About the Project

What: The progress you see at the Northeast Mixmaster is a continuation of reconstruction that began back in 2008. The completed work includes new bridges over I-80 between I-35 and I-235 and resurfacing of the existing I-80 bridges.

Here’s a rundown of what has been done and what we still need to finish.

  • In 2016, the NE 54th Avenue bridge over I-35 was reconstructed to make room for the new ramp from westbound I-80 to northbound I-35. This ramp is currently under construction under the east side of this bridge.
  • In 2017, the Delaware Avenue bridge over I-35/80 was reconstructed to make room for the new eastbound I-35/80 ramp to westbound I-235 and to northbound I-35 that is currently under construction.
  • In 2023, grading work for a new eastbound I-80 to westbound I-235 and eastbound I-80 to northbound I-35 ramp and westbound I-80 to northbound I-35 ramp were completed. Work also started on a new bridge from eastbound I-80 to northbound I-35 started along with a new bridge over NE 29th St. for the westbound I-80 ramp to northbound I-35 was constructed.
  • In 2024, paving will be completed for the ramps and bridges.

Why: Interchanges like this are designed to allow a certain number of vehicles to safely pass through each of the ramps. Data shows that the number of vehicles passing through this area will exceed the current maximum capacity by 2030. Increasing the capacity now not only improves safety in the short term it allows for safe travels for decades to come.

How: Since there are several bridges and roads being reconstructed or updated, we’ve taken a carefully planned, phased approach to the area.

When: Building on the work that has already been done, the next phase will begin in the summer of 2024 and continue over the next three years. This work includes the reconstruction/addition of lanes so that there will be four eastbound and four westbound lanes between the Northeast Mixmaster and U.S. 65. Work includes new bridges at NE 29th Street, NE 38th Street and over Fourmile Creek. Traffic on 38th Street will be detoured from spring 2025 until the end of the project, approximately two and a half years.

Project Budget: $76 million

Remote Media URL
Back to top

Long Term Detours

Visit Iowa DOT News to find detour information for closures lasting less than a week.

Back to top

Northeast Mixmaster Long-Term Detours

The 38th Street bridge over I-80 will be closed to traffic beginning Monday, December 2, 2024. This closure will last the duration of the project, which is approximately three years. The bridge needs to be removed so the interstate can be widened underneath. Work to rebuild the bridge is planned for winter 2026-2027. Please follow the detour on the map below during this closure.

38th Street bridge over I-80 detour
Back to top

Photos and Videos

Northeast Mixmaster Interchange Construction

Northeast Mixmaster Interchange Construction

Join Des Moines Area Interstate Projects on Facebook

Get the latest information about interstate construction projects in and around the Des Moines metro area.


 

Email Newsletter

Stay Connected with Des Moines Area Interstate Projects

Sign up to receive notifications of upcoming construction and project updates.

 

511IA Travel
Traffic & Road Conditions

Iowa 511

Real-time updates about weather-related road conditions, construction, commercial vehicle restrictions, road closures, and other events that impact traffic in Iowa.

Back to top