Plans occasionally require a few revisions after field crews have had a chance to review them. Tabulation
111-23 is used to keep track of these revisions. This tabulation is to include all changes and corrections to the original plans. A short description of each change and a reason for the change should be included. In addition, the revision date should be shown on the sheets that have been revised.
Tabulation 111-23 is placed on a sheet called the Plan Revision Sheet. This sheet is placed after the Title and Location Map Sheets and will typically be the last of the A sheets. The Sample Plan Revision Sheet provides an example.
Section 1E-3 provides more information regarding the procedures used to make revisions to final project plans.