Contractor at no additional cost.

2407.14 FINISH.
All surfaces which will be exposed in the finished structure, shall be finished as provided in Article 2403.21, B, and be free of honeycomb or surface defects. Structural Repair procedures shall be submitted to the Engineer for approval.

The outer surface of exterior beams shall be finished as follows:

As soon as practicable after removal of the forms, all fins and other surface projections shall be removed, and a prepared grout shall be brushed or sprayed onto the prewetted surface.

The grout shall consist of one part of silica sand and one part of Portland cement blended with acrylic bonding agent and water to produce a consistency sufficient to fill the cavities. The Engineer may require white Portland cement to be used in amounts necessary to obtain a uniform finish.

Immediately after application of the grout, the surface shall receive a float finish with a cork or other suitable float. This operation shall completely fill all holes and depressions on the surface. When the grout is of such plasticity that it will not be pulled from holes or depressions, a float of sponge rubber shall be used to remove all excess grout. When the surface is thoroughly dry, it shall be rubbed vigorously with dry burlap to completely remove excess dried grout. The surface finish shall be cured in a manner satisfactory to the Engineer, and heat curing may be required in cold weather. When finished, the surface shall be free from stain and shall have a uniform color.

Tendon projections shall be cut and bent as detailed in the contract documents. Where the tendon end will be exposed in the complete structure, it shall be cut off reasonably flush with the concrete. The end of each cut off tendon shall be cleaned to a bright appearance.

Beam ends exposed in the complete structure shall be coated and sealed with an approved gray or clear epoxy listed in Materials I.M. 491.12, Appendix A. The epoxy coating and sealing of beam ends shall be as indicated on the plans and shall be applied at the fabricating plant.

2407.15 METHOD OF MEASUREMENT.
For precast or prestressed structural units, the Engineer will determine the number of units of each of the various respective sizes, lengths, and types from actual count.

The measurement of precast sheet piles or precast or prestressed bearing piles shall be in accordance with Article 2501.20.

For cast-in-place prestressed concrete, the method of measurement for concrete, reinforcing steel, and structural steel shall be in accordance with Article 2403.22 for structural concrete, and the prestressing will be a lump sum item.

2407.16 BASIS OF PAYMENT.
For the number of approved precast or prestressed structural units of each size and length incorporated in the project, the Contractor will be paid the contract unit price. This payment shall be full compensation for producing and furnishing the units complete as shown in the contract documents, with all plates, pads, bolts, grout enclosures, reinforcing steel, prestressing material, coil rods, hold down devices, and any other items to be cast in the concrete, and for transporting units to the site and placing them in the structure. The contract amount shall also include the cost of furnishing and installing bearing plates and anchor bolts or neoprene pads when specified in the contract documents.

For furnishing precast sheet piles or precast or prestressed bearing piles, the Contractor will be paid as provided in Article 2501.21.

For cast-in-place prestressed concrete, the Contractor will be paid in accordance with Article 2403.23. The prestressing will be paid for as a lump sum item. The lump sum amount shall be full payment for furnishing and placing the required material and stressing, anchoring, and grouting the prestressing steel in accordance with the contract documents.