Content Information
On this page...
120-1 Specifications Overview
Specifications are detailed statements describing materials, dimensions, and quality of work for something to be constructed, installed, or manufactured. At the Iowa DOT, the Specifications Section of the Contracts and Specifications Bureau manages the specification development process. Additionally, all changes to the specifications (exception for Special Provisions) are decided by the Specification Committee (or Spec. Committee). This committee consists of representatives from FHWA, local governments, and various bureaus within the Highway Division within the DOT. For more information on the Specification Committee, refer to PPM 600.02.
Requests for specification changes (except for Special Provisions) must be submitted to the Specifications Committee by a current member. The Design Bureau’s representative is the Methods Engineer.
Below are the types of specifications used at the Iowa DOT listed in an increasing order of precedence, shifting from general in nature to more project specific:
Standard Specifications
General Supplemental Specifications
Supplemental Specifications
Developmental Specifications
Special Provisions
As an example, a requirement in a Developmental Specification would override a similar requirement in a General Supplemental Specification, whereas a related requirement in a Special Provision would override them both.
For a complete listing of the hierarchy for all contract documents, refer to Article 1105.04 of the Standard Specifications.
Back to topStandard Specifications
The Standard Specifications are published in the Electronic Reference Library (ERL). ERL is updated through the issuance of General Supplemental Specifications.
General Supplemental Specifications (GS)
General Supplemental Specifications are published twice each year to coincide with the April and October bid lettings. Each new GS replaces the previous one and incorporates the changes from all previous GSs. Therefore, designers need only refer to the newest GS to find the most accurate information.
Supplemental Specifications (SS)
Supplemental Specifications are specifications that either modify the requirements for work covered in the Standard Specifications or describe requirements for work not covered by the Standard Specifications. SSs are typically linked to specific bid items. The Contracts and Specifications Bureau automatically assigns an SS to a project when those specific bid items are included.
Developmental Specifications (DS)
Developmental Specifications are a hybrid of SSs and SPs. They are reusable, but will be assigned to specific projects. If a DS is modified, it will be assigned a new number. Most DSs require the approval of a controller before they can be assigned to a project. When a DS is required on a project, follow the procedures outlined in Section 2120-2.
Special Provisions (SP)
Special Provisions are specifications for work items applicable to a specific project or group of projects. SPs are typically written by designers and submitted to the Specifications Section as outlined in Section 120A-3120-3. Some SPs are drafted by the Specifications Section. SPs override information shown in the plans.
120-2 Developmental Specifications
The DOT has developed many Developmental Specifications (DSs) in response to reoccurring Special Provisions (SPs) and other special situations. The intent of DSs is similar to that of SP’ in that they are both project specific. However, unlike SPs, DSs can be reused on multiple projects without being reviewed and approved each time.
Before drafting a new DS, check to see if a DS already exists that suits the needs of the project. If a DS already exists, follow the Requirements for Submitting Supplemental and Developmental Specifications in Masterworks.
If a DS that will satisfactorily cover work on the project cannot be found, the designer must write a new DS. Contact the Specifications Engineer. Section 120-4 provides guidance for writing specifications.
New DSs must be approved by the Specifications Committee. Since the committee meets only once a month, it is preferable to submit the proposed DS at least six months prior to plan turn-in. This provides adequate time to process and resubmit any changes that may be requested by the committee.
Back to top
120-3 Special Provisions
Occasionally, there may be a need to use an innovative product or an experimental procedure to address the unique demands of a particular project. Often, these items are not covered by existing specifications, so they may require new or modified specifications to describe their construction and payment. Special Provisions (SPs) are written to cover these situations.
Checking the Special Provisions List
If an SP is found that will satisfactorily cover work on the project, contact the Specifications Engineer.
Using a New or Modified Special Provision
Follow the Requirements for Preparing and Submitting Special Provisions if modifying a previously used SP or writing a new one.
Proprietary Products
Specifications using patented or proprietary (brand name) products or processes are generally discouraged; it is preferred to describe the product using generic, end-results-type language. However, it is sometimes necessary to call out a specific brand name, especially when using a new or experimental product:
If a range of proprietary products exists that will meet the needs of the project, list at least three acceptable alternatives, along with the phrase “or approved equal,” for example:
“Hydrants shall comply with AWWA Standard C502, have a three-nozzle arrangement, and be manufactured by Clow, Mueller, American Darling, or approved equal.”
