Fuel Adjustment Calculation
The following provides information on fuel adjustment calculation for the below scenarios:
- Contracts where the DOT is the Contracting Authority
- Using AASHTOWare Project*
- NOT using AASHTOWare project
- Contracts where the DOT is NOT the Contracting Authority
- Let on or after 4/16/24
- Let prior to 4/16/24
*Note: This would be DOT contracts beginning with the January 17, 2024 letting (the letting where full AASHTOWare Project implementation started) or prior to this, select DOT contracts that have the Developmental Specification “Fuel Adjustment for AASHTOWare Project” applied.
For Scenario 1a - Contracts where the DOT is the Contracting Authority and using AASHTOWare Project
There is no contract quantity threshold for fuel adjustment to apply to an eligible item. This means that all eligible items of any quantities will have fuel adjustment calculated in AASHTOWare Project.
In accordance with Article 2120.05, fuel adjustment is processed automatically in each pay estimate for the quantity that is posted to the eligible item(s). This means there is no need to use the fuel adjustment spreadsheet for calculations, because the AASHTOWare Project software handles the calculations. Therefore, it is important that quantities for eligible items are posted on a Daily Work Report that is dated in the month that the grading work was performed.
For Scenario 1b - Contracts where the DOT is the Contracting Authority and NOT using AASHTOWare Project
Fuel adjustment applies to an item when the contract quantity of the item is 50,000 CY or more.
In accordance with Article 2120.04, the contractor shall provide to the Engineer, on a monthly basis, a spreadsheet with quantities and the calculated amount of fuel adjustment for the month. Payment will be processed with a Contract Modification.
A standardized Fuel Adjustment spreadsheet has been developed by the Construction and Materials Bureau and is available in EXCEL format.
Fuel adjustment will be made for items of work covered in Section 2120 when the CPI for the month the work is performed is
more than
$0.15 per gallon different than the BPI established at the beginning of the project.
For Scenario 2a - Contracts where the DOT is NOT the Contracting Authority that are let on or after 4/16/24
Fuel adjustment applies to an item when the contract quantity of the item is 50,000 CY or more.
In accordance with Article 2120.04, the contractor shall provide to the Engineer, on a monthly basis, a spreadsheet with quantities and the calculated amount of fuel adjustment for the month. Payment will be processed with a Contract Modification.
A standardized Fuel Adjustment spreadsheet has been developed by the Construction and Materials Bureau and is available in EXCEL format.
Fuel adjustment will be made for items of work covered in Section 2120 when the CPI for the month the work is performed is
more than
5% different than the BPI established at the beginning of the project.
For Scenario 2b - Contracts where the DOT is NOT the Contracting Authority that are let BEFORE 4/16/24
Fuel adjustment applies to an item when the contract quantity of the item is 50,000 CY or more.
In accordance with Article 2120.04, the contractor shall provide to the Engineer, on a monthly basis, a spreadsheet with quantities and the calculated amount of fuel adjustment for the month. Payment will be processed with a Contract Modification.
A standardized Fuel Adjustment spreadsheet has been developed by the Construction and Materials Bureau and is available in EXCEL format.
Fuel adjustment will be made for items of work covered in Section 2120 when the CPI for the month the work is performed is
more than
$0.15 per gallon different than the BPI established at the beginning of the project.