Article 2601.05, A, 13 of the Standard Specifications provides information regarding the Mobilization for Watering bid item. Projects identified as erosion control or landscaping should not include this bid item.
Quantities of Mobilization for Watering on a project are as follows:
3 Mobilizations: If the project includes Special Ditch Control, Turf Reinforcement Mat, Slope Protection, and/or Transition Mat.
5 Mobilizations: If the project includes Sodding.