PCC NON-STRUCTURAL & MISCELLANEOUS - FIELD AND PLANT SAMPLING AND TESTING GUIDE

(See Specifications for Complete Details.)

 

 

Field Acceptance

Plant Acceptance

 

Article

Work Type

Air & Slump

Gradation QC

Gradation Verification

 

NON-STRUCTURAL

 

 

 

2212

Base Repair

1/30 yd3 (1)

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2201

PCC Base

1/700 yd3: 1/100 yd3 RM

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2213

Base Widening

1/700 yd3: 1/100 yd3 RM

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2415

Curtain Wall

1/30 yd3

n/a

n/a

2507

Revetment Grout

Air -1/half day

S/T for Mix Design only

n/a

 

Slope Protection

Air -1/day

n/a

n/a

 

Fabric Formed Revetment

Air- 1/half day

S/T for Mix Design only

n/a

2511

Sidewalks

1/100 yd3 (1)

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2511

Trails

1/100 yd3

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2512

Curb & Gutter

1/100 yd3 (1)

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2515

Driveways

1/100 yd3 (1)

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2517

Railroad Approach Sections

1/100 yd3 (1)

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2529

Patching (Full depth), rumble strip

1/30 yd3 (1)

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

2530

Patching (Partial depth)

1/30 yd3 (1)

S/T 1st week, S/T 1 per month (3)

S/T 1/project (3)

 

MISCELLANEOUS

 

 

 

2304

Detour Pavement, 3 yrs or less

n/a

n/a

n/a

2405

seal course

n/a

n/a

n/a

2416

Pipe collars

n/a

n/a

n/a

2503

Catch basins, abandonment,collars

n/a

n/a

n/a

2506

Flowable Mortar

n/a

S/T for Mix Design only

n/a

2519

Fence construction

n/a

n/a

n/a

2524

Type A and B

n/a

n/a

n/a

2554

Thrust blocks

n/a

n/a

n/a

(1) If less than 20 yd3/ day, the engineer may waive air testing if inspection is not available and producer has exhibited consistency in prior placements. When inspection available on project,test minimum of 1/day for concrete exposed to freezing and thawing.

(3)  Sampling and testing rate if no other concrete supplied. Use structural or paving test results to cover non-structural concrete items.

Any concrete items not listed are considered miscellaneous concrete.