If the needs of the project can be met by only one specific product, state the name of the product in the specifications. In this case, a Public Interest Finding (PIF) must be submitted to the Contracts and Specifications Bureau for approval. Refer to Section 1C-7 for more information.
Local Systems Projects
Follow the Requirements for Preparing and Submitting Special Provisions.
Back to top
120-4 Writing Specifications
Occasionally, designers must write their own specifications, either for use on an individual project or as a proposed revision to the Standard Specifications. This section provides guidelines to use when writing specifications.
A particular style and format is used for writing specifications. One convenient resource for writing specifications is the Standard Specifications. They demonstrate the preferred formatting and wording of specifications used at the Iowa DOT.
Method Specifications vs End-result Specifications
Method specifications describe step-by-step exactly how to fabricate, erect, and install materials to construct an end product (tell the contractor how to build it).
End-result specifications describe the requirements for an end product, and the contractor devises the steps needed to construct a product that complies with stated requirements (tell the contractor what is wanted and they will figure out how to build it).
The Five C’s
For specifications to be effective, they must be concise, clear, complete, correct, and consistent. These are referred to as “the Five C’s”.
Concise
Use simple words and try to keep sentences to 25 words or less. Try to limit paragraphs to five sentences or less. Limit each sentence to one thought and each paragraph to one topic.
Clear
Avoid words or sentences that can be interpreted in more than one way. For example, words like “accurate,” “clean,” “reasonable,” and “sufficient” can mean different things to different people.
Avoid using “and/or.” Instead of “A and/or B,” use “either A or B, or both.”
Avoid repeating requirements or providing reasons to back up a requirement.
Do not restate information found in the plans.
Complete
Use the five part format:
DESCRIPTION
A short and concise statement of the work required.
MATERIALS
A list of the materials required to complete the work.
CONSTRUCTION
A description of the requirements for completion and acceptance of the work.
METHOD OF MEASUREMENT
A description of the procedures used to measure the pay items. Include units of measurement, how items will be measured (plan quantity, placed, etc.), and measurement factors such as temperature, waste, spillage, etc.
BASIS OF PAYMENT
A definition of pay items needed to complete the work. Include incidental items.
Correct
Thoroughly research information to be sure that it is correct. Make sure references are correct and up-to-date.
Make sure spelling, grammar, and punctuation are correct.
Consistent
Be consistent with punctuation, grammar, word usage, format, referencing, and the use of abbreviations and numbers.
Abbreviations, Symbols, and Numbers
Article 1101.02 lists definitions for several abbreviations used in the Standard Specifications. When introducing an abbreviation that is not in Article 1101.02, spell it out first followed by the abbreviation in parentheses.
Example: Ensure the moisture content of sawed material treated with chromated copper arsenate (CCA) is no more than 20% prior to treatment.
Spell out all months and days of the week.
Do not use contractions, for example: isn’t, don’t, or aren’t.
Abbreviations to Avoid
Use “also known as” instead of “a.k.a.”
Use “for example” instead of “e.g.”
Use “and other things” or “and so forth” instead of “etc.”
Use “in other words” or “that is” instead of “i.e.”
Use “and” instead of “&”
Use “additional” instead of “addl.”
Use “amount” instead of “amt.”
Use “approximately” instead of “approx.”
Use “average” instead of “avg.”
Use “each” instead of “ea.”
Use “including” instead of “incl.”
Use “manufacturer” instead of “mfr.”
Use “quantity” instead of “qty.”
Use “section” instead of “sec.”
Use “standard” instead of “std.”
Allowable Abbreviations
“Iowa DOT” (but not “IDOT”) for “Iowa Department of Transportation.”
“No.” for “number” when referring to a particular item, for example Gradation No. 32 in the Aggregate Gradation Table, or the No. 200 sieve, or insulated No. 22 AWG wire.
In the names of businesses:
Use “Co.” for “Company.”
Use “Corp.” for “Corporation.”
Use “Inc.” for “Incorporated.”
Use “Ltd.” for “Limited.”
Symbols
Use “%” after a number. Spell out “percent” in other situations.
Use “°” for temperature. Spell “degrees” out for an angle.
Use “±” instead of “plus or minus.”
Use “less than” instead of “<”
Numbers
Spell out ordinals: first, second, third, fourth; not 1st, 2nd, 3rd, 4th.
