Content Information
On this page...
The Title Sheet has the following project, plan, and design information:
Index of Sheets,
Design Data,
Type of Work,
Project Location,
Project Number,
Project Identification Number (PIN),
R.O.W. Project Number,
County,
Design Team,
Revision Block (if needed),
Primary Signature Block,
Index of Seals,
Total number of sheets within the plan,
Iowa One Call
Letting Date, and
Value Engineering remarks.
These items will vary depending on the type of project.
Back to topIndex of Sheets
The Index of Sheets provides a listing of all the sheets included in a project. Section 1F-1 explains the numbering system to be used. U sheets may contain several groups of details, e.g. modified 500 series details, modified standard road plans, etc. When listing these in the Index of Sheets, group these together.
Back to topDesign Traffic Data
The Field Exam Engineer obtains Design Traffic Data from the Systems Planning Bureau.
Back to topType of Work
This is a statement that describes the work, for example HMA RESURFACING WITH MILLING, or PCC PAVEMENT - NEW. This statement is ties the project to a work type code. The project type of work must exactly match the work type in MasterWorks.
Back to topProject Location
This provides a brief statement of the project location. This must exactly match the project description in MasterWorks.
Back to topProject Location Map and Scale
The Title Sheet shows a map of the project location along with a scale. Include a small Iowa state map with the county or counties involved marked, see Figure 1.
Project Number and Project Identification Numbers (PINs)
These numbers must exactly match the project numbers in MasterWorks.
Back to topR.O.W. Project Number
This number must exactly match the ROW numbers in MasterWorks.
Back to topCounty
If the project is in more than one county, the county in which the project begins is listed first.
Back to topDesign Team (Contacts)
The design contacts should be listed at the bottom of the sheet in the following format:
Section Leader’s last name\Lead Designer’s last name
or
DOT contact’s last name\Consultant company name
Back to topRevision Block
Include a revision block for revisions. Refer to Section 1E-3 for plan revisions.
Back to topPrimary Signature Block
The Primary Signature Block should include the name and seal of the engineer who is overall in charge of the project’s design. See Section 1E-1 for information regarding signature blocks.
Back to topIndex of Seals
Project plans often need several engineers’ signatures. The index of seals lists the names of those engineers, the types of signature blocks, and the first pages on which their signature blocks appear.
Provide a space after the name of the engineer who is in overall charge of the project’s design for revisions. See Section 1E-1 for more information regarding signature blocks.
Back to topTotal
Tally the number of sheets in the plan.
Back to topLetting Date
Include the letting date for the plan.
Back to topValue Engineering Remarks
A box should be provided referring to the Specifications, similar to Figure 2.
Back to topIowa One Call
Provide the Iowa One Call number on the Title Sheet.
Back to topSample Title Sheet
Plan Quality Checklist
- Does the sheet include the labeled items as shown in the sample sheet, and are they accurate?
- Do the project description, work type, and project number match what is in MasterWorks?
- Is the letting date correct?
- Seals:
- Is an Index of Seals included if multiple seals are required?
- Are all engineers listed and page numbers correct?
- Are all sheets sealed by a licensed professional?
- Do all seals within the plans have a signature?
- Are all sheets accounted for on the index?
- Is the traffic information correct?