Use commas in numerical values of five or more digits.
Examples: 1500 feet, 12,000 gallons.
Always use numerals when designating a technical measurement, including hours and days.
Examples: 3 inches, 12 feet, 5 gallons, 2 hours, 7 calendar days.
Spell out the number when designating a quantity, unless the number is greater than ten.
Examples: six copies of the shop drawings, two passes with a roller, 50 repetitions.
Fractions and Decimals
Fractions may be used with English units, but never with metric units.
Examples: a 1/4 inch bolt, a 1/2 mile detour.
When using a whole number with a fraction, place a space between the number and the fraction.
Examples: 1 1/4 inches, 3 1/2 working days.
Decimals may be used with English or metric units. For decimal values between 0 and 1, place a 0 before the decimal point.
Examples: 0.8 kg, 0.15 inches, 0.12 gallons.
Referencing
Do not use gender references.
Instead of “his” or “he” use “they,” “their,” “the Contractor,” or reword the sentence.
Use “quality” instead of “workmanship.”
Use “flaggers” instead of “flagmen.”
Documents
The Standard Specifications are referenced in the following manner:
Division 26 of the Standard Specifications
Section 2602 of the Standard Specifications
Article 2602.07 of the Standard Specifications
Article 2602.07, F, of the Standard Specifications
Article 2602.07, F, 1, of the Standard Specifications
When referencing a Developmental Specification, Special Provision, or Supplemental Specification, use only the title. Do not include the number.
When referencing a Materials I.M., use only the number. Do not include the title.
ASTM references are shown in this format: ASTM C 103.
AASHTO references are shown in this format:
AASHTO M 86/M 86M if the standard is available in both English and metric units.
AASHTO M 198 if the standard is available in English units only.
Entities
The following items are defined in the Standard Specifications and must be capitalized as shown:
Contracting Authority (not Owner).
Engineer (not Owner or Inspector).
Contractor (not Prime or subcontractor).
Professional Engineer licensed in the State of Iowa (when referencing a licensed engineer).
Typically, references are not made to the plans; instead, references are made to the contract documents, of which the plans are a part.
Example: Refer to the contract documents for details of over-excavation of rock and wet or soft foundations.
Back to topWording
Stating a Contractor’s Responsibility
A contractor’s responsibilities are described using the active voice and imperative mood. The subject is understood to be the contractor, so the subject does not need to be stated.
Example: Mark subdrain outlets with steel posts. Use steel posts meeting the requirements of Article 4154.09. Drive the posts 3 feet into the ground.
Stating a Contracting Authority or an Engineer’s Responsibility
A contracting authority’s or engineer’s responsibilities are described using the indicative mood with either an active or passive voice. Use the active voice if the subject is doing the action. Use the passive voice if the subject is the receiver of the action or the subject is not stated.
Examples:
Active: The Contracting Authority will supply all permanent signs on the project.
The Engineer will compute the volume of flowable mortar furnished and placed.
Passive: Placing backfill for construction of the shoulder area will be paid for separately.
Payment will be at the contract unit price per cubic yard for the quantity of backfill material furnished.
Stating the Method of Measurement
When payment is by plan quantity, state the following: “Measurement for bid item description, in units, will be the quantity shown in the contract documents.”
Example: Measurement for Combined Concrete Sidewalk and Retaining Wall, in cubic yards, will be the quantity shown in the contract documents.
When payment is by measured quantity, state the following: “Measurement for bid item description will be in units.” Accuracy of measurement can also be specified.
Example: Measurement for Combined Concrete Sidewalk and Retaining Wall will be in cubic yards.
Stating the Basis of Payment
- State the following: “Payment for bid item description will be at the contract unit price per unit.”
Example: Payment for Combined Concrete Sidewalk and Retaining Wall will be at the contract unit price per cubic yard.
- Do not include the sentence, “This payment shall be full compensation for all materials, labor, and equipment necessary to complete the work.” This is covered by Division 11 of the Specifications. However, items included in the payment can be stated for clarification. Something similar to the following statement (for the example above) can be included:
Payment is full compensation for:
- Excavation and foundation preparation,
- Furnishing and placing concrete and reinforcing steel,
- Joint material,
- Subdrain,
- Porous backfill material,
- Suitable backfill material,
- Finishing disturbed areas, and
- Shoring as necessary.